10.1 Single-Crane Mobile Lift Plan Scenarios & Ground Bearing

Key Takeaways

  • Review all loaded phases, including the transition between sectors. Use the manufacturer’s chart method for actual operating radius and configuration.

  • Check the envelopes of the boom, counterweight, load, hook and rigging throughout the lift using site and equipment clearances.

  • Crawler track contact pressures can be nonuniform. Use configuration-specific track reactions and pressures for the lift and travel path.

  • Passing the crane chart check does not establish adequate ground support. Verify the ground and supporting materials separately.

Last updated: November 2026

Review each phase of the single-crane plan

A crane may start a lift within its rating but encounter a limiting radius, quadrant or clearance before the load lands. For each phase, match the actual model, boom and jib arrangement, counterweight and support configuration to the chart. For a crawler, verify the allowed track position and whether the crane will lift while stationary or travel with the load. For a hydraulic mobile crane, use the chart for the actual outrigger position or allowed on-tire arrangement. Confirm whether the crane can achieve the required reach without exceeding manufacturer restrictions.

Review itemQuestion to answer
Chart and load basisWhat radius, sector and configuration limit the operation? What payload and gear or deductions must be counted for the selected chart?
Loaded envelopeWhere are the boom and attachments, hook, rigging, load, and the rotating superstructure at each stage? Is there room for expected deflection and controlled load motion?
SupportWhat loads and contact pressures occur at the tracks, mats or floats for the planned lift and travel phases? What ground conditions and design limits govern those locations?
Site and peopleCan ground traffic be diverted? Can the operator and signalperson see or reliably communicate through each phase? Is a safe landing point available if the final location is blocked?

For the radius check, use the loaded geometry and the applicable chart notes. Deflection can move the boom point outward as the crane takes load, but the effect depends on the configuration and conditions. If the planned loaded radius would place the crane outside the rating, change the plan before attempting the pick. The same reasoning applies if the lift starts within capacity but would reach a lower rated position in the swing or at final set. §1926.1417 requires compliance with manufacturer procedures and rated capacity.

Check clearances for the actual load shape, motion and equipment with the site and equipment requirements. Confirm that fixed obstructions remain clear and apply separate electrical clearances if relevant. Use §1926.1424 controls for the rotating-superstructure hazard area and arrange the load path to minimize exposure under §1926.1425. Make sure traffic controls cover the job’s actual work area, including the tail swing and set position.

Evaluate crawler ground support

Manitowoc’s ground bearing pressure estimator uses the selected crane, crawler position, counterweight, attachments, surface, load and radius, and can consider swing angle. A dimension-based average may conceal high pressures along particular parts of the tracks. As the boom rotates or the load radius changes, the resultant forces beneath and along each track can change. Compare the controlling pressure and loading profile for actual lift and travel phases with the site’s approved support limits. Under §1926.1402, the ground must provide adequate support with supporting materials if necessary to meet manufacturer requirements.

Worked decision: 45-short-ton transformer

A hypothetical crawler setup will hoist a 90,000 lb transformer and counts 8,000 lb of block and rigging. It uses a 120 ft lattice boom. The planned controlling loaded radius is 55 ft and, for this exercise, the applicable gross chart entry is 118,500 lb. 98,000 ÷ 118,500 = 82.70% of gross rating. This comparison only establishes the capacity result at the stated phase. Verify other phases, any site-specific utilization limit and independent line and rigging constraints.

Assume a 210,000 lb operating crane weight excluding the block and rigging already counted, with two 24 ft by 4 ft nominal track footprints. The combined weight is 308,000 lb and the nominal area is 192 ft². The quotient, about 1,604 psf, is a simple average with that footprint. A configuration-specific evaluation finds a 3,900 psf peak in the unpadded setup. The project’s allowable pressure at the applicable bearing plane is 2,400 psf. The average is lower than the allowance but the predicted peak exceeds it by 1,500 psf. Hold the lift as planned.

The revised project support design evaluates mat flexure, bearing area, local pressure and settlement. If that design verifies a maximum of 1,850 psf for the approved installation and phases, the peak comparison is 550 psf below the stated allowance. Confirm the as-installed arrangement, underlying site conditions and any restrictions in the support design, and monitor for changes. This peak is a result supplied for the revised example. Multiplying total nominal mat dimensions does not reproduce it.

Test Your Knowledge

A proposed 25,000 lb gross load would have a loaded radius of 50 ft. In the selected chart, the 48 ft entry is 27,200 lb and the 50 ft entry is 23,800 lb. The empty hook is at 48 ft. What is the proper decision?

A

Change the lift before the pick because the proposed loaded radius permits only 23,800 lb.

B

Use the 48 ft reading because it was measured before the crane took load.

C

Average the two entries and proceed if the result is above 25,000 lb.

D

Proceed with a lower slew speed while leaving the planned radius and setup unchanged.

Test Your Knowledge

Why can the two-track average pressure be insufficient for checking crawler support?

A

Both tracks always carry identical loads once the boom is horizontal.

B

Footprint area always equals effective bearing area.

C

Individual track reactions and local pressures can change with load, radius and swing position.

D

The chart’s maximum capacity measures the supporting soil pressure.

Test Your Knowledge

A transformer case passes the gross rated load check at a lift phase but the predicted unpadded peak ground pressure is 3,900 psf against an allowable 2,400 psf. What should the lift director conclude?

A

Proceed because the equipment is below 85% of the rated capacity.

B

Allow the mats already on the site regardless of their design.

C

Compare only the average nominal ground pressure because the crane is on tracks.

D

Hold the lift as planned and verify adequate support, a revised setup or a revised path before proceeding.