Key Takeaways
Under §1926.1417(u), a competent person supervises permitted travel with load, determines any needed capacity reduction and sets the conditions for the entire move.
Travel speed, grade, load location, boom position, tire pressure and working quadrant come from applicable procedures and the actual site evaluation.
Duty-cycle equipment ratings depend on the application, configuration and attachment. The 90% brake-check rule uses maximum line pull.
For mechanical demolition with a ball, §1926.859(b) uses the lower of two limits calculated from the configured crane rating and the line’s nominal breaking strength.
Travel with a suspended load
A pick-and-carry lift adds the travel route to the load path. A moving crane crosses varying support, starts and stops, and can change heading while the load swings. A load initially within capacity can become uncontrolled as its radius increases. Check whether the manufacturer allows travel under load in the exact configuration. Under 29 CFR 1926.1417(u), a competent person supervises permitted travel, determines whether rated capacity must be reduced, and sets safe load position, boom location, ground support, route, overhead clearance and speed. The employer implements those determinations and maintains the manufacturer-specified pressure for equipment on tires. Review these decisions together:
- Crane setup: Confirm the permitted travel configuration, capacity and any needed reduction.
- Carrier path: Verify support, grade, turns, overhead clearance and speed along the full route.
- Load path: Allow for the movement of the load during starts, stops and turns, and place workers clear of the moving equipment.
Crane charts and instructions may specify permitted travel configurations, including boom position, house lock, grades and whether the load is kept over one sector. For example, a Grove RT9130E-2 procedure calls for the applicable pick-and-carry chart, level travel and the house lock engaged with the boom over the front. Verify the applicable procedures for the machine on the job. Section 1417(r) generally prohibits lifting over the front of wheel-mounted equipment unless the manufacturer permits it. If a tag or restraint line is needed to prevent hazardous rotation, §1417(w) requires one. Plan its handling without putting a worker in the travel or crush path. Keep the load controlled through acceleration, steering and stopping and obey the crane’s permitted side loading and rotation limits (§1417(q), (v)).
Route decision. A crew will move a suspended skid on a rough-terrain crane. The short route crosses a utility trench restored that morning. The other route runs along a surveyed pad but leaves less room when the load rounds a corner. Compare ground support, slope and the full moving envelope, including the projected swing and overhead clearances. Verify the trench fill’s support before relying on that route. If taking the pad, confirm the permitted chart sector still applies when the carrier changes heading and that the path stays clear of employees. If neither route meets all limits, reset the lift or change equipment. For a rail-mounted tower crane, follow its travel and load limits and check the path, rail supports, travel bogies and end stops. Section 1926.1435(e)(5)(vii) addresses the rail travel limiting device. If using its temporary alternative, use a spotter in direct communication with the operator within 10 ft of either end stop, as specified there.
Repetitive duty and attachment selection
A duty-cycle machine may work a succession of cycles with a bucket, grapple, dragline or other equipment designed for that application. Engagement with the material, acceleration and deceleration, and repeated use change what the machine sees. The lift director checks the manufacturer's application ratings and procedures, including the permitted attachment, boom geometry and configuration. For example, the Liebherr HS 845 HD technical data identify specific dragline and grab configurations. For a grab cycle, count the installed gear and the payload and evaluate the actual working radius and configuration on the applicable chart. If a bucket takes on unexpected extra material or sticks, interrupt the cycle and resolve the condition using the manufacturer’s procedures. A freely suspended load and a stuck bucket subject the crane to different forces.
For repeated concrete bucket placements with a tower crane, compare the filled bucket and rigging with the applicable chart at the most restrictive phase, including the transfer from fill point to placement. Before repeating the sequence, confirm that the fresh load, path and working conditions still fit the plan. Under §1926.701(e), keep workers out from under the bucket while raising or lowering it into position and route it to minimize employee exposure to the extent practical.
Use the correct rating for the brake-check decision. Section 1417(s) uses 90% or more of maximum line pull, with a brake check by lifting a few inches and applying the brakes. For a duty-cycle or repetitive sequence in which each lift reaches that threshold, it applies to the first lift, with the exception for successive lifts of the sequence. Chart utilization at working radius and percentage of maximum line pull measure different limits.
Demolition
Before demolition, §1926.850(a) requires an engineering survey by a competent person and written evidence that it was performed. Where a crane will hoist cut structural steel, include the verified weights, rigging points, remaining structure and sequence that keeps members supported during separation. Section 1926.858 addresses steel removal and dismantling members without overstress. A snag or partially cut member can transfer unplanned forces. Stop if the actual release or support condition differs from the plan and reassess before moving the crane. Section 1417(q) prohibits using the crane to drag or pull loads sideways.
For mechanical demolition with a ball or clam, keep workers out of the area that can be adversely affected while balling or clamming (§1926.859(a)). Under §1926.859(b), if the configured boom-length and maximum-angle crane rating is 24,000 lb and the line’s nominal breaking strength is 40,000 lb, the alternatives are 12,000 lb and 10,000 lb. The regulatory limit for the ball is 10,000 lb, subject to any stricter manufacturer limit. That work also requires the shortest practicable boom and line, a swivel-type and positive attachment, and continuing competent-person inspection as demolition advances (§1926.859(c), (d), (g)). The ball-weight arithmetic belongs to the demolition-ball rule.
A crane manufacturer permits travel with this load configuration. How should the crew handle a newly filled trench along the proposed route?
Have the competent person assess the route and support and determine any needed capacity reduction. The employer ensures the required travel conditions are implemented.
Cross whenever the load is below the stationary chart limit.
Use the same speed and tire pressure as the crew’s previous crane.
Have a signalperson confirm visibility and proceed while ground support is still unknown.
A grab cycle is to be performed with a crane that has both lift and duty-cycle data. Which basis best supports the capacity decision?
The lift chart with a standard 20% reduction
The heaviest single lift the operator recalls in the same sector
The manufacturer’s rating for the actual duty-cycle application, attachment and configuration
The hook rating alone, if the operator uses a slow swing speed
For mechanical demolition, the rated load for the boom length and maximum operating angle is 24,000 lb. The suspension line’s nominal breaking strength is 40,000 lb. What is the maximum ball weight under §1926.859(b), before applying any stricter manufacturer limit?
24,000 lb
12,000 lb
20,000 lb