7.3 Radon and Building in Flood Plains
Key Takeaways
Article 3.1.1.5. names three Ontario areas and sets two annual-average indoor radon measurements. The Part 9 counterpart is 9.1.1.7.
Article 3.1.1.6. requires both resistance to anticipated vertical and horizontal hydrostatic pressure and measures preserving exits and means of egress during flooding.
When a conservation authority permission is required as applicable law, the Code’s floodproofing requirements and that permission each need to be addressed.
Use the actual construction stage and statutory conditions for inspection notices, covering orders and occupancy decisions.
Check the Part and then locate the site
For a new building, first use Division A Subsection 1.3.3. to identify which Division B provisions apply. The two Part 3 articles in this lesson are Articles 3.1.1.5. and 3.1.1.6. Part 9 contains corresponding provisions in 9.1.1.7. and 9.1.1.8. The permit reviewer needs the site and building facts before assigning the design rules.
Under 3.1.1.5., the specified areas are the City of Elliot Lake in the Territorial District of Algoma, the Township of Faraday in the County of Hastings, and the geographic Township of Hyman in the Territorial District of Sudbury. In those areas the building must be designed and constructed so the annual average concentration of radon-222 does not exceed 200 Bq/m³ of air, and the annual average concentration of its short-lived decay products does not exceed 0.02 working levels inside the building. These are separate limits, using different units. The King’s Printer PDF for the 2024 Code prints the Part 3 radon unit as Bq/m³. The ministry’s Part 3 HTML currently displays Bq/m² at that point. Use the PDF’s volumetric unit, which also appears in the parallel Part 9 rule.
Read the annual-average design requirements
Suppose a Part 3 project in Faraday demonstrates an annual average of 190 Bq/m³ of radon-222 but 0.025 working levels for the short-lived decay products. The first result is within its limit and the second exceeds its own limit. Both need to be addressed. An isolated measurement is also a different quantity from the annual average named in the article. The listed locations trigger this specific provision. Outside those locations, check other applicable soil-gas provisions and the applicable building Part. The list does not decide every soil-gas requirement for Ontario.
Assess structural resistance and egress on a flood plain
Under 3.1.1.6., design and construct a building on a flood plain in accordance with good engineering practice to withstand anticipated vertical and horizontal hydrostatic pressures. Incorporate floodproofing measures to preserve the integrity of its exits and means of egress during floods. Vertical pressure can act as uplift. Horizontal pressure can act laterally against a below-grade wall. In a plan review, read the structural evidence and the proposed exit arrangement separately. An analysis of wall pressure without an analysis addressing egress cannot establish compliance with both clauses.
Verify the external permission when it applies
Division A 1.4.1.3. includes the specified prohibition under s. 28 of the Conservation Authorities Act and relevant permits under ss. 28.1, 28.1.1 and 28.1.2. If that permission is required for a specific regulated activity and remains outstanding, the engineer’s demonstration of compliance with 3.1.1.6. does not satisfy the missing applicable-law requirement for an ordinary permit under Act s. 8(2)(a). Similarly, a granted external permission leaves the Code performance assessment to be completed. Use the applicable activity and approval in the question. A map designation alone does not prove every listed permit is required.
For example, a proposed Part 3 building is on a flood plain, and the file stipulates that an outstanding conservation authority permit is required. Resolving both directions of hydrostatic pressure and providing flood-resistant egress completes the stated technical portion of review. The chief building official (CBO) still needs the applicable-law requirement met to issue the ordinary permit. For specified Downtown Brampton lands, also check the separate occupancy rule in Division C 1.3.3.6.A., added through O. Reg. 119/26. That rule has its own coverage and exceptions.
Use the actual inspection and order provisions
Where Division C 1.3.5.1.(2)(f) applies, notify at substantial completion of the air-barrier system. Whether a particular detail triggers a stage notice depends on the work and applicable provision. If work has been concealed, Act s. 13(6) requires reason to believe it is noncompliant plus a listed circumstance before a CBO or registered code agency may order uncovering. At occupancy, use the requirements of the applicable authorization. The radon and flood-plain articles themselves state design and construction requirements.
On a project facing both hazards, record three separate findings.
- Site and scope — Identify the listed radon location, any applicable flood-plain designation and the governing Building Code Part.
- Radon evidence — Record how the design addresses each annual average. A soil-gas detail may require validation independently of the floodproofed exits.
- Flood-plain evidence — Check the pressure design, the protected egress and any required external permission. If new drawings revise the below-grade assembly to address uplift, check whether the change affects soil-gas protection and whether Act s. 8(12) requires approval of a material change. This keeps the design, notice and permit decisions tied to the work that will actually be built.
Primary references
2024 Compendium, Division B Part 3 · King’s Printer 2024 Compendium PDF, Division B Part 3 page 3 · 2024 Compendium, Division B Part 9 · 2024 Compendium, Division A · 2024 Compendium, Division C · Building Code Act, 1992 · O. Reg. 119/26
For a new Part 3 building in Faraday, which pair of annual-average indoor limits applies under 3.1.1.5.?
200 Bq/m³ of radon-222 and 0.02 working levels of its short-lived decay products.
0.02 Bq/m³ of radon-222 and 200 working levels of its short-lived decay products.
200 Bq/m³ of radon-222 with no limit on its short-lived decay products.
250 Bq/m³ of radon-222 and 0.20 working levels of its short-lived decay products.
A Part 3 flood-plain design addresses both vertical and horizontal hydrostatic pressure. Which further requirement does 3.1.1.6. specify?
The design must prohibit all below-grade building elements.
The design must consist entirely of prefabricated assemblies.
Floodproofing must preserve the integrity of exits and means of egress during flooding.
An applicable zoning by-law must require the building to be taller.
An ordinary permit application meets the flood-plain design requirements but an applicable conservation authority permission required for the proposed construction is outstanding. What must the CBO do?
Issue the ordinary permit because structural compliance controls the decision.
Withhold the ordinary permit while the applicable-law requirement remains unsatisfied.
Treat the engineer’s drawings as a conservation authority permit.
Obtain a Building Code Commission decision to waive the permission.
The CBO has reason to believe required air-barrier work is noncompliant and it was concealed before the required readiness notice was received. Which statutory order directly addresses inspection access to the concealed work?
An occupancy permit covering the completed work under Division C.
A written technical interpretation of the building code under Act s. 28.1.
An approval to vary the requirements of the local zoning by-law.
An order to uncover the work under Act s. 13(6).