6.2 Construction Work Design and Management

Key Takeaways

  • The CDM Regulations came into operation on 1 June 2024. Start with their duties and apply the domestic-client provision where relevant.

  • For a project involving more than one construction work contractor, check the written appointments required by regulation 7. Regulation 8 notification is a separate test based on working days or person-days.

  • The construction work designer must be satisfied the client is aware of their duties before commencing work on the project. Design out risks where practicable and communicate what remains.

  • Distinguish pre-construction information, the construction phase plan and the safety and health file by when each is created, who keeps it current and how it is used.

Last updated: November 2026

Commencement and allocation of roles

The Occupational Safety and Health (Construction Work) (Design and Management) Regulations 2024, P.U. (A) 147/2024, came into operation on 1 June 2024. They apply to places of work where a project is carried out. Part II gives client duties, Part III addresses duty-holder roles, Part IV covers general requirements for construction sites, and Part V includes safety assistance and site safety supervision. The pre-construction phase can include design and preparatory work continuing during construction. If the contractor proposes a design change during that period, reassess its effects on the design and construction controls.

The client establishes the project arrangements

Under regulations 4–6, the client provides and reviews management arrangements including sufficient time, funds and resources and the required welfare facilities. The client provides pre-construction information as soon as practicable to designers and contractors appointed or being considered. Utility plans, as-built structural records and investigation reports can help them identify foreseeable risks. The client must ensure the construction phase plan is drawn up before the construction phase begins, and check the safety and health file requirements and the specified duties of those appointed.

Under regulation 7, where there is more than one construction work contractor or that is reasonably foreseeable, the client appoints in writing a principal construction work designer (PCWD) with control of the pre-construction phase and a principal construction work contractor (PCWC). Make the appointments as soon as practicable before the construction phase begins. If a commercial client fails to make a required appointment, regulation 7(3) assigns the applicable duties to it. Regulation 9 supplies different rules for a domestic client, including who carries out duties under regulations 4–6 and 8 and who takes the principal roles if appointments were omitted. Identify that status from the facts before applying regulation 7(3).

Under regulation 8, notify the Director General in writing as soon as practicable before the construction phase when the work is scheduled to last longer than 30 working days or exceed 500 person-days. Use the Third Schedule particulars and follow the applicable display and update requirement. Any day or part-day when someone is expected to carry out construction work counts towards person-days as defined. The two thresholds operate independently.

Prevention through design and document responsibilities

Under regulation 11 a construction work designer (CWD) must be satisfied that the client knows their duties before commencing work in relation to the project. In preparing or modifying a design, take account of the First Schedule prevention principles and pre-construction information. Eliminate foreseeable risks so far as practicable for those carrying out or affected by construction, those maintaining or cleaning, and those using a structure designed as a workplace. If elimination is impossible, reduce or control risks through design where practicable, inform the PCWD and ensure appropriate information goes into the safety and health file.

Project record or roleResponsibility in the stated multi-contractor project
Design coordination and informationUnder regulation 12, the PCWD plans, manages and monitors the pre-construction phase, coordinates designers, assists in providing pre-construction information, and shares relevant risks and information with the PCWC.
Construction phase planUnder regulation 13 the PCWC prepares it or arranges for preparation before setting up the site and keeps it updated. The PCWD assists by providing information. On a single-contractor project, the contractor prepares or arranges the plan under regulation 17(1)(d).
Safety and health fileUnder regulation 14 the PCWD prepares and updates it, with relevant information from the PCWC. If the PCWD appointment ends early, the PCWD hands it to the PCWC to update. The responsible PCWD or, where there is none, the PCWC presents it to the client at completion.
Site coordinationRegulations 15–17 address coordination, consultation and safe work. A contractor must confirm client awareness before carrying out construction work and comply with the relevant plan and directions. Regulation 39 requires the PCWC to appoint a competent site safety supervisor.

Worked example

A commercial warehouse extension in Penang will last 28 working days, with 19 people expected to undertake the work each day and no additional person-days. The programme totals 532 person-days, so written notification is required even though the working-day threshold is not exceeded. A principal designer and contractor are required if more than one contractor is reasonably foreseeable. For the extension, the designers can move maintenance points away from a roof edge, reducing the need for later edge exposure. They should convey the remaining access risk and the inspection information needed by the construction and maintenance teams. Revisit the construction phase plan if the new access route affects the site layout.

Identify the specific regulation for a sanction. The maxima in regulation 7(4) for appointments are RM500,000 and one year's imprisonment, in the alternative or together. Regulation 8(3) sets RM100,000 and one year for its notification offence. Regulation 11(5) sets RM200,000 and one year for its design duty offence.

CDM 2024 Regulations and schedules

Loading diagram...
Records for a multi-contractor CDM project
Test Your Knowledge

Before doing construction work design for a commercial rail facility, what does regulation 11(1) require the designer to establish?

A

The client is aware of its duties under the regulations

B

An SHO has already filed the construction phase plan with the Director General

C

The client has a certificate of fitness for all eventual lifting plant

D

A letter of award has already been issued to each trade contractor

Test Your Knowledge

A commercial project is scheduled for 25 working days with 21 workers expected each day and no other person-days. What does regulation 8 require?

A

No notification because the schedule is 30 working days or fewer

B

The PCWC must notify based solely on the total contract price

C

The client must notify in writing before the construction phase because there are 525 person-days

D

Notice is required only if the work also exceeds 30 working days

Test Your Knowledge
Matching

Match each CDM record or requirement to the responsible actor for a multi-contractor commercial project.

Match each item on the left with the correct item on the right

1

Early pre-construction information under regulation 5(1)

2

Construction phase plan before site setup under regulation 13(1)

3

Safety and health file under regulation 14

4

Site safety supervisor under regulation 39

Sections you finish are checked off in the contents.