4.4 Stage Certification and Filing the CCC

Key Takeaways

  • Use the project’s gazetted forms to identify the scope, signers, verification and enclosures for each certification. State requirements can differ.

  • For the Selangor example, an applicable G17 relies on the required authority confirmation or the specific 14-day deemed-confirmation rule in the form.

  • Where a Form G stage does not apply, complete the prescribed declaration through the Principal Submitting Person. A missing certification for applicable work cannot be treated as inapplicable.

  • Selangor by-law 25(3) requires the PSP to deposit the CCC or partial CCC and G1–G21 with the local authority and the applicable professional board within 14 days of issue.

Last updated: November 2026

Track records, signatures and clearances

The Principal Submitting Person (PSP) assembles the support needed before issuing a Certificate of Completion and Compliance (CCC). The current gazetted by-laws for the project determine the applicable conditions. The Department of Local Government lists separate state texts and amendments. The table below uses the Selangor Uniform Building By-Laws 1986 as a worked example. The stage scopes help identify evidence. Read the actual form for who must sign and which attachments apply.

FormsSelangor stage certifications
G1–G4G1 earthworks, G2 setting out, G3 foundations, G4 structural
G5–G8G5 internal water plumbing, G6 internal sanitary plumbing, G7 internal electrical, G8 passive firefighting
G9–G12G9 active firefighting, G10 mechanical ventilation, G11 lift/escalator installation, G12 building
G13–G16G13 external water supply, G14 sewerage reticulation, G15 sewerage treatment plant, G16 external electrical supply
G17–G21G17 road and drain, G18 street lighting, G19 external main drain, G20 telecommunications, G21 landscape

A document check concerns both the work and the person who signs. G3 relates to foundations and its evidence can include the foundation records inspected under the applicable requirements. G11 concerns lift or escalator installation. Where the form applies, the Selangor G11 calls for the Department of Occupational Safety and Health certificate of fitness. For G8 and G9, check the Fire and Rescue Department attachment rule and the residential height exception. G13 concerns external water and the form addresses confirmation by the water authority. G16 addresses readiness for connection of the external electricity supply. A presence check for forms will miss issues such as a reused clearance from the wrong phase, an outdated approval number or the wrong signatory.

A genuinely inapplicable stage

Where the state has adopted the relevant 2021 amendments, apply the signatory checks in BEM Circular 013. The PSP or SP verifies the credentials of the contractor and site supervisory signatories. The circular identifies forms and project-value categories for CIDB personnel and directs the certifier to check the latest designations. For projects with multiple site supervisory staff it calls for a signed responsibility matrix and endorsement of the applicable form by the most senior staff member. Use the adoption date and the locally prescribed form before carrying these requirements into a project file. BEM Circular 013

If a project includes no lift or escalator, the PSP can use the applicable inapplicability declaration in Form G11. Review the approved scope and document the reason. A lift that exists but lacks its required verification is still applicable. It needs the applicable checks and attachments. Use the same reasoning for an absent sewerage treatment plant versus a plant that was included in the approved scheme but is awaiting clearance. The stage form guides show who signs the prescribed declaration.

Two separate 14-day periods

For an applicable G17 in the Selangor worked example, the form calls for a confirmation letter from the relevant local authority or the Public Works Department. If the Submitting Person does not receive the letter within 14 days from the date of application, the form provides for deemed confirmation. The file should identify the proper authority, date and receipt evidence for the application and any actual response. That rule supplies confirmation for G17. The certification of the road and drain works and the remaining requirements for issuance still have to be met.

The other clock starts at issuance. Under Selangor by-law 25(3), the PSP deposits a copy of Form F or F1 with G1–G21 to the local authority and the Board of Architects Malaysia or Board of Engineers Malaysia, as applicable, within 14 days of issuance. Follow the local authority and board’s submission channels. For example, Majlis Perbandaran Selayang publishes a local One Stop Centre form for lodgement. Check both destinations and retain proof of the deposit.

Worked review before issue

A project team has signed the applicable building and services stages. Its inspection log shows that the lift and its clearance are still outstanding. An earlier, properly filed G17 application falls within the specific deemed-confirmation provision, and 20 days have passed with no reply. Apply the rule to G17 and retain the filing evidence. The missing lift evidence is a separate matter. Review whether the statutory requirements for the particular certificate are met once the lift evidence and any other required technical conditions are addressed. A client’s requested move-in date does not complete the record.

As PSP, compare the approval number and site scope on each stage document. Review authority conditions and evidence of available essential services before issuing. Use an issue and deposit record that ties the date, project revision and supporting documents together. If an authority directs the PSP to withhold issuance, resolve and document the noncompliance through the local procedure.

Selangor Uniform Building By-Laws, by-laws 25 and 27 and Second Schedule · BEM Form F and F1 guide · BEM stage form guide · Gazetted state by-laws and amendments · Selayang One Stop Centre forms

Loading diagram...
Stage evidence and CCC filing in the Selangor example
Test Your Knowledge

On a project governed by the Selangor form, G17 is applicable. The SP submitted the proper confirmation application 20 days ago and received no reply. What follows from the G17 footnote?

A

The G17 confirmation is deemed given. The remaining certification and issuance conditions still apply.

B

The entire building is automatically certified

C

Every other technical agency clearance is also deemed given

D

The road and drain works are now an inapplicable stage

Test Your Knowledge
Ordering

Put the Selangor Form F workflow in order for a project with all conditions eventually met.

Arrange the items in the correct order

1

The PSP issues Form F

2

The PSP verifies the evidence, applicable technical conditions, services and basis for issuance

3

The PSP deposits the certificate and stage forms with the required recipients

4

The relevant stage certifications and supporting records are completed

Test Your Knowledge

A Selangor project has no lift or escalator in the approved design and no such installation. How should the G11 stage be accounted for?

A

Make up a contractor’s signature to complete the form set

B

Ask the electricity supplier to sign for the missing lift

C

Use the prescribed inapplicability declaration signed by the PSP

D

Code the form as complete without recording why it is inapplicable