3.3 Change of Use and Demolition Decisions

Key Takeaways

  • Section 10(1) can require a permit for a change in use that increases hazard even with no construction.

  • Check Division C Table 1.3.1.4. from previous major occupancy to proposed major occupancy, then check the additional triggers and exemptions in the article.

  • The applicable-law definition for a section 10 permit is in Division A Sentence 1.4.1.3.(2).

  • Under Division C Article 1.2.2.3., a demolition permit applicant retains a professional engineer when any of the listed conditions applies.

  • For demolition within Sentence 1.2.2.3.(1), include the structural characteristics and demolition method in the permit application.

Last updated: November 2026

Start with the action the owner proposes

Section 10(1) of the Building Code Act, 1992 (BCA) addresses a change to the use of a building or part of one. If the Code treats the change as an increase in hazard, a person needs a permit from the chief building official (CBO) before making or allowing that change. The trigger can apply when the project does not involve construction, such as an existing space proposed for use by the public in a new way. Section 8(1) governs construction and demolition. The two sections answer different questions about the same property.

Read the matrix and the independent triggers

Go to Division C Article 1.3.1.4. Read the original major occupancy across the columns in Table 1.3.1.4. and the proposed major occupancy down the rows. Check the intersection and the notes. The note attached to a negative entry limits it to a change involving the entire suite. In a scenario with only part of a suite, consult the table notes before using a negative result. The table points the reader to a separate check for the single residential suite being converted to additional suites.

Fact in the stemHow to apply Article 1.3.1.4.
A store of Group E becomes a seated restaurant of Group A, Division 2Find column E and row A-2. The table identifies a hazard increase. A change-of-use permit is required on these facts if no exemption applies.
A Group C suite becomes more than one Group C suiteCheck Clause (1)(b). The absence of a group change does not remove this separate trigger.
A Group A, Division 2 or 4 suite, or part of one, becomes a gaming premisesCheck Clause (1)(c).
A farm building or part of one moves to a major occupancy outside Group G, or into Group G, Division 1Check Clauses (1)(d) and (e). A transition within farm occupancies needs the exact designation.
A change creates a post-disaster building or retirement home, or the previous major occupancy cannot be determinedCheck Clauses (1)(f) to (h). For an unknown previous occupancy, do not guess a matrix column.

Under Sentence 1.3.1.4.(2), the s. 10 permit is not needed if the change will result from proposed construction for which a s. 8 permit has been issued. Merely applying under s. 8 does not satisfy the exemption. Construction and use still need to satisfy the applicable Code requirements. Sentence (3) exempts change of use in unorganized territory from the s. 10 permit. Compendium, Division C Part 1

When a s. 10 permit is required, s. 10(2) calls for issuance unless the proposed use would contravene the Act, Code or other applicable law, the application is incomplete or fees due are unpaid. Division A Sentence 1.4.1.3.(2) defines other applicable law for this decision as general or special Acts and their regulations and by-laws that prohibit the proposed use unless complied with. Use Sentence (1) for the separate s. 8 decision. Compendium, Division A Part 1

Demolition review and submissions

The Act defines demolish to include removal of a building or any material part. Removing a load-bearing wing of a commercial building can therefore require a s. 8 demolition permit. Check Division C Article 1.3.1.1. for exemptions, including farm-building demolition on a farm and work in unorganized territory. Determine whether the proposal is exempt before applying steps that are specifically duties of a demolition permit applicant.

For a nonexempt demolition, Article 1.2.2.3. requires the applicant to retain a professional engineer to undertake general review during demolition if any of these facts applies:

  • The building exceeds three storeys in building height or 600 m² in building area.
  • The structure contains pre-tensioned or post-tensioned members.
  • The demolition will extend below adjacent footings and occur within the angle of repose of the soil measured from the bottom of those footings.
  • Explosives or a laser will be used during demolition.

Under Division C Sentence 1.3.1.1.(3), a permit application in one of these cases describes the building's structural design characteristics and the proposed demolition method. Sentence (4) also requires occupants to vacate before demolition begins unless their safety is unaffected. A one-storey building of 480 m² with post-tensioned members still meets the professional review trigger. Height and area are only two possible ways to trigger it.

Check any separately applicable heritage or planning control. For example, Division A Sentence 1.4.1.3.(1) includes a municipal demolition consent in specified Ontario Heritage Act cases and addresses Planning Act s. 33 residential demolition control. The permits and approvals answer different statutory questions. Section 9 of the BCA is repealed. Section 11 governs occupancy or use of newly erected or installed buildings or parts and has separate completion rules. Building Code Act, 1992, ss. 1, 8–11, Compendium, Division C Part 1

Test Your Knowledge

A 250 m² shop of Group E will become a seated restaurant of Group A, Division 2. No construction is proposed and the property is inside a municipality. What is the permit route?

A

A change-of-use permit under s. 10 because Table 1.3.1.4. marks this transition as an increase in hazard.

B

A demolition permit under s. 8 because the lease is new.

C

A permit under repealed s. 9.

D

No permit because the business will use the same physical partitions.

Test Your Knowledge

Proposed construction will create a change in use that would otherwise require a s. 10 permit. A s. 8 application has been submitted, but the permit has not yet been issued. Is the application enough to invoke the construction exemption from the s. 10 permit?

A

Yes, as soon as the application form is signed.

B

Yes, if the use will involve the entire suite.

C

No. Sentence 1.3.1.4.(2) requires issuance of a s. 8 permit for the construction that will cause the change.

D

Yes, upon completion of either a planning review or a fee payment.

Test Your Knowledge

A nonexempt, one-storey 480 m² building will be demolished. Its structural members are post-tensioned. What does Division C require of the permit applicant?

A

Retain an engineer only for buildings over 600 m², and submit the demolition method.

B

Retain a professional engineer for general review. Describe the structural design and demolition method.

C

Retain a designer after demolition starts, and submit a copy of the site plan.

D

Retain an engineer for partial demolition only, and describe the structure.

Test Your Knowledge

Which test defines other applicable law for the CBO’s decision on a s. 10 change-of-use permit?

A

Only the construction and demolition list in Division A Sentence 1.4.1.3.(1).

B

Only municipal fee by-laws made under s. 7.

C

Only the construction-stage terms of a conditional permit agreement.

D

General or special Acts and regulations and by-laws under them that prohibit the proposed use unless complied with.