5.3 Building, Earthworks and Structural Inspection
Key Takeaways
Check Act 133 and the by-laws in force at the site. In Selangor, building and earthworks approvals, the building start notice, and the CCC each serve a distinct function.
Section 70A requires prior earthworks approval where applicable and provides immediate cessation powers in specified circumstances.
Section 70B addresses suspected structural failure during erection through a review by a qualified person other than the original submitting person. Section 85A creates a notice-driven inspection route for qualifying completed buildings and slopes.
Section 71 requires proof of the failure, statutory cause and responsible person. The maximum penalty differs from sections 70(27) and 70A(9).
Select the applicable law and plan route
In a Selangor local authority area, check the Street, Drainage and Building Act 1974 (Act 133) and the Uniform Building By-Laws in force in Selangor. Section 133 enables building by-laws. The model text and amendments need the relevant gazetted application. Kuala Lumpur has its own building by-laws. For Sabah use the applicable Sabah ordinance and Uniform Building By-Laws 2022, subject to the approval and transition history. For Sarawak check the Buildings Ordinance 1994 (Cap. 8) and its Fourth Schedule. The 2025 Act A1773 amends sections 47 and 48 and inserts section 125A, with locality-specific commencement and scope including Labuan. Use it for the provisions it changes. The building, earthworks and inspection sections considered here are unchanged by it.
Under section 70(1), obtain written permission from the local authority before erecting a building. Check the building plan submission and accompanying declarations under the applicable by-laws, including Selangor Form A where prescribed. A proper professional submission depends on the scope and authority of the signatory. Section 70(9) requires four days' written notice for commencement or resumption of the relevant work. Selangor by-law 22 uses Form B for building operations. Section 70(9A) requires submission of the detailed structural plans, legible structural calculations and other particulars required by the authority before erection. A later change must be checked against the approved plans and relevant approval procedure before being built. The authority can inspect and require rectification under section 70D.
For new private streets check section 9 on plans and specifications. Sections 11–13 address works to private streets and the procedures by which they may be declared public. Parts III and IV separately address drains and back-lanes. On a site with an existing road, identify who owns the street, who approves the work and whether any formal takeover has occurred. For example, section 28 allows the authority to repair a public street or certain adjoining features damaged by an excavation on neighbouring land and recover the costs from that landowner.
Compare earthworks, structural review, failure and inspection
| Provision | Trigger and action |
|---|---|
| Section 70A, earthworks | Excavation, filling and piling can fall within section 70A(18). Obtain approved plans and specifications before commencing where the provision applies. Check section 70A(2) for simultaneous submission of related construction plans where required. Under section 70A(4), the authority can order immediate cessation where it certifies safety of life or property is or is likely to be affected. Subsection (5) provides direction and cessation powers. Check applicable minor or temporary work exemptions. |
| Sections 70B–70C, during building erection | If the authority reasonably suspects a structural defect, deformation or deterioration likely to lead to failure, it can order the owner to obtain a safety and stability review. A qualified person other than the original submitting person must do it. The statutory process can lead to cessation or directions. Revocation under section 70C follows a conviction under section 70B(15). |
| Section 71, actual failure | A building or earthwork, or any part, can fail during work or after completion. Where the cause fits misconstruction, lack of proper supervision, misdesign, miscalculation or misuse, identify the responsible person. The maximum fine is RM500,000, with up to ten years' imprisonment or both. |
| Section 85A, completed building or qualifying slope | Applies to buildings exceeding five storeys, counting storeys at or below ground-storey level, and to land with slope exceeding both 25 degrees and 10 metres total vertical height. The authority may send a written notice. The owner then appoints an engineer as defined in subsection (1), a registered Professional Engineer, to inspect within the time specified. The building first-inspection window is after the tenth year from CCC issuance, then intervals no longer than ten years from the last completed inspection. The slope first window is after five years from possession, then intervals no longer than five years from the last completed inspection. |
Worked example: two properties and separate inspection dates
An engineer receives two enquiries. Cracking and deformation appear in concrete under erection at the first site. If the local authority issues a section 70B order on the stated ground, the owner appoints a qualified person who did not prepare and certify the original submission. The reviewer addresses the building, foundation and surroundings within the time set by the authority. At the second site, a seven-storey occupied building last inspected on 1 February 2023 receives a section 85A notice. The ten-year limit puts the latest date at 1 February 2033. The owner must also meet any earlier deadline specified in the notice. The engineer begins with the prescribed visual inspection and requests permission for a full investigation where subsection (6)(c) applies.
Keep occupation distinct from inspection. Section 70(27)(f) creates an offence for occupying or permitting occupation without a CCC where the Act 133 CCC route applies. The maximum is RM250,000, ten years' imprisonment or both. Under section 70A(9), contravening the earthworks section or failing to comply with a direction or order can instead carry up to RM50,000, five years' imprisonment or both, plus a daily continuing fine where applicable.
Act 133, sections 9, 11–13, 28, 70–71, 85A and 133 · Act A1773 amendment text · KPKT state gazette index · Selangor building by-laws · Sabah building by-laws · Sarawak Buildings Ordinance
On a Selangor building project, the developer permits occupation of apartments before any CCC for that area. The current CCC route applies. What is the maximum penalty for the specific offence under section 70(27)(f)?
RM250,000 fine, up to ten years’ imprisonment or both
RM50,000 fine, up to five years’ imprisonment or both
RM100,000 fine, up to five years’ imprisonment or both
RM500,000 fine, up to ten years’ imprisonment or both
The Joint Management Body of a completed six-storey Selangor building receives a local authority notice eleven years after the CCC was issued requiring structural inspection. Which provision supplies that building inspection mechanism?
Section 70A, approval and control of earthworks
Section 70B, safety and stability review during erection
Section 85A, written notice for qualifying completed buildings
Section 71, liability for actual building or earthwork failure
Which three statements fit the rules for a Selangor project governed by Act 133 and the Selangor building by-laws?
Select all that apply
Under section 70A(9), unauthorised earthworks can attract a maximum fine of RM50,000, up to five years’ imprisonment or both
The federal model by-laws apply in Selangor upon publication of the model without checking the state instrument
Under section 70B a structural review in the stated circumstances must be by a qualified person other than the original submitting person
Under by-law 22, when work does not start on the building date in Form B, a further Form B notice precedes the new start
A basement is excluded from the section 85A storey count