5.2 Marine & Barge-Mounted Lifting Operations

Key Takeaways

  • Section 1926.1437(m) covers qualifying permanently attached, purpose-designed floating equipment. Paragraph (n) covers land cranes and derricks on flotation.

  • For a land crane on flotation, use the capacity developed for the equipment and specific vessel. Apply the excessive list and trim limits in §1926.1437(n)(3)–(4) together.

  • Check deck loads, list and trim throughout the lift, including the direction of swing and the transfer of weight onto or off the vessel.

  • For work covered by §1926.106, include its flotation equipment, ring buoy and skiff requirements in the rescue preparation.

Last updated: November 2026

Identify the crane and flotation arrangement

29 CFR 1926.1437 supplements Subpart CC for floating cranes and derricks, and land equipment supported by a barge, pontoon or other flotation device. Paragraph (a) excludes a jacked barge when the jacks are deployed to the bed and fully support the barge. Under §1926.1437(m), use the applicable ratings for equipment both designed for this use and permanently attached to its flotation device. Paragraph (n) applies to a land crane on flotation. The fact that a crane is secured to a barge during a job does not turn it into equipment designed for floating service.

For a land crane on flotation, paragraphs (n)(1)–(2) require the capacity reduction to account for operating effects such as list, trim, wave action and wind. The rating must specify the operating locations on the particular vessel and the environmental conditions under which it applies. The manufacturer or a qualified person with expertise in both land crane capacity and vessel stability determines it. Under paragraphs (n)(3)–(4), apply the lower of 5° and the manufacturer’s limit, or the qualified person’s limit if the manufacturer gives no limit. Also satisfy the requirements for keeping the deck above water and the bottom submerged. Paragraph (n)(5) provides several ways to prevent shifting, including physical attachment and corralling, subject to its design and placement criteria. A narrow auxiliary-equipment exception in (n)(6) requires the specified conditions and signed plan.

List is sideways inclination. Trim concerns inclination along the vessel’s fore-and-aft axis. Both can change as the boom swings, even while the load remains at the same indicated radius. For qualifying permanently attached machines under (m), use that paragraph and Table M1. Compare each measured angle with its own limit. Check the equipment’s specific rating and environmental limits as well.

Permanently attached marine equipment under §1926.1437(m)Maximum listMaximum trim
Cranes rated up to and including 25 tons5°5°
Cranes rated above 25 tons7°7°
Derricks of any rated capacity10°10°

Plan both sides of the transfer

Identify both the crane support and the load support at pick, swing and set. On a floating crane, hook load changes how the flotation device sits, and releasing onto the deck shifts that weight to the landing point. For a crane supported on shore or on a trestle that lifts from a vessel, the vessel can move independently of the boom and hook. Consider relative motion from tides, wake and waves. A load can go slack before it has been released and then retension abruptly. Coordinate the crane and vessel crews and plan when the load can be landed or picked without catching or pulling sideways. Include safe escape and stop arrangements for deck personnel.

Section 1437(k) requires the flotation device to withstand the combined operating and environmental loads it will encounter. Check its support and deck loading, verify the intended crane and ballast positions, and include deck cargo, planned swing sectors and concurrent activity. Section 1437(e) requires a list/trim device at the cab or operator station and a positive house lock. A competent person determines whether wind must be considered, which triggers a wind speed and direction indicator. Paragraph (c) addresses swing/crush hazard marking, including training when warning signs and high-visibility equipment markings are used. Paragraph (d) excludes §1425 for this setting. Plan personnel separation based on the applicable rules and the actual landing and swing hazards. Section 1437(h) adds inspections of securing means and flotation conditions to the applicable inspections of the crane.

Worked decision and rescue

A land crane on a specific barge will lift a 130,000 lb load. For a hypothetical gross-rating chart, count 6,500 lb of block and rigging. The lifted demand is 136,500 lb. The capacity developed for this crane on this barge and at the controlling phase is 145,000 lb, so utilization is about 94.1%. A 195,000 lb land rating at the same nominal radius is the wrong basis for this decision. Suppose the approved afloat operating conditions include a maximum of 3.5° and predict up to 2.8° for the planned lift and environment. Compare against 3.5°, verify the submergence and deck criteria, and check every phase including the transfer of weight to the final support. A change in vessel position or environmental conditions can invalidate that comparison. The lift proceeds only if all applicable controls and limits are satisfied.

Where the danger of drowning exists, §1926.106 requires U.S. Coast Guard-approved life jackets or buoyant work vests for employees working over or near water. Inspect flotation gear before and after use. Have readily available ring buoys with at least 90 ft of line and no more than 200 ft between buoys. At least one lifesaving skiff must be immediately available where employees are working over or adjacent to water. Identify how help will reach a worker in the water from the actual deck or shore location.

Test Your Knowledge

Who may develop the capacity reduction for a land crane to be used in specified positions on a particular barge?

A

The crane operator whenever the land chart shows sufficient reserve

B

The manufacturer or a qualified person with expertise in both land crane capacity and vessel stability

C

Any qualified rigger once the crane’s deck restraint is installed

D

The vessel master whenever list stays under 5°

Test Your Knowledge

For a land crane on flotation, the manufacturer permits at most 3.5° of list and trim under the operating conditions. The plan predicts 4°. What is the proper decision?

A

Withhold this lift as planned because 4° exceeds the manufacturer’s 3.5° limit.

B

Proceed because 4° is below 5°.

C

Proceed if crane demand is less than the land chart rating.

D

Use Table M1’s 7° limit if the crane is rated above 25 tons.

Test Your Knowledge

The crew will work next to water where there is a drowning danger. Which group matches the equipment provisions of §1926.106?

A

A buoyant vest only while riding the crane hook, plus one ring buoy onshore

B

Ring buoys with 50 ft of line and use of any vessel that arrives within ten minutes

C

U.S. Coast Guard-approved life jackets or buoyant work vests, ring buoys with at least 90 ft of line and a lifesaving skiff immediately available

D

U.S. Coast Guard-approved vests and an ordinary work boat kept at a remote storage site