6.1 Building Code Commission: Disputes, Hearings and Decisions

Key Takeaways

  • Section 24(1) defines three disputes. Identify who filed, who made the decision or owed the inspection, and whether the issue is technical sufficiency or a prescribed time frame.

  • The Commission hears an inspection time-frame dispute between the permit holder and the chief building official, agency or inspector about Act s. 10.2(2). It does not resolve delays of every kind.

  • The five-day hearing period applies to the two time-frame dispute classes. It starts the day after receipt of the application in the Commission-approved form and uses Ontario government office days, not the municipality’s permit calendar.

  • The Commission may substitute its technical opinion in a sufficiency dispute, but a time-frame order can require compliance with the governing subsection, not immediate permit approval.

Last updated: November 2026

First identify the dispute and its parties

The Building Code Commission (BCC) is continued under s. 23 of the Building Code Act, 1992 (the Act). The Lieutenant Governor in Council appoints its members and may designate a chair and one or more vice-chairs. Section 23(5) specifies a three-member quorum. Under s. 23(3), a deputy minister, a public servant employed under the specified part of the Public Service of Ontario Act, 2006, and a municipal employee are ineligible. Division C Article 2.2.1.4. adds the prescribed agency relationships: being registered as a code agency, being its officer, director, partner or employee, or being engaged by it to carry out statutory functions. Check those relationships, not merely whether a person has a technical qualification.

IssueStatutory parties and question
Technical sufficiency, s. 24(1)(a)A permit applicant, permit holder or order recipient disputes with the chief building official (CBO), registered code agency (RCA) or inspector whether the design or work sufficiently complies with the Code’s technical requirements.
Permit decision or reasons, s. 24(1)(b)A permit applicant disputes whether the CBO complied with s. 8(2.2) or (2.3). Check the qualifying application and prescribed deadline for deciding or giving the reasons for refusal.
Required construction-stage inspection, s. 24(1)(c)A permit holder disputes with the CBO, RCA or inspector whether s. 10.2(2) was met. Start with receipt of the required readiness notice and the applicable prescribed inspection period.

A party to the qualifying dispute may apply under s. 24(1.1). A homeowner asking general questions before applying for a permit is not necessarily a party to a dispute under this section. Likewise a permit holder cannot use s. 24(1)(c) to challenge every service delay; this route is tied to the required construction-stage inspection. The application fee under Division C Article 2.2.1.5. is $212 for 2025 and subsequent calendar years.

Distinguish a statutory hearing period from a municipal service period

Under s. 24(2) the Commission holds a hearing and gives the parties notice. Under s. 24(2.1) and Division C 2.2.1.3., a hearing under clause (b) or (c) is held not more than five countable days after the Commission receives an application for a hearing in its approved form. Counting begins the day after receipt and excludes Saturdays, holidays and all other days on which Ontario government offices are not open for business with the public. If the Commission receives the application in its approved form on Monday and government offices are open on ordinary weekdays, Tuesday is day 1, Friday is day 4 and the following Monday is day 5. This is neither the permit decision period under Division C 1.3.1.3. nor the inspection period under 1.3.5.3. A technical sufficiency dispute under clause (a) does not get this five-day period by virtue of its subject matter.

How the Commission decides

  • Technical dispute: Under s. 24(3), the Commission determines the dispute by order and may substitute its opinion for the CBO’s, agency’s or inspector’s on the technical question.
  • Time-frame dispute: Under s. 24(3.1), the Commission determines the dispute by order and may require the relevant actor to comply with the applicable subsection. It does not turn a missed deadline into an automatically approved permit.
  • Decision and evidence: The decision is final under s. 24(4). Under (5), members hearing the case cannot investigate or consider its subject beforehand or communicate about it without giving all parties notice and an opportunity to participate. Under (6), they may obtain independent legal or technical advice, but disclose the nature of the advice so the parties can make submissions. Under (7), findings of fact rest exclusively on admissible evidence or matters that may be noticed under ss. 15 and 16 of the Statutory Powers Procedure Act. Under (10), a person who produced an item in evidence can request its return within a reasonable time after final determination.
  • Syllabus limits: Act ss. 24(8) and (9) and Division C Articles 2.2.1.1. and 2.2.1.2. are excluded. Article 2.2.1.3. remains in scope even though it cross-references 2.2.1.2.

Separate issues in a mixed refusal

Suppose a CBO issues a refusal identifying two distinct concerns: a proposed fire separation that the applicant says meets the Building Code as an alternative solution, and a separate zoning setback that the applicant says does not apply. The first is a technical sufficiency issue under s. 24(1)(a). The Commission cannot overturn the zoning requirement under that clause; a permit decision on applicable-law grounds raises a distinct issue under the statutory court route. A fee amount dispute likewise does not fit any of the three Commission categories. Refusal to issue a conditional permit under s. 8(3) does not itself fall into those categories and is expressly excluded from the s. 25(1) appeal. Always isolate the question the decision-maker is being asked to answer.

Primary references: Building Code Act, 1992, ss. 23–25 · 2024 Building Code Compendium, Division C Part 2 · Commission procedure handbook · General Legal/Process syllabus

Test Your Knowledge

An ordinary permit refusal cites the absence of a required conservation authority approval and a disagreement about whether an alternative fire separation meets the technical requirements of the Building Code. Which issue may the Commission decide under s. 24(1)(a)?

A

Whether omitting the conservation authority approval was permissible under applicable law.

B

Whether the proposed alternative meets the Code’s technical fire-separation requirements.

C

Whether the municipality set a reasonable fee for reviewing the conservation approval.

D

Whether the CBO met the deadline for giving reasons for refusal under s. 8(2.3).

Test Your Knowledge

The Commission receives a hearing application in its approved form on Monday for an Act s. 24(1)(b) permit time-frame dispute. Ontario government offices are open on the ordinary weekdays and closed on the weekend, with no holidays. When is the latest hearing day under 2.2.1.3.?

A

Thursday of the same week.

B

Friday of the same week.

C

Tuesday of the following week.

D

Monday of the following week.

Test Your Knowledge

A permit holder says the appointed RCA failed to carry out a required construction-stage inspection within the prescribed period after receiving the required notice. Which provision applies to this dispute?

A

Act s. 24(1)(c), with a possible Commission order requiring compliance with s. 10.2(2).

B

Act s. 24(1)(b), because only the applicant can complain about an inspection delay.

C

Act s. 24(1)(a), because every inspection timeline is a question of technical sufficiency.

D

No s. 24 provision, because the Commission cannot hear disputes involving an RCA.

Test Your Knowledge

During a technical sufficiency hearing on a disputed plumbing vent layout, the Commission obtains independent technical advice. How must it handle that advice, and what can its order do?

A

Keep the advice confidential and return the technical question to the CBO.

B

Disclose the advice only to the CBO and obtain the Minister’s decision.

C

Disclose its nature for submissions. The Commission may substitute its technical opinion.

D

Disclose its nature and send the technical sufficiency question to the municipality.