6.2 Pre-Lift Meetings & Safety Briefings

Key Takeaways

  • OSHA has separate requirements for A/D instruction, power-line planning meetings, personnel-hoisting meetings and multiple-crane plan reviews.

  • For personnel hoisting under §1926.1431(m), hold the meeting before the trial lift at the new work location and repeat it for newly assigned employees. The shift rule in (h) governs the trial lift.

  • Verify signal qualifications and agree on the method, its users and the stop response. Under §1926.1421(b), the voice order is function/direction, distance and/or speed, then function/stop.

  • Set project documentation and communication expectations in advance, and revisit the applicable briefing when responsibilities or plan conditions change.

Last updated: November 2026

Identify the applicable briefing rule

A useful briefing links the planned operation to the people and equipment actually present. Identify the task before deciding who attends and when the discussion takes place. ASME P30.1-2024 has separate provisions for pre-lift review in Standard Lift Plans and pre-lift meetings in Critical Lift Plans. Federal OSHA requirements for specific construction activities apply independently.

Work coveredTiming, participation and subject
Assembly/disassembly, §1926.1404(d)Before work starts, the A/D director ensures crew members know their tasks, hazards and positions to avoid. Provide the instruction when an employee takes an unbriefed assignment or joins the operation.
Power-line A/D under §1926.1407(b)(1)If those encroachment precautions apply, plan with the A/D director, operator, A/D crew and other workers in that area to identify line locations and controls.
Power-line operations, §1926.1408(b)(1)If using Option (2), or if Option (3) requires paragraph (b) precautions because Table A encroachment is possible, conduct a planning meeting with the operator and other workers in the area of the crane or load. Review the lines and how to prevent encroachment.
Personnel hoisting, §1926.1431(m)Meet before the trial lift at each new work location and repeat for newly assigned employees. Include the operator, signalperson if used, employees to be hoisted and the person responsible for the task. Review the rule and procedure. Paragraph (h) separately requires a trial lift immediately before each shift involving personnel hoisting.
Multiple cranes supporting a load, §1926.1432(b)(2)The lift director reviews the plan in a meeting with all workers who will be involved. Verify that everyone understands the shared-load sequence and the signals intended for each crane.

Brief the actual job

  • Load and equipment: Show the load weight, center of gravity, hoist line and chart entries used. Point out where the radius or working quadrant changes and the expected condition at each hold point.
  • People and support: Confirm that workers know the rigging, landing and hazardous positions. Discuss where control lines, barriers or other measures required in the selected setting are placed. Note overhead and subsurface hazards and address the route before lifting.
  • Environment and emergency: Tell the crew which wind or visibility limits apply and how conditions are monitored. Review the planned response to a blocked landing zone, lost signal or equipment issue. Identify a usable landing area if the plan includes one.
  • Signals: Confirm the signal types the signalperson is documented to use, and choose a usable method for the whole path. §1926.1420 requires onsite electronic equipment testing, a dedicated channel subject to the rule’s coordination exceptions, and hands-free reception for the operator. Under §1926.1421, agree on voice signals before beginning. State function and direction, distance and/or speed, then function and stop, in that order. Confirm a language the participants can use effectively. For a slow hoist in a blind area, the signalperson could use “hoist up, slowly for two feet, hoist stop” if the team has agreed to that wording. Brief the operator and the new signalperson together before continuing after a personnel substitution.

Use the site’s attendance or sign-off requirements if they apply and record the plan version used. Have participants describe the operation back to you, especially the first move, who initiates it, and where each worker will be. If the work changes, hold long enough to verify the changed conditions and brief affected personnel. Repeat the voice agreement if signals change, a person is added or substituted, or confusion occurs.

Practice a stop and restart

Suppose the ordinary §1926.1408(b) precautions apply and the operator cannot see the elevated warning line. Review the added dedicated spotter and the separate encroachment measure, and explain how the two work together. The spotter’s clearance assignment is separate from the signalperson directing a blind set. If someone sees a safety problem, give the stop or emergency stop signal and the operator obeys it under §§1926.1417(y) and 1926.1419(j). If the signaling method is interrupted, the operator safely stops operations that require signals until transmission is restored and a proper signal is given and understood. Reconfirm the revised sequence before releasing a hold related to a new hazard. An operator’s §1926.1418 refusal over a safety concern remains in effect until a qualified person determines that safety is assured.

Test Your Knowledge

What meeting trigger does OSHA §1926.1431(m) specify for construction personnel hoisting?

A

Every operating shift solely because a shift begins.

B

Only when the initial proof test fails.

C

Only after the first occupied lift at the location.

D

Before the trial lift at each new work location, with repetition for newly assigned employees.

Test Your Knowledge

Who reviews the plan with all workers involved in a lift where two cranes support one load under §1926.1432(b)(2)?

A

The designated lift director.

B

Any operator, by briefing only their own crew.

C

The controlling entity, by posting a copy without discussion.

D

The qualified plan developer, regardless of the assigned lift director.

Test Your Knowledge

On a job outside Subpart V, §1926.1408(b) applies and the operator cannot see the elevated warning line. What should the briefing confirm?

A

The operator can proceed without a warning-line or clearance plan.

B

The load signalperson should watch the line and rig the load at the same time.

C

Verbal reminders replace all paragraph (b)(4) measures.

D

Use the dedicated spotter and another appropriate measure under §1926.1408(b)(4).