9.2 Design Stage II & Tender Stage
Key Takeaways
Design Stage II prepares detailed documentation and applicable authority calculations. Tender Stage evaluates tenderer suitability and the relative merits within the adopted basic scope.
Form 1999 clause 5.7 requires written client instructions before the engineer accepts a tender on the client’s behalf.
The 1998 general notification apportions 20% to Design II and 5% to Tender. Check separate fee provisions for bar bending schedules and interrupted tendering.
Turn the coordinated scheme into a detailed package
Under Part A 1(2)(b)(ii) of the 1998 general fee notification, the structural engineer prepares the calculations and details required for submission and the sufficiently detailed drawings for construction, and advises on conditions, specifications, tender forms and invitations. The Type A Design Stage includes preparing the works design, drawings and pricing documents. For Type C the Design Stage includes preparing authority calculations and details, schedules and specifications, and advising on the contract conditions. Check the scope adopted for the discipline.
A design package should identify the governing brief, the proposed design and the current revision of each drawing and specification. Prepare the statutory package for the applicable jurisdiction and have the appropriately registered submitting person take the required step. Giving a client the calculations and drawings, making a submission and receiving statutory approval are different events. A technical agency's role, the project location and the appointed person determine which route applies. Record conditions that need to be reflected in the tender documents.
For example, a structural tender package for a ten-storey office should communicate the scope, relevant loading assumptions, foundation design and interfaces with the architectural and service drawings. Check that quantities and technical schedules align with the drawing issue. A contractor proposing a change to the foundation should be able to identify the baseline design and the assumptions affected.
Apply tender advice and acceptance authority
The basic Tender Stage lists in Part A 1(1)(c), 1(2)(c) and 1(3)(c) cover advice on suitability and relative merits and exclude the specified alternative tenders, prices and estimates. For a particular tender, establish the required qualifications and the comparison criteria. Compare submitted designs, interfaces and promised performance against the brief and set out any material qualifications. If the client wants engineering advice on an alternative that falls outside the basic list, record the extra scope and obtain the agreed instruction and remuneration before relying on the assessment.
Under BEM Form 1999 clause 5.7, the engineer may accept a tender only on the client's instructions in writing. Accept on the client's behalf and apply the tender's actual acceptance requirements. For example, a director's telephone message asking the engineer to award a warehouse package leaves the required authorisation missing. Identify the permitted signatory, get clear written authority and ensure the proposed notice matches the offer being accepted.
Keep the fee base and stage share separate
The 1998 schedule in Part B paragraph 3 apportions 20% to Design Stage II and 5% to Tender. After the first three stages in that schedule the cumulative proportion is 75%. After Tender it is 80%. These proportions apply to the relevant fee base under the stated arrangement. A new project requires the applicable version, contract and calculation.
Part B paragraph 1(1)(c) addresses bar bending schedules prepared and furnished by the consulting engineer. The additional fee is 0.75% of the cost of the reinforced concrete work covered by those schedules. The provision specifies what the relevant reinforced concrete work comprises. For example, where the covered work costs RM18 million, the stated calculation is RM18,000,000 × 0.0075 = RM135,000. Confirm the scope and the actual cost included in the base before using the rate. A construction package with both concrete and unrelated finishes needs a cost breakdown.
| Event under Part C | Applicable cost basis |
|---|---|
| Paragraph 6(3): tendering delayed or likely to be delayed more than nine months, or postponed at the client’s request | Estimate for the relevant works at completion of design. |
| Paragraph 6(4): work suspended or postponed after tender call | For the preliminary, design and tender fees, the lowest acceptable tender or, if there is none, the consultant’s estimate at the date of calling tenders. |
| Paragraph 6(4): suspended work resumes and tenders are recalled | Keep the early-stage fee basis above. Use the final contract sum at completion for the construction-stage fee. |
Record the dates and establish which event occurred before choosing a calculation. For example, suppose the client suspends a project after tender call, with no acceptable bids. Keep the consultant’s cost estimate dated to that call. A later estimate prepared after a redesign does not represent the date specified in paragraph 6(4)(a). If the project is re-tendered, retain that early-stage record and assess the separate construction-stage base against the final contract sum at completion.
A structural Consulting Engineer under BEM Form 1999 prepares all formal Design Stage II drawings for a RM40,000,000 commercial complex and is additionally instructed by the Client to prepare and furnish complete Bar Bending Schedules (BBS) for the reinforced concrete structure, which accounts for RM12,000,000 of the contract sum. Under SOF 1998 Part B paragraph 1(1)(c), what additional fee applies for the Bar Bending Schedules?
No additional fee, because Bar Bending Schedules are included within Design Stage II Basic Services (20%)
0.75% of the RM40,000,000 total cost of the works (RM300,000)
5.00% of the RM12,000,000 reinforced concrete work cost (RM600,000)
0.75% of the RM12,000,000 cost of the reinforced concrete work (RM90,000)
Under Clause 5.7 of the BEM Model Form of Agreement 1999, the Consulting Engineer shall not accept any tender unless the Client gives instructions ____ to do so, and such acceptance is made on behalf of the Client.
Type your answer below
In this project the client chooses the following plan for a structural design and tender. Order the tasks from design preparation to acceptance.
Arrange the items in the correct order
Complete the agreed procurement package in time for the tender.
Accept the selected tender on the client’s behalf after receiving the written instruction required by Form 1999.
Advise the client on the suitability of firms to invite.
Prepare the required authority calculations and detailed drawings.
Compare the tenders received and advise on their relative merits within the agreed scope.