9.1 Inspection & Test Plans (ITPs), Hold Points & Witness Points

Key Takeaways

  • Quality assurance provides confidence in the system. Quality control checks performance and conformity to requirements.

  • An inspection and test plan links activities to requirements, verifying records and responsible parties.

  • Work cannot pass a hold point without the required approval. Check the plan for the exact witness and waiver rules.

  • Record any bypassed verification, notify the designated supervisor, and follow the approved disposition.

Last updated: November 2026

Use the plan before the joint is closed

Quality assurance (QA) provides confidence that quality requirements will be fulfilled. Quality control (QC) is concerned with fulfilling those requirements, including the operational checks that verify conformance. An audit of how a shop issues procedures is one way to gain confidence in the process. Measuring a root opening against the issued procedure is a QC check. On some bridge contracts, the owner’s independent QA agency also examines material and work and verifies the fabricator’s QC. Inspecting a physical weld can therefore be part of a QA assignment. ISO on quality assurance and British Columbia Bridge Standards Manual.

An inspection and test plan (ITP) assigns verification points throughout the work. For each relevant row, look for the activity, the applicable revision and requirement, how much is to be checked, who acts, and the required record. An ITP may reference criteria in another controlled document. Open that document to obtain the actual requirement. CWB Form 101 gives an example of operational control procedures and project ITPs under its certification framework. CSA W178.2:18 clause 7.4.2 describes reviewing contractors’ ITPs for welding-related quality requirements as a Level 3 competency. Release and approval roles are assigned by the applicable project. The Level 1 inspector performs their assigned checks with qualified supervision. CWB Form 101 and CSA W178.2:18 clauses 5.3 and 7.

Read a welding ITP

This sample uses fictional requirements and an expressly assigned set of intervention points.

ActivityRequirement and scopeEvidenceIntervention in this plan
Material receiptCheck the drawing grade and the receiving traceability rule for each lotMaterial test report (MTR) and receiving logFabricator checks. Client reviews the records
Fit-upAt each identified splice, use the required drawing and a procedure data sheet with a 2–4 mm root openingFit-up readings by weld IDThird-party hold point before depositing the root
Thermal controlsApply the specified procedure and measure at the interval in the work instructionIn-process thermal logClient surveillance
Back preparationExamine the exposed root at each listed double-sided joint before closing itSurface examination and release recordThird-party hold point
Final nondestructive examinationApply the method, area and timing specified at the listed weldsExamination report and examiner identificationWitness as specified. Retain results for document review

For example, the ID on a visit request has to identify the correct inspection stage and joint. Record a 4.5 mm root opening as 0.5 mm above the maximum for the example. Even after correction, the designated person still needs to release the fitting stage as required by the ITP.

Interpret the intervention legend

  • Hold (H). Pause at the required stage until the designated authority provides the approval or authorized waiver required by the plan. Notification alone cannot release the hold.
  • Witness (W). Give the required notice so the designated party can observe a test or activity. The project defines if and how attendance can be waived. For example, TC Energy’s published specification requires attendance or a written waiver. Confirm the waiver or other defined condition for proceeding.
  • Review (R). Supply the specified records for review. Confirm any required sign-off and when it is due.
  • Surveillance (S). Monitor ongoing work under the plan, for instance by sampling specified work stages or reviewing trends in a log. If an observation identifies a deviation, follow the reporting process.

Read the governing legend for the job. Different organizations can use additional letters and notification periods. TC Energy inspection and test plan specification.

Respond to a bypassed hold

The crew welds Side 2 before a backgouge hold point is released. The exposed stage is now hidden. Record the affected weld and what can be established from the inspection record. Notify the supervisor, flag the missed verification through the project’s nonconformance route, and check which further work is restricted. Report only evidence you actually have. The responsible authority decides the approved examination, corrective work or other disposition under the governing requirements. An acceptable-looking cap cannot establish that the hidden stage was examined. CSA W178.2:18 clause 6 on reporting and signatures.

Loading diagram...
Check release and witness conditions before work proceeds
Test Your Knowledge

Which pair illustrates quality assurance and quality control on a welding project?

A

Reviewing a shipping address is QC and welding to any setting is QA.

B

Auditing the system for issuing approved procedures supports QA. Measuring a root opening against the issued requirements is a QC check.

C

Both functions occur only on finished work.

D

Neither function uses documented requirements.

Test Your Knowledge

A girder’s second side has been welded before release of the backgouge hold point. What is the first inspection response?

A

Sign the hold from the appearance of the cap.

B

Treat the earlier notification as a formal release.

C

Remove all weld metal without a disposition.

D

Record and report the missed verification and identify the affected weld for disposition under the plan.

Test Your Knowledge
Matching

Match the intervention with the condition in a plan that requires attendance or written waiver for witness points.

Match each item on the left with the correct item on the right

1

Hold

2

Witness

3

Review

4

Surveillance

Sections you finish are checked off in the contents.