4.3 Compliance, Covering and Stop-Work Orders
Key Takeaways
An inspector can issue a section 12 compliance order upon finding a contravention of the Act or Code.
An inspector can prohibit covering pending inspection. A section 13(6) uncovering order comes from the CBO or appropriate RCA and requires reason to believe the concealed work is noncompliant plus a listed trigger.
Section 14(1) allows the CBO or appropriate RCA to stop all or part of construction or demolition after a section 12 or 13 order was not complied with in time.
The stop-work order is effective on posting. Section 14(4) allows work necessary to carry out the underlying section 12 or 13 order.
Service requirements depend on the order. An order to comply or not to cover may be posted, while a stop-work order must be posted.
Identify the problem before selecting the order
Sections 12, 13 and 14 of the Building Code Act, 1992 (BCA) address different enforcement problems. Read the issuer, factual threshold, service and effect separately. A construction project can have multiple orders addressing different work.
| Problem | Rule and statutory actor |
|---|---|
| Inspector finds a contravention of the Act or Code | Inspector can order compliance under s. 12(2). |
| Part of the building is still exposed and inspection is pending | Inspector can prohibit covering or enclosing under s. 13(1). |
| Part is concealed and there is reason to believe the work is noncompliant | Chief building official (CBO) or registered code agency (RCA), as applicable, checks the additional conditions in s. 13(6). |
| A section 12 or 13 order remains uncomplied with after its time limit, or a reasonable time if no limit was specified | CBO or RCA, as applicable, can stop all or part of construction or demolition under s. 14(1). |
Compliance orders and service
Under s. 12(1) an inspector may enter at a reasonable time without a warrant to inspect compliance with the Act, Code or an order, subject to dwelling protections in s. 16. Where the inspector finds a contravention, s. 12(2) permits an order directing compliance immediately or within the time specified. Serve the order on the person believed to be contravening. The form must identify the nature and location of the problem and the compliance required. A site with an unpermitted addition can therefore get an order identifying that scope of work and the compliance needed. Under Division C Article 1.3.5.5. use the form approved by the Minister.
Section 12 permits public site posting, other public availability and land registry registration. Those steps are distinct from required service. Where a copy was made publicly available, the statute requires an indication when the requirements have been satisfied. Where the order was registered, a later acquirer is deemed served on the original service day and the CBO registers a discharge certificate on satisfaction. Sections 13 and 14 use similar registration and resolution mechanisms. Section 27 permits personal, specified email or registered-mail service. Section 20 protects the visibility and presence of posted orders. Building Code Act, 1992, ss. 12–14, 20 and 27
Covering and uncovering
An inspector can order that a part remain exposed pending inspection under s. 13(1). The order is served on the permit holder, if any, and other affected persons the inspector identifies. After the recipient gives notice of readiness under s. 13(4), inspection must be made within a reasonable time. Section 27 service rules do not apply to that readiness notice.
For an uncovering order under s. 13(6), the CBO or RCA must have reason to believe the covered or enclosed part was constructed in contravention of the Act or Code. At least one additional condition must also apply:
- The work was covered contrary to an order under s. 13(1).
- The required local notice was not given, or the required s. 10.2 notice was not received.
- The part was covered before the prescribed inspection period following the s. 10.2 notice elapsed.
- Following a required local notice, the specified local inspection period or, if none was specified, a reasonable time had not elapsed.
- The part was constructed without a permit.
The order directs the persons responsible for the construction to uncover the part at their expense for inspection. If a contractor covers framing without notice and credible evidence suggests required bracing was omitted, identify both the belief and the notice facts. Skipping the notice alone does not establish the full two-part trigger.
Escalation to stop work
A missed deadline under a prior s. 12 or 13 order permits escalation under s. 14(1). The CBO or RCA can order all or only part of construction or demolition to cease. Under ss. 14(2) and (3), serve the affected persons identified by the issuer and post a copy at the site where the public can see it. Posting makes the order effective. Under s. 14(4) only work necessary to carry out the underlying s. 12 or 13 order may continue within the stopped scope. Match the scope of the order to the work in the question.
If an RCA is involved, distinguish the agency’s appointment and the authorized signer. Division C Article 3.7.4.4. specifies different qualification categories for signing s. 13(6) or 14(1) orders and for s. 12(2) or 13(1) orders. Subsections 14(5)–(7), on referral of an RCA stop-work order, are excluded from the published General Legal/Process syllabus. Failure to comply can lead to prosecution under s. 36. Under s. 38 the CBO may also apply to the Superior Court of Justice for a compliance order when the statutory conditions apply. Compendium, Division C Part 3 · General Legal/Process syllabus
An inspector finds work underway on an addition that requires a permit. No permit was issued and no order is yet outstanding. Which order can the inspector issue for the contravention?
An order under s. 14(1) to stop construction
An order under s. 12(2) directing compliance
An emergency order under s. 15.10
A court order under s. 38
Framing was concealed before a required s. 10.2 notice was received. Photos give the CBO reason to believe required bracing was omitted. Which action is available under s. 13(6)?
The inspector orders a change in major occupancy.
The CBO issues an uncovering order only after a prosecution.
The tenant orders reconstruction at the municipality’s expense.
The CBO may order the persons responsible for construction to uncover the part at their expense.
A CBO serves affected persons with a valid stop-work order in the morning and posts a copy on the site at noon. When does the order take effect under s. 14(3)?
At noon when posted
When the first person was served in the morning
At the end of the next business day
When it is registered on title
The CBO stops work on a specified part after a section 12 order to reinforce a beam is not complied with. Which work may continue within the stopped part under s. 14(4)?
Installing unrelated finishes
Any work already listed in the original permit
Work necessary to carry out the section 12 reinforcement order
Any work approved by the owner’s insurer