3.5 General Review and Site Records
Key Takeaways
Division C Article 1.2.2.1. uses the general review table and special rules to determine when an architect, professional engineer or both must be retained.
Article 1.3.2.1. requires conspicuous permit posting during permitted construction or demolition. Article 1.3.2.2. defines the construction records to maintain on site.
Under BCA s. 8(12), a material change to the basis of a permit requires notification, filing details and Chief Building Official authorization.
Under Article 1.3.6.1., a local instrument under s. 7(1)(g) lets the Chief Building Official require as-constructed plans from those responsible for construction.
Articles 1.3.1.6. and 1.3.1.7. govern separate disclosure duties for prescribed permit information.
Professional general review and the permit record
A project can have a general review by a design professional and statutory inspections by building officials. Under Division C Article 1.2.2.1., the person intending to construct or have the building constructed arranges the required general review by an architect, professional engineer or both. The reviewer works within applicable professional standards and assesses whether construction generally conforms to the documents on which the permit or an authorized change is based. The architect or engineer sends written reports to the chief building official (CBO) or registered code agency (RCA), as appropriate. The general review reports remain distinct from notices of readiness for inspection under the Building Code Act, 1992 (BCA).
To decide who must review, locate the project's major occupancy and building description in Table 1.2.2.1. Read the table notes on the scope of architecture and engineering. An assembly-only building corresponds to the row for an architect and professional engineer. An industrial-only building with no subsidiary occupancy that exceeds the table's height or gross-area threshold corresponds to the row for an architect or professional engineer, subject to the professional practice limits in the notes. Separate sentences impose professional review for specified activities such as underpinning or construction of a tent's supporting framing and anchorage when the tent exceeds 225 m². Article 1.2.2.2. confines general review associated with an architect's design or services to an architect and that associated with a professional engineer's design or services to a professional engineer. Demolition has a separate trigger in Article 1.2.2.3. Compendium, Division C Part 1
Which documents belong on site?
| Requirement | Responsible party | What to keep or post |
|---|---|---|
| Permit posting, 1.3.2.1. | Person to whom the permit was issued | The permit or a copy posted conspicuously on the property throughout the construction or demolition. |
| Drawings and specifications, 1.3.2.2. | Person in charge of construction | At least one certified copy of the submitted drawings and specifications used for the construction application, with authorized changes. |
| Basis for special approval, 1.3.2.2. | Person in charge of construction | Copies of authorizations from the Building Materials Evaluation Commission and Minister's rulings under s. 29(1)(a) or (c) where the permit was issued on that basis. |
| As-constructed plans, 1.3.6.1. | Persons responsible for construction | Plans showing the whole building, a part or a system when required by the CBO under an applicable local instrument made under s. 7(1)(g). |
For drawing certification, Article 1.3.2.2. identifies the CBO or a person designated by the CBO. A copy held by a designer somewhere off site does not meet the requirement for a certified copy to be maintained on site. Posting the permit and keeping the approved technical record are distinct responsibilities.
A material change comes before record drawings
Suppose the design team moves an exterior exit and increases a beam span after issuance. If it materially changes the basis of the permit, s. 8(12) requires notice to the CBO, filing the change details with the CBO and obtaining authorization before making it. Section 8(13) ties the work to the approved record and its authorized changes. Under s. 8(14), a change certificate containing prescribed information limits refusal on Code-compliance grounds for the certified construction. The request and authorization process still applies. At completion, any required as-constructed plans describe what was built. They do not authorize an earlier deviation.
The CBO or RCA may refer plans, drawings, specifications or general review reports to the relevant professional association on reasonable grounds under s. 8(9) to determine whether the professional statute was contravened. Under s. 8(9.1), the CBO must refer the described documents and information on a request from the Association of Professional Engineers of Ontario or the Ontario Association of Architects for that purpose. Compare discretionary referral with the mandatory response to a request. Building Code Act, 1992, s. 8
Permit reporting to external recipients
Article 1.3.1.6. prescribes information to Tarion Warranty Corporation under s. 8(8.1). For covered Group C construction, the CBO sends the permit date and identifier plus application form information excluding schedules and attachments. Check the exclusions, including boarding, lodging or rooming houses, buildings containing hotels, and information relating to the extension or material alteration or repair of an existing building.
Article 1.3.1.7. covers specified light floor or roof systems in buildings with permits issued after July 1, 2022, excluding a house with or without a secondary unit. The CBO sends permit identifiers and dates, building address and floor or roof system description to the fire chief or to the municipal clerk where there is no fire department. Both articles specify 45 days after issuance and exclude Saturdays, holidays and other days the authority's office is closed for public business. A project may meet one reporting rule and fall outside the other. Compendium, Division C Part 1
A permitted assembly-only building is under construction. Who must provide general review under the assembly-only row of Division C Table 1.2.2.1.?
An architect and a professional engineer, within their respective practice areas.
Any two qualified building inspectors.
A designer qualified for houses without a professional designation.
The installer of any proprietary building system.
The permit holder posts the permit conspicuously. The person in charge keeps the only certified permit drawings in an off-site office. Which further step does Article 1.3.2.2. require?
Keep the certified set at the office and post an ordinary copy of the drawings.
Give the inspector an off-site address for the certified set with changes.
Keep an ordinary set on site and send the only certified copy back to the CBO.
Keep a certified set of the submitted documents and authorized changes on site.
A relocation of an exit is a material change to the plans on which the permit was issued. What must happen before the change is made?
Show the change only in the final as-constructed plans.
Notify the CBO, file details with the CBO and obtain authorization.
Obtain a revised warranty report from Tarion.
Notify the owner and proceed without filing.
A municipality has made a building by-law under BCA s. 7(1)(g). For a completed project, the CBO asks for as-constructed plans of only one building system. Does Article 1.3.6.1. allow the limited scope?
No. The CBO can require plans only if all building systems are included.
No. The CBO can require plans only when the initial work was unapproved.
Yes. The CBO can require plans for a whole building, part or system.
Yes. The CBO can require plans for one system only after a stop-work order.