2.3 Local Administration, Fees and Conduct

Key Takeaways

  • Section 7(1) sets out administrative topics a local enforcement instrument can address within the authority’s jurisdiction.

  • Section 7(2) caps the total fees authorized under s. 7(1)(c) at anticipated reasonable costs of administering and enforcing the Act.

  • Under s. 7(4)–(8), an authority prepares a report every 12 months, makes it publicly available and gives notice and holds a public meeting concerning proposed fee changes.

  • Section 7(1)(f) and (9) protect prescribed and Minister-approved forms from replacement by a local form for the same purpose.

  • Section 7.1 requires an enforceable code of conduct for the Chief Building Official and inspectors, with breach procedures, disciplinary provisions and public notice.

Last updated: November 2026

Which local rules can the authority make?

Start with the Building Code Act, 1992 (BCA), s. 7. It authorizes rules about local administration in the area and for the matters within an authority's enforcement jurisdiction. A local council, qualifying upper-tier council or prescribed board of health can pass a by-law. A prescribed planning board can pass a resolution. A prescribed conservation authority or the Minister can make a regulation in the applicable area. In each case, identify the enabling clause and the limits attached to it before applying a local rule.

Administrative questionSource in s. 7What the source allows
Can an authority set permit classes and submission requirements?7(1)(a)–(b)Specify permit classes, including stages of work, and prescribe the information and documents that go with permit applications.
Can it run or govern sewage maintenance inspection programs?7(1)(b.1)–(b.2)Establish and govern additional programs or govern a provincially established program, subject to the regulations made under s. 34.
Can it charge or refund permit and inspection fees?7(1)(c), (c.1), (d)Prescribe fees for applications, issuance, maintenance inspections and specified information, provide for late-payment costs and prescribe refund circumstances.
Can it require notice at a further inspection stage?7(1)(e)Require notice at additional stages specified in the Code and prescribe the inspection period following the notice.
Can it set a local permit form?7(1)(f), 7(9)Prescribe forms within the statutory grant. Where the Code prescribes a form or the Minister approves one for the same purpose, that local power does not extend to replacing it.
Can it require record plans at completion, allow transfer of a permit when land changes ownership, or require site fencing?7(1)(g)–(j)Those topics are expressly authorized, subject to the applicable conditions and enforcement scope.

For example, an authority may use a building by-law to request site plans with an application. The requirement for a supporting plan is separate from choosing the application form itself. Division C Article 1.3.1.2. requires the Minister-approved form for a s. 8 construction or demolition application. Under s. 7(9), a local by-law cannot replace that form with a proprietary one for the same purpose. A local checklist can help the applicant identify what to submit alongside the approved form. Building Code Act, 1992, s. 7, Compendium, Division C Part 1

Fee ceiling, reporting and changes

Section 7(2) compares total fees authorized under s. 7(1)(c) with anticipated reasonable costs in the area of jurisdiction. Suppose an authority's own estimates show that its fee schedule would generate more than those costs, and it includes an extra amount solely for unrelated road work. The problem is that the forecast fees exceed the statutory ceiling. If collections exceeded expectations in a single year, start by checking the cost and revenue assumptions before drawing the same conclusion.

Section 7(3) requires a reduced-fee provision in an instrument setting application and issuance fees under s. 7(1)(c)(i) for construction where an agency was appointed under s. 4.2. Read the appointment route closely. A principal authority hiring an agency under s. 4.1 is a different statutory route. Section 7(8.1) also makes specified tax-roll provisions applicable to fees of a municipality or local board, and to the fees of a qualifying conservation authority when the treasurer gives the required approval.

Every 12 months the authority must prepare a report with the prescribed information about fees and enforcement and administration costs, and make it publicly available in the prescribed manner. Before a proposed fee change, it must give prescribed notice and hold a public meeting within the prescribed period before adopting the change. Read ss. 7(4)–(8) for those duties. Division C Section 1.9 supplies the operational reporting and notice details and is outside the direct General Legal/Process syllabus. Building Code Act, 1992, s. 7, General Legal/Process syllabus

Conduct, enforcement and public access

Under s. 7.1, every principal authority establishes and enforces a code of conduct for its chief building official (CBO) and inspectors. The statute gives three purposes: appropriate behaviour and enforcement action, prevention of abuses of power, and honesty and integrity. The code must have provisions for its enforcement and policies or guidelines for handling breach allegations and potential disciplinary action. The authority must bring the code to the public's attention.

Consider a council adopting a new code that sets professional standards but leaves disciplinary action entirely unaddressed and circulates the policy internally only. Section 7.1(3) requires enforcement and breach and disciplinary procedures. Section 7.1(4) requires public notice. Identify the two deficiencies separately. If the complaint is about a permit decision itself, first identify the decision and the legal route for challenging it. A disciplinary code serves a different function from the dispute and appeal procedures in sections 24 and 25. Building Code Act, 1992, s. 7.1

Test Your Knowledge

A proposed permit fee schedule would raise more under s. 7(1)(c) than the authority anticipates reasonably spending to administer and enforce the Act in its jurisdiction. Which limit applies?

A

The spending forecast is irrelevant if the authority holds a public meeting.

B

The fee difference is allowed when it funds any other local service.

C

The limit applies only to the fee for a single residential permit.

D

Section 7(2) caps the total authorized fees at the anticipated reasonable administration and enforcement costs.

Test Your Knowledge

A principal authority sets standard application and issuance fees in an instrument made under s. 7(1)(c)(i). What additional fee provision must it include by virtue of s. 7(3)?

A

A reduction for construction where an agency is appointed under s. 4.2

B

A mandatory refund whenever an application is refused

C

An exemption for every application involving a professional engineer

D

An increase for all work reviewed by an agency under s. 4.1

Test Your Knowledge

An authority wants to replace the Minister-approved form for applications to construct or demolish with a local form for exactly the same purpose. Which Act rule controls?

A

It must use a fee report as the application form.

B

Section 7(9) limits the local form-making power when there is a prescribed or Minister-approved form for that purpose.

C

Section 7(1)(f) authorizes replacement whenever a majority of inspectors agrees.

D

A project-specific code of conduct determines which form to use.

Test Your Knowledge

Which requirement applies to an authority’s code of conduct under s. 7.1?

A

Only inspectors are covered, and the policy may stay internal.

B

The authority can address professional behaviour without any enforcement procedure.

C

The code covers the CBO and inspectors, provides for breach response and disciplinary action, and is brought to the attention of the public.

D

The CBO sets standards that apply to permit applicants but not to officials.