10.3 Multi-Crane Mobile Lift Scenarios & Load Sharing

Key Takeaways

  • Under §1926.1432, a qualified person develops the shared-load plan, with engineering expertise when that person determines it is needed. The lift director reviews the plan with all involved workers.

  • In the collinear two-vertical-support model, both horizontal lever arms shrink by the same factor as the column rotates. Angle alone does not define transfer.

  • Use the plan’s actual load cases, radii and support arrangements for each crane and each stage, including the first time the main crane takes the full weight.

  • Do not infer readiness to release tail rigging from a vertical vessel. Verify the plan’s load-transfer, stability and release criteria.

Last updated: November 2026

Set up the load cases and decision points

Before multiple cranes support one load, §1926.1432 requires a qualified person to plan the operation. Obtain engineering expertise if that planner determines it is needed. The lift director meets the competence and qualification criteria in (b) and reviews the plan in a meeting with all involved workers. Decide how the cranes will coordinate, identify the intended crane for each signal under §1926.1419(m), and define hold, transfer and release criteria. One person may signal a crane at a time, with the stop-signal exception. Apply the relevant rules and the agreed schedule of moves if communications are interrupted.

Determine which force paths exist at each stage. On the transport, the saddles can support part of the load. Once free of the saddles, the cranes provide the support assumed in the initial model. During upending, actual forces can depend on contact with a support, noncollinear geometry, rigging constraints or dynamic effects. Do not use planned travel, booming or other motion unless permitted by the equipment and accounted for by the plan. For a crane that will travel with load, check §1926.1417(u) and its applicable chart and procedures. Check ground and line limits and ensure the equipment is not used to drag or pull the load sideways.

Start with the supported equilibrium calculation

Consider an 80,000 lb distillation column free of its saddles and held horizontal in quasi-static equilibrium. The main and tail forces act vertically, the pick points and the center of gravity are collinear, and the distance between the two pick points is 90 ft. The center of gravity is 36 ft from the main and 54 ft from the tail.

Taking moments about the tail gives main support 80,000 × 54 ÷ 90 = 48,000 lb. The tail supports 32,000 lb. Under this example’s chart conventions, add 6,000 lb of counted main block and rigging and 2,800 lb of counted tail block and rigging. Initial gross demands are 54,000 lb and 34,800 lb. Check the hardware and hoist limits independently of the chart demand.

At 45°, if the same idealized assumptions still hold, both the 54 ft and 90 ft moment arms are multiplied by the cosine of 45°. The ratio stays 54/90, so the idealized column shares are unchanged. At exactly vertical the two vertical lines of action coincide in this model, and the moment equation no longer determines their shares. Once the main crane is verified to support the full column during the planned transfer, the gross main demand is 86,000 lb. The tail crane may still carry its own gear. The plan must establish intermediate loads and transfer rather than infer them from inclination.

Check the earliest full-support position

For this exercise, assume the facility limits each crane to 75% of its gross chart rating and the crane charts supply the example values below. This cap is a hypothetical site condition, not a percentage set by §1926.1432.

PhaseMain craneTail crane
Initial horizontal lift-off54,000 lb ÷ 99,000 lb = 54.55%34,800 lb ÷ 52,000 lb = 66.92%
Intermediate rotationVerify loads and ratings for the planned geometry, including line and support reactions.Verify loads and ratings with the same supported model or separate engineered cases.
Proposed first full main support86,000 lb ÷ 112,000 lb = 76.79%, above the facility cap.Verify that the tail no longer supports the column and that the gear can be released safely.
Later at the set position86,000 lb ÷ 124,500 lb = 69.08%.No column load after a verified release.

The minimum gross rating for 86,000 lb at the facility cap is 86,000 ÷ 0.75 = 114,667 lb, rounded up to the next whole pound. The later set position meets that criterion but cannot excuse the failed earlier phase. Revise the setup or transfer position and re-evaluate the whole sequence before work. After the revised plan is briefed, verify the actual support and release criteria before disconnecting the tail rigging. The crew needs a supported load and acceptable capacity at the time and radius where the transfer occurs.

Test Your Knowledge

An 80,000 lb horizontal column is free of its saddles and supported only by two vertical hoist forces. The pick points are 90 ft apart and the center of gravity is 36 ft from main and 54 ft from tail. What are the initial shares, excluding rigging?

A

Main 32,000 lb; tail 48,000 lb.

B

Main 40,000 lb; tail 40,000 lb.

C

Main 48,000 lb; tail 32,000 lb.

D

Main 56,000 lb; tail 24,000 lb.

Test Your Knowledge

An idealized column has collinear pick points and center of gravity. The two hoist forces are vertical and the column remains in quasi-static equilibrium. At 45° instead of horizontal, what happens to the ratio of the moment arms that determines the split?

A

It doubles and the main takes the entire load.

B

It is unchanged because both arms have the same cosine factor.

C

It goes to zero because the tail arm disappears.

D

It increases by half because the tail brake must be released.

Test Your Knowledge

The main crane takes 86,000 lb gross first at the planned transfer point where the gross chart allows 112,000 lb. At the set point the chart allows 124,500 lb. The site caps gross utilization at 75%. What is the result?

A

The transfer passes because the set point has sufficient rating.

B

The two chart entries can be averaged, which permits the transfer.

C

Only the initial horizontal load share needs to pass.

D

The transfer must be revised because 86,000 ÷ 112,000 is about 76.8%.