4.4 AWS A2.4 vs. ISO 2553 Conventions & Pre-Weld Fit-Up Verification
Key Takeaways
ISO 2553:2019 System A uses the continuous line for the arrow side and dashed line for the other side when both lines are shown.
ISO System B uses a single line, with symbols below for arrow side and above for other side as in AWS A2.4.
In ISO notation a specifies nominal throat thickness and z specifies leg length for a fillet.
ISO n × l (e) gives count, segment length and clear spacing. AWS length-pitch gives segment length and centre-to-centre pitch.
Before welding, compare the prepared and assembled joint with the governing drawing and procedure, and record evidence for the assigned release decision.
Identify the specified drawing convention
A welding symbol standard supplies the rules for reading the callout. ISO 2553:2019 includes two systems for showing joint side. AWS A2.4:2020 uses a reference line for side placement and can use multiple reference lines to sequence operations. Check the drawing and governing specifications for the system and edition. A single line does not by itself identify ISO System B because System A omits the dashed line in some cases.
| Convention | Arrow-side weld | Other-side weld |
|---|---|---|
| AWS A2.4 | Symbol below the reference line | Symbol above the reference line |
| ISO 2553 System A | Symbol on the continuous line | Symbol on the dashed line |
| ISO 2553 System B | Symbol below the single reference line | Symbol above the single reference line |
System A permits the dashed line above or below the continuous line. Clause 4.7.1A recommends omitting it for symmetric welds and for spot or seam welds at the interface of components. Read the full symbol and drawing before choosing the weld side. Both sides refer to the indicated joint. A hidden weld belonging to a different joint requires its own identification.
Worked example. A bracket drawing specifies ISO System A. The dashed line lies below the continuous line and carries the fillet symbol. The weld goes on the other side of the indicated joint. On a separate AWS drawing, an elementary fillet symbol below the single reference line specifies the arrow side. At the bench, identify the indicated joint and orientation before checking hardware.
Read throat, leg and segment dimensions
AWS fillet symbols with a displayed size show leg dimensions on the left. ISO 2553 clause 5.5 uses a prefix to distinguish the measured dimension. For ideal equal legs on a 90° joint, the geometry gives the following comparisons.
| ISO prefix | What it measures | Example |
|---|---|---|
| a | Nominal throat thickness | a6 gives a 6 mm throat. Equal legs in the ideal 90° geometry would be about 8.49 mm. |
| z | Leg length | z8 gives an 8 mm leg. The ideal throat is about 5.66 mm. |
| s | Deep-penetration throat thickness | This dimension precedes the nominal throat designation in the deep-penetration callout. Read both requirements together. |
The ideal conversion is . Reading a8 as z8 in this geometry changes the throat from 8 mm to about 5.66 mm, a difference of about 2.34 mm. Geometry alone cannot establish capacity, actual penetration or acceptance.
ISO's main intermittent notation gives the number of segments, each segment's length and the clear spacing between adjacent segments. A callout of 4 × 75 (125) gives four 75 mm segments with 125 mm clear spacing. The first and last centres span three pitches of 200 mm, or 600 mm. The complete pattern occupies 675 mm measured from the start of the first segment to the end of the last. AWS 75-200 gives the same segment length and pitch. Check the AWS drawing for any separate layout, count and end requirements. ISO also recognizes alternative intermittent notation. Read the drawing's specified convention before converting.
Turn the symbol into a fit-up inspection
- Identify the work. Confirm the sheet revision, weld number, symbol system, side and referenced detail. Read the specified welding procedure data sheet (WPDS) before measuring.
- Check the preparation. Identify the prepared member. Compare bevel angle, depth and root face with the specified joint geometry. Use the required instrument and units.
- Check assembled fit-up. Measure opening and offset independently. Verify the backing or spacer type, location and fit when specified. Compare each reading with the applicable tolerance. If the reading is out of tolerance, record the extent and ask the designated person for disposition.
- Check readiness. Verify surface condition, tack condition, personnel qualification, preheat and consumables as applicable. Record the results and provide them to the person assigned to release the work under the inspection and test plan.
Worked check. An approved detail calls for a 3 mm root opening with a tolerance of ±1 mm. At two specified locations you measure 2.5 mm and 4.5 mm. The first is within 2–4 mm and the second exceeds the maximum by 0.5 mm. Record both measurements with their locations and advise the responsible person before release. The tolerance here comes from the example drawing. Obtain the limits and authorized repairs for a real job from its applicable documents. CWB Form 101E, company certification guide illustrates documentation of the joint configuration and procedure variables.
An ISO 2553:2019 System A symbol places a fillet on the dashed line below the continuous line. Where is the weld specified?
On the arrow side, because the symbol sits below the solid line
On the other side (opposite the arrow), because the symbol sits on the dashed identification line
On both sides simultaneously, because dual reference lines require double-fillet welds
In the field during site erection, because the dashed line represents field work
An ISO 2553 drawing calls for an a6 continuous fillet weld on one side of a bracket and a z8 fillet weld on an adjacent stiffener (both equal-leg joints). Which statement accurately compares the two welds?
The a6 weld requires a 6 mm leg length, while the z8 weld requires an 8 mm throat thickness
Both welds have identical cross-sectional sizes because a and z are interchangeable metric prefixes
The z8 weld requires an 11.3 mm leg length, making it substantially larger than the a6 weld
a6 gives a nominal 6 mm throat. z8 gives an 8 mm leg and about 5.66 mm of ideal throat.
For the worked fit-up inspection, put the steps in the documented order.
Arrange the items in the correct order
Compare joint preparation, opening, offset and backing with the detail.
Record measurements and refer the result for the assigned release decision.
Find the controlled drawing, confirm the side and read the procedure.
Check the surface, tacks and thermal readiness.
Sections you finish are checked off in the contents.