21-2 Contract Surety Bonds: Bid, Performance, Payment, and Maintenance Bonds

Key Takeaways

  • Identify the public contracting authority and compare the applicable procurement statute with the executed instrument.

  • On a bid bond, use the actual covered measure of loss and the applicable penal sum.

  • For performance, document Section 3 steps and test the response options under the actual bond.

  • Georgia’s remote-claimant notice and the time to sue are separate deadlines.

Last updated: November 2026

21-2 Contract Surety Bonds

Identify the contracting entity and legal regime before applying a dollar threshold or claim deadline. For Georgia local public construction, payment bonds or authorized security protect eligible claimants who cannot enforce a construction lien against the public property. The contract also matters because statutory provisions can permit security alternatives or exceptions.

ProjectPerformance and payment protection
Federal constructionFAR 28.102-1 generally requires both bonds on contracts exceeding $150,000. The statutory text in 40 U.S.C. § 3131 uses $100,000. FAR 28.102-2 generally uses 100% of original contract price plus price increases, with specified determinations allowing a different amount and a payment bond no lower than the performance bond. For amounts over $35,000 through $150,000, the FAR requires the contracting officer to select at least two specified payment protections for the contractor to choose from.
Georgia state public constructionO.C.G.A. §§ 13-10-40 and 13-10-60 and the Georgia Procurement Manual use a threshold above $100,000. The performance bond must cover at least the total amount payable and increase with the contract amount, subject to the Title 32 qualification. Payment security starts at no less than the initial amount payable and increases on the state’s request when the contract amount rises. The state can accept specified checks or cash instead of a payment bond and can require bond protection below the threshold.
Georgia local public worksAfter 2025 HB 137, § 36-91-22(a) generally excludes projects performable for less than $250,000 from Chapter 91. Apply the specific bond or security requirements in §§ 36-91-50, 36-91-70 and 36-91-90 when the chapter applies. Check any emergency or self-performed project exception and the separately worded threshold for a contracted portion of self-performed work in § 36-91-22(g).

Bid security and the re-award cost

A bid bond protects the owner if a bidder fails to execute the required documents or furnish required bonds after a qualifying award. Federal SF 24 (10/2023) conditions the bond on execution and submission within the relevant periods or payment of the excess cost of procuring the work. For state and local work, read the statute, the solicitation and the signed instrument. Georgia § 36-91-52 permits withdrawal without forfeiture for certain appreciable bid errors when statutory conditions are met. Record the required proof and written notice before the award and within 48 hours of opening, excluding Saturdays, Sundays and legal holidays. Determine whether the good-faith error, evidence and undue-prejudice conditions are met.

For a municipal bid with a stipulated excess-cost clause and a 5% bond, a $2,000,000 bid gives a $100,000 penal sum. If the bidder defaults and permissible replacement procurement costs $2,160,000, the $160,000 spread exceeds the stipulated limit, so the bond pays $100,000 if liability is established. If the replacement procurement instead costs $2,070,000, the covered spread on those facts is $70,000. Confirm that the obligee re-awarded the same scope and incurred compensable added cost.

Loading diagram...
Contract Surety Lifecycle and Performance Bond Default Options

Performance bond response

A performance bond secures the contractor's obligations to the owner. Under AIA A312–2010 §§ 3–4, first check for owner default, notice that contractor default is being considered, the actual declaration and termination and notice to the surety, and the owner's agreement concerning the unpaid contract balance. A failure of the preliminary notice in § 3.1 is different from a failure to declare default and terminate under § 3.2. Under § 4, the preliminary-notice defect relieves the surety only to the extent of actual prejudice.

After the conditions are satisfied, § 5 permits the surety to arrange for the original contractor to complete with the owner's consent, undertake completion itself, arrange an acceptable bonded replacement and pay qualifying damages above the contract balance, or waive completion and investigate and pay the amount owed or issue a reasoned denial. A continuing default under § 6 has its own additional demand procedure. Approval of a completion proposal depends on the bond, consent, capability, schedule and estimated cost. §§ 7–8 distinguish response costs, covered damages and the relevant cap; a takeover deserves its own agreement and exposure analysis.

For a project with an unpaid contract balance of $600,000 and qualifying replacement completion costs of $760,000, start with a $160,000 difference. Verify any covered corrective costs or delay damages, confirm the available balance, and apply the selected response's terms. A separate maintenance bond, if purchased, can secure the stated warranty obligation after completion. For a supply or completion bond, identify the promised delivery or completion work and the protected party in the instrument.

Payment bond notice and suit

The payment bond protects eligible claimants furnishing labor or materials for the bonded work. Obtain the contract chain, bond, delivery records, payment history, filed Notice of Commencement and evidence of posting and furnishing copies. Under the Georgia provisions, check the 15-day filing requirement after physical commencement and the contractor’s 10-calendar-day response to a written request. The preliminary notice deadline and the time to sue are separate.

Georgia public payment bond issueApply §§ 13-10-62/63/65 or 36-91-92/93/95 as appropriate
Contractor complied with the Notice of Commencement requirementsA qualifying supplier or sub-subcontractor without a contract with the prime must give the prescribed notice to the contractor within 30 days after filing of the notice or after the claimant's first delivery, whichever is later. The notice identifies the claimant and who requested the work, the project and location, and the work or supplies and known value or claim.
Contractor failed to comply as to the claimantThe alternate statutory notice for a claimant directly contracting with a subcontractor but without a prime contract uses 90 days from last qualifying furnishing. Verify the amount claimed, the supplier’s customer and authorized service, such as certified mail or service as for process.
Right to sue and outside limitApply the 90-day nonpayment condition from the applicable last furnishing or subcontract completion and the separate one-year limit from completion and acceptance of the public work. A claimant contracting with the prime is outside the special remote-claimant notice requirements.

For federal Miller Act payment claims, 40 U.S.C. § 3133 uses a separate federal regime. For example, a claimant directly contracting with a subcontractor and having no relationship with the prime must meet the federal 90-day notice rule measured from last furnishing, and the federal suit period is no later than one year after the claimant's last labor or materials. For private work, apply the actual payment bond and separately check any lien or lien-discharge security rights under state law.

Test Your Knowledge

A municipal bid bond expressly covers qualifying re-award costs above the original bid, capped at a $300,000 penal sum. The original bid is $3 million. After a covered failure to furnish the required bonds, proper re-award of the same work costs $3.45 million. What is payable on the stipulated facts?

A

$450,000

B

$300,000

C

$150,000

D

$0

Test Your Knowledge

On a Georgia state project, the prime contractor complied with the Notice of Commencement requirements. A supplier directly contracts with a subcontractor and has no contract with the prime. What notice timing applies under § 13-10-63(a)(2)?

A

One year after acceptance of the work.

B

Ninety days after the last furnishing in every case.

C

Ten days after delivery of the last materials.

D

Within 30 days after filing of the Notice of Commencement or the first qualifying delivery, whichever is later.

Test Your Knowledge

An owner has satisfied AIA A312–2010 § 3. The original contractor remains able to finish the remaining work with support. The owner agrees that the original contractor may complete it. Which § 5 option can use that agreement?

A

Arrange for the original contractor to perform and complete the contract with the owner’s consent.

B

Cancel the bond unilaterally after 30 days.

C

Require the owner to accept an unrelated contractor without concurrence.

D

Require the owner first to litigate against the principal to judgment.