4.3 Multi-Crane & Tandem Operations

Key Takeaways

  • Under OSHA 1926.1432, a qualified person develops the multiple-crane lift plan, and the employer provides engineering expertise when that person determines it is needed.

  • The person directing a multiple-crane lift must meet both competent and qualified person criteria or be a competent person assisted by one or more qualified people. Review the plan with all workers involved.

  • For a static load supported by two separated vertical forces, each share depends on the moment arm of the load about the other support.

  • For ideal collinear pick points and center of gravity, tilting with both forces vertical scales both moment arms equally. Reaching vertical alone does not establish how the cranes share the load.

  • Check each planned stage against the actual chart basis, rigging, ground and line-pull limits, and use the load-transfer and release criteria specified by the plan.

Last updated: November 2026

Plan development and implementation

Two cranes sharing a load have coupled demands. A change in lift geometry, line angle, motion or support conditions can invalidate a load estimate for either machine. OSHA 1926.1432 applies when more than one crane or derrick supports the load.

  • Develop the plan. A qualified person develops a plan that meets Subpart CC. The employer obtains engineering expertise if the qualified person determines it is needed. OSHA's construction crane compliance directive explains that §1926.1432 itself does not require the plan to be written. Other applicable requirements or the project may specify a written plan and engineering approvals.
  • Direct the operation. Assign the lift director as required by paragraph (b)(1): a person meeting both the competent and qualified person criteria, or a competent person with one or more qualified assistants. Before the lift, the lift director reviews the plan in a meeting with all workers involved. Review the machine positions and configurations, rigging, travel and landing sequence, and signals for movement, hold and stop.
  • Coordinate signals. Under 1926.1419(m), when a signalperson is communicating with more than one crane, identify the intended crane before giving the function and direction for each signal or use an equally effective identification method. One person normally signals each crane at a time. Under 1926.1420, a dedicated channel may be shared to coordinate multiple cranes. Agree on signals, test electronic equipment at the site, and arrange hands-free reception for the operators. Operators obey stop or emergency stop signals, and safely stop operations requiring signals if communications are interrupted.

Calculate the horizontal static shares

Assume a rigid load at rest or in quasi-static equilibrium, supported only by two vertical hoist forces in the same vertical plane. The horizontal distance between the vertical force lines is LL, with the center of gravity between them. The weight is WW, and distances from A to the center of gravity and from it to B are dAd_A and dBd_B. Then L=dA+dBL=d_A+d_B. A moment balance about B eliminates the force at B so the share at A is WA=WdB/LW_A=Wd_B/L. A moment balance about A gives WB=WdA/LW_B=Wd_A/L. Check that WA+WB=WW_A+W_B=W. See the rigid-body equilibrium equations.

A       center of gravity                B
↑               ↓                        ↑
|<--- d_A ----->|<--------- d_B -------->|

For a 100,000 lb vessel with 60 ft between pick points, the center of gravity is 20 ft from A and 40 ft from B. A carries 100,000(40/60)100{,}000(40/60), about 66,667 lb; B carries 100,000(20/60)100{,}000(20/60), about 33,333 lb. The pick point closer to the center of gravity carries the greater share in this model. Take the moment about the other pick point. Dividing the load equally would understate crane A's demand by about 16,667 lb.

Verify demand on each chart

Under the example’s gross chart convention, add 2,500 lb of hook block and 800 lb of rigging at A, and 1,500 lb of hook equipment and 500 lb of rigging at B. The resulting initial gross demands are about 69,967 lb and 35,333 lb. Check each against the applicable chart at its initial radius and actual setup, and check hoist line pull, attachment and rigging limits. Reconcile the chart’s notes for any other required deductions. Plan limits or restrictions can be more conservative than the chart. The federal multiple-crane provision sets no universal 75% or 80% capacity factor.

A trial movement may help verify clearances, visibility and communication if it is part of the plan. Analyze the actual loads, inertia, support reactions and geometry separately. 1926.1417(q) prohibits dragging or pulling loads sideways. Plan how to maintain the load-line geometry the crane is designed to accept and assess the effect of any stop, restart or mismatch in movement.

Upend and release according to the planned load cases

A main crane may attach near the top of a vessel while a tail crane controls its lower end. An engineered sequence specifies how the equipment moves and how support shifts before releasing the tail rigging. Do not calculate a progressive transfer by treating a shrinking horizontal moment arm as a shrinking hook force. For example, if both pick points and the center of gravity are on the vessel axis and both forces remain vertical, inclining by an angle θ\theta from horizontal multiplies both relevant moment arms by cos⁡θ\cos\theta. The factor cancels for separations greater than zero. At exactly vertical in this idealized model, the force lines coincide. Moment equilibrium alone then does not determine the split. Off-axis geometry, support contact, the rigging and the controlled unloading sequence can all change the real result.

Check initial lift, intermediate angles and radii, controlled transfer and final placement. Before disconnecting the tail rigging, verify the prescribed transfer and stability conditions. Once the main crane alone supports the example vessel, its gross demand is 103,300 lb including the same 3,300 lb of hook equipment and rigging. Check that demand at the radius where the main crane actually has full support and at subsequent radii through set-down. A final chart rating is not enough by itself to establish that the intermediate stages are acceptable. If the plan lacks reliable load cases and release criteria, hold the operation and have the planning team resolve them.

Test Your Knowledge

Under OSHA 1926.1432, how is a lift in which two cranes support the same load planned and directed?

A

Each operator develops and follows a separate plan for their own crane

B

A competent person can develop the lift plan solely by virtue of that designation

C

A qualified plan developer may skip the meeting if each operator receives a drawing

D

A qualified person develops the plan, and a competent and qualified lift director or a competent lift director assisted by qualified personnel reviews it with all workers involved

Test Your Knowledge

Two mobile cranes support a 100,000 lb horizontal vessel in static equilibrium by vertical hoist forces. The pick points are 60 ft apart and the center of gravity is 20 ft from A and 40 ft from B. What vessel load does A carry before adding rigging and hook equipment?

A

33,333 lb

B

66,667 lb

C

50,000 lb

D

80,000 lb

Test Your Knowledge

A vessel being upended reaches vertical while both cranes are attached. What establishes that the tail rigging can be released?

A

The vessel reaching vertical automatically places its full weight on the main crane

B

The final placement radius is shorter than the initial radius

C

The tail operator can see the main crane’s boom

D

The lift plan’s load-transfer and stability criteria are verified, and the main crane’s capacity is confirmed for the ensuing full-load positions