1.1 Ground & Subsurface Evaluation
Key Takeaways
OSHA 29 CFR 1926.1402 requires ground and supporting materials that meet the crane manufacturer’s support and leveling specifications. The drainage requirement excepts marshes and wetlands.
The controlling entity arranges needed ground preparations and tells the equipment user and operator the location of known or documented subsurface hazards at the setup area.
When an A/D director or an operator determines the ground is inadequate, that person’s employer must discuss needed ground preparation with the controlling entity under 1926.1402(e).
Obtain a site-specific bearing and settlement assessment where support is in doubt. An excavation soil classification, compaction result or generic bearing number cannot resolve a hidden void or trench.
Uneven outrigger or track settlement can change crane level, increase the actual radius in some directions and impose side loads. Stop and resolve the support deficiency before restarting.
1.1 Ground & Subsurface Evaluation
Start with the ground beneath the crane. Check the support and leveling assumptions of the manufacturer’s instructions for the crane you will use. A load moment indicator measures operating parameters under those assumptions. It cannot establish whether a pad is bearing on sound soil, an old trench or a culvert roof.
Ground preparation and responsibility
29 CFR 1926.1402 governs support for construction cranes.
| Paragraph | What to verify before setup |
|---|---|
| (b) | The surface must be firm, drained and graded enough to meet the manufacturer’s support and leveling specifications, using mats or other suitable supports as needed. The drainage requirement excepts marshes and wetlands. |
| (c)(1) | The controlling entity must ensure the necessary preparations are provided. |
| (c)(2) | The controlling entity informs the equipment user and operator of the location of subsurface hazards under the setup area that it knows about or that are identified in documents it holds, whether at the site or off-site. |
| (d) | If there is no controlling entity, the employer with authority to make or arrange the needed ground preparation must meet (c)(1). |
| (e) | If the A/D director or operator determines the ground fails (b), that person’s employer must discuss the necessary preparation with the controlling entity. |
The Lift Director coordinates the field response when the lift plan’s ground assumptions fail. The A/D director and operator are the two people identified in paragraph (e). If the operator has a safety concern, 1926.1418 gives the operator authority to stop and refuse to handle loads until a qualified person determines safety is assured. Verify that the agreed changes actually satisfy paragraph (b) before using the equipment.
Soil identification and allowable bearing pressure
Soil varies with grain size, moisture, density, disturbance and the depth of different layers. Allowable bearing pressure is a site and loading-condition input, commonly expressed in pounds per square foot (psf) or pounds per square inch (psi). Unconfined compressive strength describes failure of a soil specimen in a different test. Having the same units does not make the two measures interchangeable.
OSHA Subpart P Appendix A classifies soils for excavation protection. For example, an undisturbed cohesive soil may qualify as Type A at 1.5 short tons per square foot (3,000 psf) of unconfined compressive strength, subject to the other classification criteria. Previously disturbed, fissured or vibration-affected soil cannot qualify as Type A on strength alone. The 3,000 psf measurement does not supply a bearing value for an outrigger mat.
To evaluate a proposed setup, obtain the expected support reactions for the crane configuration, loading and operating path. A manufacturer tool such as Manitowoc’s ground support estimator estimates the demand side of that check. A site assessment addresses the allowable side, including weak layers, voids, allowable settlement and the effective area over which the mat will distribute the reaction. A compaction report is evidence about the material and test locations covered by that report. Confirm that its scope matches the proposed pad location and loading.
Subsurface hazards and void detection
A hard surface can conceal an unsupported slab, a weak fill layer or a void. An outrigger positioned nearby may surcharge a buried structure or cause shallow soil to fail into an excavation. Include these features during site plan review and the footprint walk:
- Buried services. Compare current site drawings and locate information with proposed crane locations. An excavation locate can indicate where a service runs. Its marking alone gives no structural capacity for surcharging it.
- Drainage structures. Culverts, vaults, catch basins and manholes may have load limits. Establish their positions and determine whether the predicted loads can be supported before accepting the setup.
