5.3 Crane Assembly & Disassembly (A/D) Oversight
Key Takeaways
The A/D director under §1926.1404(a) must be both competent and qualified, or a competent person assisted by one or more qualified persons. A sole performer must meet both definitions.
Follow applicable manufacturer prohibitions and use manufacturer or compliant employer procedures under §§1926.1403 and 1926.1406.
Plan for component weights, center of gravity, assist-crane loads, blocking and a safe counterweight and pin sequence. Section 1926.1405 separately prohibits certain pin removals.
A qualified person must complete the required post-assembly configuration inspection before the equipment is used. Tower crane erection and climbing also have supplemental requirements.
Assign responsibility and choose the procedure
Assembly/disassembly places the crane in configurations that may be unstable or unsuitable for production lifts. The A/D director supervises this work under 29 CFR 1926.1404(a). Use a person who is both competent and qualified, or a competent person assisted by one or more qualified persons. If one person performs the assembly or disassembly, that person must meet both definitions. This assignment applies to A/D. The §1926.1432(b) lift director provision applies when multiple cranes will support a load and has a separate planning provision.
Under §§1926.1403 and 1926.1406, follow applicable manufacturer prohibitions and use either manufacturer procedures or compliant employer procedures. If employer procedures are used, a qualified person develops them. They must prevent unintended dangerous movement and collapse, provide adequate support and stability, and minimize employee exposure to unintended movement or collapse. Section 1404(b)–(c) requires the A/D director to understand the procedure, and to review it immediately before starting unless that director already understands it and has applied it to the same equipment type and configuration, including accessories.
Control the sequence and positions
Under §1926.1404(d), before starting, the director ensures the crew understands its tasks, the hazards of those tasks, and hazardous positions to avoid. Repeat the instruction for new personnel or assignments they have not previously received. Under (e), someone going out of the operator’s view at a place where movement could injure them must inform the operator. The operator then waits until informed by a prearranged communication system that the person is safe. Under (f), keep employees from beneath components during pin removal. A limited exception requires site constraints that make compliance infeasible and procedures that minimize exposure and the risk of unintended movement. The rigging work must be done by a qualified rigger under §1926.1404(r).
| Check | What the A/D team needs to establish |
|---|---|
| Support and blocking | Confirm ground support under both cranes and the correct size, condition, placement and capacity of blocking. For outriggers or stabilizers use full extension or the manufacturer-authorized load-chart position, attach floats when used and keep the units visible to the operator or signalperson during extension and setting. Outriggers remove the weight from wheels where §1404(q)(2) applies. |
| Component and assist crane loads | Have individual component weights available. Verify assist-crane loads for each stage in accordance with §1417(o)(3) before A/D starts. Verify rigging weight, lift points and center of gravity so the component can be controlled at each transfer. |
| Balance and stored force | Follow the applicable sequence for counterweight and boom changes, including rearward stability. Observe the manufacturer’s cantilever limit. If it is unavailable, a registered professional engineer familiar with this equipment type determines the limit in writing under §1404(j). |
| Lattice boom and jib pins | Under §1926.1405(a)–(b), keep pendant pins and pins between the pendant attachment points and crane body in place while pendants are in tension. Under (c), keep pins between the uppermost section and the body in place when the uppermost section itself supports the boom on ground or another support. Under (d), support the cantilevered section to be removed fully before withdrawing its top pins. |
Worked planning decision
An assist crane is to take a lattice section during dismantling. The main crane’s tip end is resting on cribbing and the planned joint is between the supported uppermost section and the crane body. Even if the pendants are slack, §1926.1405(c) prohibits partial or complete removal of the pins at that joint in this setup. Hold the work. The A/D director verifies a compliant support and removal sequence and briefs the crew before it resumes. For an illustrative planned phase in which the assist crane takes the full 16,000 lb section plus 900 lb of counted hook and rigging, compare 16,900 lb with the applicable gross rating at that phase’s radius and configuration. Check other stages independently because radius, geometry or load share can change throughout disassembly. Visible cribbing, a slack pendant and an adequate assist-crane rating are distinct checks.
Overhead lines and return to service
Use the A/D-specific power-line rules in §§1926.1407 and 1926.1409. For an applicable line up to 350 kV, screen whether equipment, load line or load including rigging could come closer than 20 ft during assembly or disassembly. Section 1409 substitutes 50 ft above 350 kV through 1,000 kV. For lines above 1,000 kV, the utility owner/operator or a registered professional engineer qualified in electrical transmission and distribution establishes the minimum clearance. If the screen is triggered, follow the deenergized-and-visibly-grounded option, the specified screening-distance clearance option with precautions, or the voltage-based Table A option with precautions when required. Under §1407(b), required measures include a planning meeting covering the exposed crew, nonconductive tag lines if used and at least one effective listed encroachment measure. Examples of those measures include a dedicated spotter, a correctly set proximity alarm or a high-visibility barrier in the operator’s view. Section 1407(c)–(d) bars being below a line or inside the applicable Table A distance during A/D unless the required deenergization and visible grounding are confirmed.
Under §§1926.1404(m) and 1926.1412(c), have a qualified person verify the assembled configuration using applicable criteria before use. If manufacturer criteria are unavailable, follow §1412(c)(2) to determine whether a registered professional engineer is required to develop criteria, as well as §1404(m)(1) for component selection and configuration. Check for any separate inspection and test requirements, including the supplemental tower-crane rules in §1926.1435.
A competent foreman will direct lattice crane disassembly but lacks the qualifications for this configuration. What is compliant under §1926.1404(a) if the foreman is directing a crew?
A crane operator signs without taking part.
The foreman proceeds alone after reading the procedure.
The lift director can waive qualification if the job has a written lift plan.
Have one or more persons qualified for the work assist the competent foreman.
During disassembly the uppermost boom section is resting on a support and is itself supporting the boom. The pendants are slack. Can the crew start to withdraw pins in sections between that uppermost section and the crane body?
Yes, for top pins only.
Hold and use a compliant support sequence. Section 1926.1405(c) prohibits removing those pins while the boom is supported that way.
Yes, slack pendants are the only relevant OSHA condition.
Yes, if the pin is only partly withdrawn.
A mobile crane has just been assembled. What must be established before it is put into use under §1926.1412(c)?
A qualified person inspects and verifies the configuration against the applicable criteria.
The operator verifies it by lifting the first production load.
A rigger inspects the rigging and releases the entire crane.
The next routine annual inspection is already scheduled.
Sections you finish are checked off in the contents.