7.5 Plumbing and Sewage System Definitions

Key Takeaways

  • Each Part ordinarily takes its italicized terms from Division A 1.4.1.2. and the Act. Part 7 specifically defines storey and Part 8 specifically defines soil.

  • The Act’s building definition includes structures with plumbing even at 10 m² or less, as well as plumbing outside a structure. Apply the permit requirement and any exemption separately.

  • A Code sewage system must meet its type, capacity and location requirements. Check the 10,000 L/day ceiling for each system and for the total on the lot when there are multiple systems.

  • The five countable days in Division C 1.3.5.3.(2) apply to the specified sewage construction notices.

Last updated: November 2026

Start with the definition for the Part being used

In Division B 7.1.1A.1., italicized terms ordinarily take their meanings from Division A 1.4.1.2. and the Building Code Act, 1992 (the Act). Sentence (2) defines storey for Part 7. It is the interval between successive floor levels or between a floor level and a roof. The floor levels include a mezzanine that contains plumbing fixtures. A mezzanine with a fixture can therefore affect the application of a Part 7 provision using that term. The general building-height classification uses its own definitions.

Plumbing termDivision A boundary
Building drainThe lowest horizontal piping, including a vertical offset, conducting sewage, clear-water waste or storm water by gravity to a building sewer.
Building sewerThe pipe connected to the building drain 1 m outside a wall, leading to a public sewer or private sewage disposal system.
Water service pipeA pipe on the property conveying potable water from a drinking water system or private supply to the inside of the building.
Water distribution systemPipes and associated components conveying potable water from the service pipe or the building’s point-of-entry treatment unit to outlets, fixtures, appliances and devices.

The Act’s s. 1(1) definition of building includes specified structures of more than 10 m², a structure of 10 m² or less containing plumbing, and plumbing outside a structure. For a 9 m² cabana with a sink, check s. 8 and applicable exemptions after identifying it as a building. For a separate outdoor sink and drain, check the scope of the outdoor plumbing independently. The shed exemption in Division C 1.3.1.1.(6) requires all its conditions, including no plumbing. A small floor area alone does not establish the result.

Identify Part 8 soil and the Code sewage system boundary

Article 8.1.1.2. follows the same convention for italicized terms, with its own definition of soil. Part 8 soil is naturally occurring, in-place unconsolidated mineral or organic material at the earth’s surface, at least 100 mm thick and capable of supporting plant growth. It includes material compacted or cemented by soil-forming processes. Displaced gravel dumps, mine spoils and similar deposits are excluded. A layer of imported fill does not become Part 8 soil merely because its depth and ability to support plants are similar.

Division A 1.4.1.2. defines sewage system for the Code. Match the system type, a design capacity of at most 10,000 L/day, a total of at most that capacity where more than one system is on the lot or parcel, and location wholly within the boundary of the lot or parcel containing the building or buildings served. The measure is design capacity, not the current volume used. For example, 5,500 + 4,500 = 10,000 L/day and satisfies the aggregate capacity limit if both are on the same lot. Two systems of 5,500 L/day each total 11,000 L/day and exceed it. If the work falls outside this definition, check the applicable sewage works approval rules under the Ontario Water Resources Act.

Under Division B 8.1.2.1., the five classes are Class 1 for the listed toilets and privies, Class 2 for a greywater system, Class 3 for a cesspool, Class 4 for a leaching bed system and Class 5 for a system using a holding tank to retain hauled sewage on site before collection. Greywater is domestic sanitary sewage from fixtures other than sanitary units. Classify the system before evaluating which other requirements govern.

Under Division C 1.3.5.3.(2), the five-day inspection window applies to the notices in 1.3.5.1.(2)(l) or (m). Apply the counting rules in 1.3.5.3. and the applicable inspector or agency assignment. This is a construction inspection timing rule. Existing-system maintenance inspections have their own Act and Code provisions.

For a site about to begin sewage construction, Clause (l) concerns readiness to construct the system and Clause (m) concerns substantial completion of its installation before backfilling. Clause (n) separately addresses substantial completion of plumbing outside a structure before backfilling. If work includes both features, identify each applicable notice and use its own period. The qualifying sewage notice initiates the five-countable-day period. Start the count the day after notice is given and exclude Saturdays, holidays and any other days the principal authority’s offices are closed to the public.

Primary references

2024 Compendium, Division B Part 7 · 2024 Compendium, Division B Part 8 · 2024 Compendium, Division A · 2024 Compendium, Division C · Building Code Act, 1992 · Ontario Water Resources Act

Test Your Knowledge

A mezzanine contains plumbing fixtures. For a Part 7 provision using the defined term storey, how is that mezzanine treated?

A

The level is ignored because mezzanines never count in Part 7.

B

It counts only if a Class 5 sewage system serves the building.

C

It counts only when connected directly to the roof.

D

It is included as a floor level under Part 7’s definition.

Test Your Knowledge

Which material qualifies as soil for the Part 8 definition, assuming the stated facts?

A

A 120 mm layer of in-place, naturally occurring unconsolidated surface material that can support plant growth.

B

A 200 mm displaced mine spoil deposit capable of supporting plant growth.

C

An 80 mm in-place, naturally occurring surface layer that supports plant growth.

D

A 150 mm layer in a gravel dump.

Test Your Knowledge

Two listed sewage system types are on the same lot as the buildings they serve. Their design capacities are 5,500 L/day and 4,500 L/day. Which statement is correct on the capacity facts?

A

Each is below 10,000 L/day but the aggregate necessarily exceeds that limit.

B

The 10,000 L/day aggregate equals the ceiling, so both individual and total capacities meet the limit.

C

Subtract the smaller capacity from the larger capacity to determine combined capacity.

D

The limit applies only to measured daily use and design capacity is irrelevant.

Test Your Knowledge

Which inspection has a deadline of five countable days under Division C 1.3.5.3.(2)?

A

Any inspection involving a building that happens to be served by a sewage system.

B

An inspection of every existing septic system following the five-year maintenance interval.

C

The construction site inspection after receipt of a notice under 1.3.5.1.(2)(l) or (m).

D

A plans review for an ordinary building permit.

Sections you finish are checked off in the contents.