9.3 Duties of the Level 1 Inspector: Before, During & After Welding (INSP-301)
Key Takeaways
CSA W178.2:18 identifies Level 1 material, fit-up and specified weld examination competencies under qualified supervision.
Use the assigned inspection procedure and plan to establish scope, measurements, timing and what must stay accessible.
Record deviations against the applicable document and advise the supervisor or responsible person promptly.
The project identifies who releases the work and which specialist qualifications are required.
Identify what you are assigned to verify
CSA W178.2:18 clauses 5.3 and 7.2 cover assigned Level 1 welding inspection under qualified supervision. Clause 7.2 includes verifying specified base and welding materials and condition, checking preparation and fit-up, and examining welds to a specified procedure. Clause 7.1 addresses monitoring, records and reports at all levels. Clause 7.3 lists additional Level 2 competencies, including confirming equipment suitability, personnel qualification and use of specified procedures. Coordinate those verifications with the responsible person. The first step is to learn which detailed checks are assigned to you and who deals with questions outside that assignment. CSA W178.2:18 clauses 5.3 and 7.
Before welding
Read the accepted welding instructions, the current drawing and applicable inspection and test plan. Confirm the specified materials, condition and traceability. Check which filler, shielding and backing the procedure requires. Use the report or marking method specified for the component. Make sure questions about the welder’s scope or equipment suitability are resolved by the responsible person before the applicable release.
Use the appropriate instrument to check the specified preparation and fit-up, including opening, land, alignment or backing as required. Record readings at their actual locations. A joint can meet the opening tolerance at one end while exceeding it at the other. Examine the condition of tacks that will remain as assigned. Check any required preheat by the specified timing and method. A reading cannot establish conformity if it was taken outside the specified area or at the wrong stage. CWB welding procedure qualification and ISO 13916 measurement scope.
During welding
Monitor the observations assigned in the plan. Examples include recording current, voltage, welding travel or shielding settings against the procedure, observing interpass cleaning, and checking whether thermal requirements and hold points are being met. Record when readings were taken. A wrong setting for one pass can require assessing that pass or weld segment. Verify consumable handling against the procedure and applicable product instructions. Follow the approved disposition for exposed or unidentified electrodes.
If a back-prepared surface must be verified before second-side welding, examine the prepared groove while accessible within the assigned inspection. Report contamination, evidence of an unsuitable profile or a missed hold to the responsible person. Describe visible slag or an irregular groove profile and record where you saw it. A written report should state what was actually verified. CWB welding procedure preparation and CSA W178.2:18 ethics and inspection competency.
After welding
Confirm the surface condition and access necessary for the assigned visual examination. Examine the required extent and take dimensions using the appropriate gauge and specified conditions. Record each observation against the applicable requirement. The practical exam’s Generic Welding Standard applies to its samples. For production, use the referenced criteria and reporting requirements.
Check that any specified heat-treatment evidence or nondestructive examination is linked to the joint. If a delay applies, compare the actual examination time with the specified start and minimum interval. Specialist examinations require appropriate qualified personnel. Report the status and unresolved items through the inspection plan. A Level 1 report documents assigned checks and does not by itself authorize shipment or certify an examination performed by someone else. CWB on practical-only criteria and CWB on visual testing and welding inspector certification.
Worked shift record
| Stage | What the inspector finds | How to report it |
|---|---|---|
| Before | Hypothetical weld W-21 specifies a 2–4 mm opening. The measurements are 3 mm at the near end and 5 mm at the far end | Record both locations and the 1 mm excess at the far end. Notify the designated supervisor |
| During | After documented correction and release, the assigned log calls for interpass readings at specified stages. One reading exceeds the current procedure maximum | Record the reading, time, location, pass and actual settings as required. Follow the plan before the next pass |
| After | The assigned visual examination is complete. The project also requires ultrasonic testing at least 24 hours after welding completion | At 18 hours the stated minimum has 6 hours remaining. Document visual findings and list ultrasonic examination as outstanding |
When the separate examination report arrives, compare its weld ID and coverage with the plan before sending the records through the designated review and release route. The 24-hour rule in this example belongs to the stated job.
An inspection plan asks for travel-speed records for three fill passes. You observed only pass 2 and its reading is within range. What should your report show?
Record all three passes as acceptable because the welder and joint were the same.
Record the reading and identification for pass 2 and identify the evidence still needed for the other passes.
Average the pass 2 reading with two copies of the procedure setpoint.
Leave the report blank because only a final surface check can be documented.
A job requires separate ultrasonic testing at least 24 hours after completion. At 18 hours the assigned visual examination is finished. What should the inspector report?
Record visual findings and the ultrasonic examination as outstanding, with six hours left before its earliest permitted time.
Accept the weld for shipment because visual inspection is complete.
Perform the ultrasonic examination personally without method qualifications.
Record the ultrasonic result as acceptable from the visual appearance.
Put these assigned inspections and reporting tasks in order for the example.
Arrange the items in the correct order
Record assigned process and temperature readings during welding.
Check material, procedure and fit-up before the root pass.
Examine the completed, accessible surfaces as specified.
Submit the records and list any outstanding verification.