6.3 Plan Deviations, Stop-Work Triggers & Management of Change
Key Takeaways
Stop safely for a hazard or if required signaling is interrupted. Use applicable crane procedures and the actual conditions to select the safe response.
A measurement that contradicts the plan triggers investigation. Follow §1926.1417(o)(3) for load-weight verification.
Changes can affect the load, crew, crane, rigging, radius, support or electrical clearance together. Check every dependency before resuming.
The governing rules and project procedure determine how a changed plan is reviewed, documented and approved.
Identify the changed condition and stop safely
A lift plan describes the conditions on which the chosen equipment, rigging and sequence rely. Stop when a safety concern arises or a change takes the work outside those assumptions. Examples include a load that does not balance as expected, visible movement at a mat, higher gusts, a rigging substitution with different geometry, additional traffic in the path, or interrupted signaling. Determine which requirements and plan assumptions are affected. A replacement signalperson may require a new voice agreement even though weights and radii stay the same.
Under §1926.1419(j), anyone aware of a safety problem alerts the operator or signalperson using a stop or emergency stop signal. The operator obeys it under §1926.1417(y) and has authority under §1926.1418 to stop and refuse to handle loads until a qualified person determines that safety is assured. Follow the crane’s applicable procedures and the actual hazard. Hold safely and keep people clear. Use a planned, safe landing point when the route, support and communication permit it. Under §1926.1419(f) the operator safely stops operations requiring signals if they are interrupted, and resumes those operations after signaling is restored and a proper signal is given and understood.
Review the effects of a proposed change
A project may call its change procedure management of change. Use the applicable procedure and document the assumptions and decisions it calls for.
| Step | Decide what has to be checked |
|---|---|
| Identify and stabilize | Pin down what changed. Protect the people near the crane or load and maintain the applicable stop. |
| Verify facts | Investigate any unexpected weight, settling, equipment response or loss of clearances. Establish reliable input data and check whether other plan assumptions are still valid. |
| Reassess the plan | Recheck the crane chart, load balance and rigging, supports and route affected by the change. If a separate provision applies, such as §1926.1432 for a new two-crane configuration, apply its planning and engineering requirements. |
| Authorize and brief | Obtain the review and approvals for the job and the qualified-person determination where §1926.1418 applies. Use the revised plan and explain the changes to affected personnel before releasing the hold. |
If the cause of a weighing discrepancy is unknown, distinguish an indicator observation from verification. If the operator uses the initial-hoist method in §1926.1417(o)(3)(ii) and the indicated load exceeds 75% of maximum rated capacity at the longest working radius, do not proceed until verifying the weight under (i). That provision accepts an industry-recognized source or method or another equally reliable means. A revised rigging geometry requires a new assembly rating or load-distribution check. A crane reposition also changes the supports and the entire load path, even if it reduces the final radius.
Worked change: unexpectedly heavy heat exchanger
For this hypothetical facility lift the gross chart at the longest planned radius of 55 ft is 100,000 lb. The expected vessel payload is 68,000 lb with a further 12,000 lb that the chart notes call for counting. Planned gross utilization is 80.0%. The facility’s approved plan limits this lift to 85% of gross capacity. During a controlled initial pick, the operator observes about 92,000 lb of gross demand. Pause safely and investigate. In this case the approved landing is the original saddle arrangement and signals remain available, so the crew can return the vessel to those supports under the applicable safe procedure.
The team finds water in the vessel and verifies a revised payload of 80,000 lb using a reliable weight determination. With the same counted allowances, 92,000 lb is a 12,000 lb increase or 15.0% above the planned 80,000 lb demand. Its revised utilization for the same setup is 92.0%, outside the facility’s 85% limit. Moving the crane and rechecking the entire path can reduce the governing radius to 45 ft. With an illustrative gross chart value of 125,000 lb there, the revised utilization is 73.6%.
Lower utilization alone cannot release the replan. The verified maximum reaction for the revised setup is 116,000 lb. If fully effective, a 4 ft by 4 ft support would average 7,250 psf. A 6 ft by 8 ft mat would average approximately 2,417 psf on the same basis before counting any further loads at the surface. That is a screening result. Verify mat strength, effective bearing and site support against the applicable limits. Confirm the bridle assembly and individual hardware for actual leg loads and angles, including where retained water sits during movement. Four legs do not establish equal load sharing. Complete the facility’s required review and explain the changed configuration, allowable path and hold points before resuming.
An indicator shows a load 15% heavier than the approved lift plan during the initial pick. What action is appropriate?
Continue toward the set point at a reduced speed.
Stop safely, protect the area, and investigate before proceeding. Use a safe planned landing if conditions and signals permit it.
Silence the indicator and use the original plan if the crane still feels stable.
Send riggers beneath the suspended vessel to check whether water remains inside.
An updated setup has a confirmed gross chart capacity of 125,000 lb and gross demand of 92,000 lb. What conclusion is supported?
Utilization is 92.0% and the ground support is suitable.
Utilization is 65.0% because the hook and rigging should be counted again.
Utilization is 73.6%; the revised rigging, route, ground support and approvals still need to be verified.
Utilization is 73.6%, permitting the operator to bypass site approval.
A lift will change from one crane to two cranes simultaneously supporting the load. What should happen before the revised lift?
Recheck the entire plan affected by the change, comply with §1926.1432 and review the revised plan with all involved workers.
Keep the one-crane plan and assign a second signalperson without a new plan.
Tell the second operator the payload and let the two operators divide it equally during the lift.
Use the old support calculations because the payload has not changed.