3.4 Conditional Permits and Revocation

Key Takeaways

  • A conditional permit under s. 8(3) is discretionary and requires the applicable law checks, an opinion on unreasonable delay and a written risk agreement.

  • Division C Article 1.3.1.5. identifies required laws, narrow zoning exceptions and the obligation to mark the permit as conditional.

  • A conditional permit agreement may be registered under s. 8(5). The registered agreement and the statutory restoration and recovery rules are separate tools.

  • Section 8(10) lets the Chief Building Official revoke on one of six grounds, subject to s. 25.

  • The two inactivity grounds differ: no serious commencement after six months and substantial suspension or discontinuance for more than one year.

Last updated: November 2026

Authorize a construction stage while approvals remain

An ordinary application is decided under s. 8(2) of the Building Code Act, 1992 (BCA). Under s. 8(3) the chief building official (CBO) may instead authorize a stage of construction by a conditional permit when the following requirements are met:

  1. The proposal complies with the zoning and interim-control by-laws made under Planning Act ss. 34 and 38, subject to the Code's specific exemptions, and with the additional applicable laws set out for conditional permits.
  2. The CBO is of the opinion that withholding a conditional permit would unreasonably delay construction.
  3. The applicant and anyone else the CBO identifies enter into a written agreement with the applicable authority.

Division C Article 1.3.1.5. gives the additional list. Examples include specified transit permits, conservation authority requirements, heritage consents and residential condominium conversion confirmation. If a required conservation authority permit under a listed provision is still pending, a conditional permit cannot be used to bypass it. Review the exact Article list for the proposed work instead of importing every entry from the ordinary applicable-law list.

The Article also provides two narrow exceptions to the zoning and interim-control compliance requirement. One concerns minor variances authorized by a committee of adjustment that achieve full compliance when no objections were made in writing or in person at the hearing. The other applies where the construction is required to comply with specified fire-protection or unsafe-building orders. The other conditional permit requirements still apply. The permit must indicate its conditional nature. Compendium, Division C Part 1

Put the terms in writing

Under s. 8(3)(c), the written agreement covers the risk of starting, the time to obtain the required approvals and file plans and specifications for the complete building, and removal and restoration at the applicant's expense if approvals or plans are not supplied as agreed. The CBO can require other conditions, including security for removal and restoration. Under s. 8(3.1) the principal authority can delegate its agreement-making power to the CBO in writing with conditions or restrictions. When deciding, the CBO must consider how difficult it would be to restore the site if approvals never arrive under s. 8(4).

A foundation-stage scenario may distinguish three facts. Achieving the required zoning and other applicable law is a gate. Unreasonable delay is the CBO's assessment. A proposed deposit can meet a security condition if accepted, but it cannot establish compliance with the legal gates. If the CBO refuses a conditional permit under s. 8(3), s. 25(1) expressly excludes that refusal from its appeal route to the Superior Court of Justice.

Section 8(5) permits registration of the agreement against the land. This lets the authority enforce it against the registered owner and, subject to Ontario's land registration statutes, against a person who acquires an interest after registration. Registration is available as an enforcement measure. The Act does not require it as a condition of every conditional permit. Under s. 8(6) the CBO can cause removal and restoration if the work required by the agreement is not performed. It includes reasonable-time entry powers for this purpose, subject to the dwelling-entry protections in s. 16. In a municipality, the statute provides a priority lien for the amount spent. In unorganized territory the cost is a debt to the Crown and may be collected under the Provincial Land Tax Act, 2006 as if it were the tax. Building Code Act, 1992, s. 8(3)–(8)

Decide whether revocation is available

Section 8(10)Fact supporting possible revocation
(a)The permit was based on mistaken, false or incorrect information.
(b)Six months have passed after issuance and, in the CBO's opinion, the work has not seriously commenced.
(c)In the CBO's opinion, work has been substantially suspended or discontinued for more than one year.
(d)The permit was issued in error.
(e)The holder asks in writing for revocation.
(f)A term of the conditional permit agreement has not been complied with.

The word may and the phrase subject to section 25 both matter. Six months without a serious start can support a revocation decision under clause (b). It is distinct from the one-year test for a substantial stoppage under clause (c), which can apply after a serious start. Neither period by itself revokes a permit. For a permit issued in March 2025 on which work seriously commenced in May 2025 and then substantially stopped until August 2026, the roughly 15-month gap is longer than one year and fits clause (c) if the CBO takes that view. Test the Act's dates and who forms the required opinion before selecting the ground. Building Code Act, 1992, ss. 8(10) and 25

Test Your Knowledge

A required conservation authority permit under Division C Article 1.3.1.5. is still pending. The owner offers security and shows the project may otherwise be delayed. What result follows?

A

Security is a substitute for the conservation authority permit.

B

The building permit becomes effective when the deposit is received.

C

The CBO can waive the Code’s applicable-law condition if the foundations are the only stage requested.

D

The CBO cannot issue the conditional permit while that applicable requirement remains unmet.

Test Your Knowledge

Which statement about registration of a conditional permit agreement follows from BCA s. 8(5)?

A

The agreement may be registered against the land.

B

Registration is compulsory for every conditional permit.

C

The applicant may register the agreement only after removing the building.

D

Registration converts the conditional permit into an ordinary permit.

Test Your Knowledge

Work seriously commenced shortly after permit issuance. The CBO considers it substantially suspended for 15 months after that start. Which ground fits?

A

Section 8(10)(a), because delay makes the original information false.

B

Section 8(10)(c), because substantial suspension exceeded one year.

C

Section 8(10)(b), because this is the first six months before serious commencement.

D

Section 8(10)(e), even though the holder made no written request.

Test Your Knowledge

The CBO refuses only a conditional permit under s. 8(3), citing difficulty restoring the site. What does s. 25(1) say about its appeal route?

A

The statute requires an appeal within 20 days in every conditional-permit refusal.

B

The amount of security determines whether a s. 25(1) appeal is available.

C

The subsection expressly excludes a decision under s. 8(3) not to issue a conditional permit.

D

The subsection makes the permit issue automatically if there is no appeal.