5.4 Multiple Load Line Lifts on a Mobile Crane

Key Takeaways

  • Check whether the manufacturer permits the actual combination of drums, load points, boom or jib, and intended movements.

  • Compare each line, reeving arrangement, load point and connection with its own rating. Check the combined demand against the crane’s applicable rating for the operation.

  • Check rope interference, side loading, changing load shares and capacity at each planned stage. Signals must identify the intended function and line.

  • Personnel hoisting has separate load-line restrictions under §1926.1431(k)(11).

Last updated: November 2026

Recognize the configuration

The CCO Mobile Crane Specialty outline includes multiple load line lifts. A single crane may use two separately controlled hoist lines to handle material, for example when two hooks support different points on a member as its orientation changes. That is different from using several parts of one reeved line to increase the hook block’s lifting capacity. It also differs from the multiple-crane operation in §1926.1432, which applies when more than one crane or derrick supports the load.

The fact that a machine has two drums or two hooks does not establish permission to load both at once. Under §1926.1417(a), follow the manufacturer’s procedures applicable to the equipment functions and attachments. Identify the particular machine, counterweight, boom/jib assembly, hoist drums, reeving and load points, and verify that simultaneous operation is permitted in that combination. If the procedures exclude the combination, change the plan or equipment.

Check each load path and the combined chart

The Manitowoc 2250 MAX-ER 2000 operator’s manual, in its section on multiple load line operation, describes use of points on a common shaft or distinct shafts. It directs the planner and operator to use the capacity and wire rope specification charts for the setup and ensure the total load is within the applicable limits. If a line operates from the jib point, that point’s chart must be considered. The manual also calls for checking the routing and reeving for interference and understanding what the drums can do simultaneously. These are examples of model-specific checks.

CheckWhat to verify before lifting
Per lineApproved reeving and parts of line, rope and drum limits at the layers used, hook or ball, attachments and the force on each line.
Crane and load pointsThe chart and configuration that govern the combined load and the use of each point on the boom or jib. Adding capacities from two single-line chart entries does not establish a combined rating.
Path and phasesRadius, boom geometry, line angles, support and changing load share at all stages. Check both blocks for clearance and potential two-blocking, and check the lines for interference as they move.
Crew and operatorAgree on the command for each hoist function and line under the applicable signal rules. Confirm with the operator how the controls and capacity indications work in the permitted configuration.

A device indicating a combined load is insufficient evidence of the individual line forces. If the plan entails transferring weight between the hooks, use a supported load case for each intended stage. If one hook is to support the full load after a release, verify that stage independently. Respect manufacturer limitations on side and forward loads, and do not drag or pull the load sideways. Safely stop operations requiring signals if transmission is lost, then resume once signaling is restored and a proper signal is given and understood under §1926.1419(f).

Worked case: a load shifts to the auxiliary line

These figures are hypothetical for a model authorized for the setup. In both planned phases, the applicable limits on the given gross basis are 32,000 lb at the main line, 16,000 lb at the auxiliary line and 42,000 lb combined. The engineering load case starts with total counted demands of 25,000 lb and 15,400 lb respectively, including hook equipment and rigging as required. The initial 40,400 lb combined demand is 1,600 lb below the combined limit. The main and auxiliary lines both pass the initial check individually.

At a later phase, the plan predicts the main demand will drop to 22,600 lb and the auxiliary will rise to 17,800 lb. The same 40,400 lb total still passes the combined check. The auxiliary limit is exceeded by 1,800 lb, so the later stage cannot proceed as planned. Revise the geometry, sequence or equipment and check each stage again.

Apply the separate personnel restriction

For construction personnel hoisting under §1926.1431(k)(11)(i), do not lift on another equipment load line while personnel are being hoisted. The provision has a pile-driving exception. Paragraph (k)(11)(ii) separately allows a qualifying factory-produced boom-mounted platform's original winch to lift loads while occupied, within 500 lb and both the winch and platform ratings. That provision does not authorize a second material hoist line during an ordinary suspended personnel lift.

Test Your Knowledge

A mobile crane has independently controlled main and auxiliary drums. What must be established before placing loads on both lines at the same time?

A

Each hook is marked with its own capacity, which is all the information needed.

B

The actual configuration and use are permitted by the manufacturer, and each load path and the applicable combined capacity have been verified.

C

The separate chart ratings can be added as long as the lift radius stays constant.

D

A separate operator is available to control each drum.

Test Your Knowledge

During a planned phase the main line carries 22,600 lb against a 32,000 lb limit. The auxiliary carries 17,800 lb against a 16,000 lb limit. The combined limit is 42,000 lb. What determines the decision?

A

The phase is acceptable because 40,400 lb is below the combined limit.

B

The auxiliary is only overloaded if the main line exceeds its own limit.

C

The phase is unacceptable because the auxiliary exceeds its limit by 1,800 lb.

D

The capacity indication can replace calculating per-line forces.

Test Your Knowledge

A mobile crane is hoisting employees in a normal suspended platform during construction work unrelated to pile driving. May the crew use another equipment load line to hoist tools at the same time?

A

No. Section 1926.1431(k)(11)(i) prohibits concurrent lifting on another equipment load line in this setting.

B

Yes, if the separate tool load is below 500 lb.

C

Yes, if both lines together stay below 50% of the crane rating.

D

Yes, provided the hook carrying tools is below the personnel platform.