- Concealed openings. Check for old tanks, basements, garages and other cavities, including below paved areas that look undisturbed. Obtain the information needed to verify the structure or relocate away from the affected ground.
- Disturbed material. A newly filled trench can settle differently from adjacent ground. Check the records and field conditions, and request a site-specific assessment when the proposed footprint could load the trench or weak material.
Slopes, drainage and differential settlement
Runoff can erode soil from beneath a mat. Rain and leakage can also soften susceptible ground, and mud pumping beside a mat under loading can indicate movement or loss of support. Verify drainage and grade at the setup location, while applying the manufacturer’s out-of-level limits for the configuration.
When one outrigger or track settles more than the others, differential settlement takes the machine out of level. The tilt changes geometry relative to gravity and can increase radius for a load in the downhill direction. It can cause out-of-plane loading and reduce stability. The result depends on the geometry and the direction of the tilt. Use the manufacturer’s tolerances for the equipment in place.
If support shifts while operating, stop as safely as conditions allow and implement the planned response using the manufacturer’s procedures. The operator retains stop authority. If an operation requires signals and signaling is interrupted, 1926.1419(f) requires a safe stop until signaling is restored and the proper signal is given and understood. Keep personnel clear while the condition is evaluated.
Inspection and follow-up
- Before mobilization, compare the planned reactions and footprint against the available site and utility drawings and ground assessment. Check whether a retaining wall, utility crossing or weak backfill needs separate evaluation.
- At the footprint, look for cracks, depressions, patched trenches, pooling water, new excavation and changes since the assessment. Verify that each mat or foundation bears where the plan assumes it will.
- At each shift, a competent person performs the visual inspection under 1926.1412(d). It includes ground support and settling around outriggers and foundations, and checks level against the manufacturer’s tolerance before each shift and after each move and setup. A safety hazard requires taking the equipment out of service until corrected.
- When the ground is uncertain, stop and resolve the uncertainty with the personnel qualified to assess soil, structures or supports. Seeing no movement during a brief check cannot establish allowable bearing capacity for a different radius, slewing sector or support reaction.
Worked scenario: setup beside trench backfill
A 90-ton rough-terrain crane is scheduled to place precast panels. A planned outrigger is four feet from the centerline of a recently backfilled eight-foot-deep stormwater trench. The setup drawing gives a maximum reaction on that outrigger of 92,000 lb during the planned swing. The only information about the backfill is that the surface was rolled with a backhoe.
The depth and proximity are warning signs. The distance from the centerline alone does not establish a safe setback. Obtain the trench width and route, soil conditions, construction records and any load limits on the stormwater structure. Determine the distance from the proposed support to the affected area. The known 92,000 lb is an input to assessing soil and structure demand. The shallow surface condition, by itself, gives no assurance about the fill, pipe or underlying support.
Hold the setup. If the operator has determined the site fails paragraph (b), the operator’s employer discusses needed preparation with the controlling entity under paragraph (e). Options include relocating to verified ground and recalculating the lift’s chart radius and support reactions, or using a support design whose assumptions and load path are verified for the actual trench and surrounding soil. Recheck the field location and support after the plan is changed.
A controlling entity has authority over ground preparation on a construction site. Under 29 CFR 1926.1402(c)(1), who must ensure the necessary ground preparations are provided?
The controlling entity
The crane operator
The lift director
The rigging supervisor
A soil report classifies cohesive soil near an outrigger footprint as Type A for excavation protection. What does this establish about allowable outrigger bearing pressure?
It establishes an allowable bearing pressure of at least 3,000 psf.
The excavation classification alone gives no allowable outrigger bearing pressure.
It establishes the same allowable pressure as crystalline bedrock.
It establishes the required crane mat area directly.
What is the primary danger when a mobile crane experiences differential outrigger settlement during a heavy pick?
The hoist drum wire rope develops loose spooling grooves
The hydraulic fluid temperature drops below operating range
The crane tilts out of level, which can increase radius or impose side loads
The counterweight tray mechanically binds the swing brake assembly