4.5 Sewage Maintenance Inspection Programs
Key Takeaways
Under s. 10.1, operating or maintaining a sewage system must comply with the Act and Code. A maintenance program checks ongoing compliance.
Mandatory programs apply to specified Lake Simcoe areas and to specified source protection areas facing a significant drinking water threat.
Under Article 1.10.2.4., the applicable initial trigger varies, and the recurring inspection interval is five years after the most recent inspection.
The principal authority can accept a compliant certificate as an alternative to its inspection. The signer must meet the Code qualifications and avoid a conflict of interest.
Section 15.10.1 provides reasonable-time maintenance inspection entry subject to s. 16 and authorizes an inspector’s compliance order.
Start with ongoing operation and maintenance
Section 10.1 of the Building Code Act, 1992 (BCA) requires a sewage system to be operated and maintained in accordance with the Act and Code. Division B Section 8.9 contains sewage operating and maintenance requirements. A maintenance inspection takes place under a program for existing systems, so it serves a different purpose from a readiness or pre-backfill inspection during installation.
Identify the program and the area
| Route | Authority and purpose |
|---|---|
| Discretionary local program | A principal authority establishes a program under s. 7(1)(b.1), subject to the regulations under s. 34(2.1). Division C Subsection 1.10.1. governs sewage systems throughout the affected area of that program. |
| Mandatory program | Division C Subsection 1.10.2. establishes the program under s. 34(2.2). The principal authority with jurisdiction administers inspections for its area. A local instrument can govern the program subject to the regulation. |
For the mandatory route, first check Article 1.10.2.3. A sewage system located wholly or partly in the specified area is within the inspection rule. Lake Simcoe coverage includes the prescribed 100 m upland shoreline strip, the identified parts of that strip and prescribed 100 m strips associated with certain watershed rivers, streams, connected water bodies and other lakes or ponds over eight hectares. Check the descriptions and how the distance is measured before inferring coverage from the name of the municipality. The source protection route requires both the specified vulnerable and source protection area facts and the identification of a significant drinking water threat for the relevant activity in the applicable approved assessment report or source protection plan. Compendium, Division C Part 1
Choose the correct five-year starting point
Under Article 1.10.2.4., the initial Lake Simcoe inspection is due no later than five years after construction under the applicable clause. For the significant drinking water threat route, compare the date of construction with the applicable publication date. An older system generally uses the Code-specified publication date for the initial deadline, while a system constructed on or after that date uses construction. For newly identified areas, check the specified approval date of the updated assessment report or publication date of the approved amended or updated plan, as applicable. Thereafter, count five years from the most recent inspection. For example, if a covered system’s most recent required maintenance inspection was June 12, 2025, its next five-year inspection date is June 12, 2030. The system’s original construction date does not restart the recurring period.
For a source protection date example, if a system was already installed before the applicable notice of approval was published on May 8, 2026, the initial deadline under Sentence 1.10.2.4.(3) is May 8, 2031. An installation after that publication instead uses its own date of construction under the same sentence.
Certificate, entry and orders
Under Articles 1.10.1.3. and 1.10.2.5., the principal authority may accept an approved-form certificate from the property owner as an alternative to conducting the required inspection. A permitted signer must have inspected that particular system and have reasonable grounds for finding compliance with the relevant program standards as of signing. Subject to the conflict rule, the signer can be a designer registered under Article 3.2.4.2. in the class in Column 1 of Item 10 of Table 3.5.2.1., a person registered under Article 3.3.3.2., an architect or a professional engineer. For example, a permitted class of registrant or a professional engineer still cannot sign where they participated in design or construction of the system. Check the 180-day former employment rule and the professional or financial interest and principal authority role restrictions. Acceptance is an option for the authority rather than a right for the holder.
Under s. 15.10.1, an inspector can enter land and buildings at a reasonable time for a maintenance inspection subject to s. 16. If the inspector finds a contravention, they may order compliance immediately or in the specified time. The order specifies the nature and location of the contravention and the required response, and is served on the person believed to be contravening. Posting, public availability and registration are available under their respective conditions. The separate building condition evaluation provisions in ss. 15.10.2–15.10.6 apply to their prescribed settings. For example, s. 15.10.3 permits an evaluation-related compliance order in a qualifying case. Division C Section 1.10 supplies sewage maintenance program rules, so use its actual scope when choosing the source. Building Code Act, 1992, ss. 10.1 and 15.10.1–15.10.6 · Compendium, Division C Part 1
An existing sewage system is partly in an area prescribed by Article 1.10.2.3. Which regime governs the recurring inspection requirement?
The construction-stage five-day notice only
The mandatory sewage maintenance inspection program
An optional local program in every case
The emergency order regime
Under the mandatory program the most recent inspection of a covered sewage system was on June 12, 2025. What date marks five years after that inspection?
June 12, 2027
June 12, 2029
June 12, 2031
June 12, 2030
A professional engineer inspected a system and is otherwise eligible to sign an alternative certificate. The engineer also designed part of the system. Can the engineer sign?
No. Participation in design is a specified conflict of interest.
Yes, if the owner agrees.
Yes, because the professional designation supersedes the conflict rule.
Yes, if the inspection was completed before noon.
An inspector finds a Code contravention during a sewage maintenance inspection. Which provision specifically authorizes a compliance order in that setting?
BCA s. 4(5)
BCA s. 10(2)
BCA s. 15.10.1(2)
Division C Article 1.3.1.3.