3.2 Complete Applications and Prescribed Review Periods

Key Takeaways

  • The prescribed s. 8 review period generally begins the day after a submission meeting Division C Sentence 1.3.1.3.(5), subject to the separate sewage-system timing rule.

  • Sentence 1.3.1.3.(6) requires written notice within two countable days for the specified determination to take the application outside the ordinary decision deadline.

  • Read Table 1.3.1.3. by building class. An application for different building classes uses the longer applicable period under Sentence (2).

  • For a separate sewage authority meeting Sentence 1.3.1.3.(9), begin on the day after the later of the qualifying building application and issuance of the sewage permit.

  • When the prescribed review period applies, a refusal must give all reasons in writing within that period.

Last updated: November 2026

Intake, timing and decision are separate steps

For a Building Code Act, 1992 (BCA) s. 8 construction or demolition permit, Division C Article 1.3.1.2. requires the owner or authorized agent to use the Minister-approved application. For that article, owner includes the registered owner, a lessee and a mortgagee in possession. Apply the article’s own definition. The 2026 Minister-approved form asks for Schedule 1: Designer Information for each individual reviewing and taking responsibility for design activities, subject to the form’s professional exceptions. Schedule 2: Sewage System Installer Information applies when the application is to construct on site, install or repair a sewage system. Ontario permit form effective February 16, 2026

What starts the prescribed decision period?

A submission qualifying under Sentence 1.3.1.3.(5) includes the correct applicant and form, completed applicable fields, all required schedules, and the fees due at submission. The applicant declares in writing that those requirements are met, that prescribed plans, specifications and applicable-law information accompany the application, and that the proposal will not contravene applicable law. The list of documents may depend on the relevant local instrument under BCA s. 7(1)(b).

Sentence (6) addresses an application that meets the requirements in Sentence (5), for example a submission with the required declarations. The chief building official (CBO) may determine that prescribed plans or applicable-law documentation are actually missing or that the proposal actually contravenes applicable law. The exception to the ordinary decision period applies if the CBO advises the applicant of that determination and gives the reasons in writing within two countable days. A missing required schedule or unpaid fee fails Sentence (5) on its own. Silence for two days does not turn a deficient submission into a qualifying one or grant a permit.

Read the table, then check timing adjustments

Table 1.3.1.3. itemCountable daysExamples and exclusions to check
110A house with no dwelling unit over another, except a retirement home. Also specified detached structures serving such a house up to 55 m² in building area, and regulated tents, signs and demountable stages or supports.
215Buildings described in Division A Clauses 1.3.3.3.(1)(a)–(c), excluding buildings in Items 1 and 4. Also farm buildings of at most 600 m² in building area.
320Buildings described in Division A Sentence 1.3.3.2.(1), excluding buildings in Items 1 and 4. Also farm buildings over 600 m² in building area and retirement homes.
430Post-disaster buildings and buildings subject to Division B Subsection 3.2.6. or any provision in Articles 3.2.8.3. through 3.2.8.8.

For a qualifying two-unit house with one unit above the other, first eliminate Item 1. If it meets the Part 9 conditions in Item 2 and no other item takes precedence, count 15 days. For two or more buildings in different table classes with different periods on the same application, use the longer period under Sentence (2). Sentence (3) also sets a longer-of test for the structures and systems named in Sentence (4), including a sewage system or standalone plumbing. Compare 10 days with the table period for the class of building the system or structure serves, if any.

Find day one

Ordinarily the period begins the day after a qualifying submission. Under Sentence (8), the table periods and the two-day notice period exclude Saturdays, holidays and other days when the principal authority’s offices are closed to public business. Assume a qualifying 10-day house application submitted Monday, May 4, 2026, with the office closed on weekends and Monday, May 18. May 5–8 are days 1–4. May 11–15 are days 5–9. After the weekend and holiday, Tuesday, May 19 is day 10.

Sentences (9) and (10) apply when a proposed building will be served by a sewage system for which construction is also proposed, and an authority listed in Sentence (9)(c) enforces the sewage rules under s. 3.1 or an agreement under s. 6.2. The period begins the day after the later of qualifying building application and issuance of the sewage permit. Suppose the building application qualifies on Monday, but the other authority issues the sewage permit on Thursday. Friday is the first countable day if the office is open and the day is not a holiday. Check responsibility on the relevant date because transfers can change which authority administers sewage permits.

End the clock with the decision and reasons

Under s. 8(2.2) and (2.3), read the Code’s timing requirement and the duty to give all refusal reasons together. Where Sentence 1.3.1.3.(1) applies, the CBO must issue the permit or refuse it and give every reason in writing within the period. An applicant disputing timing or the refusal-reasons duty may apply to the Building Code Commission under s. 24(1)(b). Disputes about technical sufficiency have their own route under s. 24(1)(a). Section 25(1) supplies a court appeal within 20 days after an appealable decision or order is made. A missed deadline alone does not authorize construction. Building Code Act, 1992, ss. 8, 24 and 25, Compendium, Division C Part 1

Loading diagram...
Selecting and Counting the Permit Review Period
Test Your Knowledge

An owner submits a qualifying application for a detached two-storey house with one dwelling unit. It is not a retirement home, and no timing exception applies. What is the prescribed review period?

A

5 business days

B

15 business days

C

10 business days

D

20 business days

Test Your Knowledge

An applicant leaves out a required schedule and does not pay the fee due at submission. Three countable days pass without a notice from the CBO. What has happened to the ordinary review clock?

A

It has not started because the application fails Sentence 1.3.1.3.(5).

B

It started on the third day because silence makes the application complete.

C

The absence of notice authorizes work to begin.

D

The CBO automatically refused the application after two days.

Test Your Knowledge

A qualifying building permit application is filed Monday. The property needs construction of a sewage system to serve the building. A board of health enforcing sewage rules under s. 3.1 issues the sewage permit on Thursday. Assuming Friday is countable, when is the first day of the building permit review period?

A

Monday

B

Tuesday

C

Thursday

D

Friday

Test Your Knowledge

One qualifying application includes a building in the 15-day class and a building in the 30-day class. Assume no other timing rule modifies the result. How long is the prescribed period?

A

15 countable days

B

30 countable days

C

45 countable days

D

23 countable days