8.4 Arbitration, Mediation & Consultancy Agreement Terms
Key Takeaways
Arbitration rests on the parties’ agreement. For a stay, check the scope, validity and the applicant’s procedural steps under section 10.
Mediation helps the parties negotiate. Act 749 distinguishes the signed settlement from the process and protects communications subject to statutory exceptions.
BEM Form 1999 has different triggers for client-ordered pause, abandonment, engineer suspension and non-payment.
Check which agreement the parties signed. BEM Form 2009 is an appointment for an accredited checker and has separate terms.
Choose the dispute procedure
| Procedure | Basis and effect |
|---|---|
| Arbitration | A written arbitration agreement covers the matter. The tribunal issues an award binding under the Arbitration Act, subject to the applicable court powers. |
| Statutory construction adjudication | CIPAA applies to qualifying payment disputes. A decision binds on the terms in section 13 while ultimate entitlement can be resolved in the agreed or available forum. |
| Mediation or conciliation | The facilitator assists negotiation. A proposal becomes an agreement through the parties' own assent and the applicable settlement requirements. |
| Civil litigation | The court decides claims within its jurisdiction, subject to any applicable arbitration stay and the relevant procedural rules. |
Under the Arbitration Act 2005 (Act 646), section 9 requires an agreement in writing. The applicable definition can include recorded terms and accessible electronic communications. Check subject matter, applicable law and the seat. Section 9A, inserted by Act A1737, allows a choice of the law for the arbitration agreement. The default is the law of the seat, and a choice for the main contract alone is not an express choice for the arbitration agreement. Check the transitional provision for an agreement made before the amendment began.
Section 10 requires the court to stay proceeding on a matter subject to the agreement and refer the parties to arbitration on a timely application made before the applicant takes any other step in the proceeding, unless the agreement is null and void, inoperative or incapable of performance. Section 18 allows the tribunal to rule on its jurisdiction and treats the clause as independent of the main contract. Section 41A governs disclosure, subject to party agreement and statutory exceptions. The award is final and binding under section 36, subject to statutory remedies including section 37 setting aside. Under amended section 38(1), recognition of the award as binding and enforcement by written application to the High Court serve distinct purposes. Check section 39, which governs refusal of recognition or enforcement.
The Mediation Act 2012 (Act 749) provides for a voluntary process within its scope. Sections 13–14 provide for a written settlement signed by the parties, authenticated by the mediator, and binding on the parties. If court proceedings already exist, a settlement may be recorded as a consent judgment subject to the applicable procedure. Sections 15–16 protect mediation communications, with different exceptions for confidentiality and privilege. Section 2 excludes specified proceedings, including mediation conducted by the court after a civil action has been filed. In an engineering dispute a conciliator may suggest settlement terms as part of helping the parties reach agreement.
Apply the BEM appointment the parties adopted
BEM publishes Form 1999 for a client's consulting engineer engagement and Form 2009 for a client's accredited checker engagement. Check which form and amendments apply. The following rules are from the unamended Form 1999 Conditions of Engagement.
| Situation | Form 1999 route |
|---|---|
| Client postpones the works | Clause 2.3 provides for written termination or a written requirement to suspend services in lieu. If the client does not require resumed services on the postponed work within 12 months of the suspension requirement, clause 2.4 treats the work as abandoned and the agreement terminates. |
| Engineer responds to breach or impediment | Clause 2.5 permits termination on at least 60 days' written notice for the client’s failure to comply with an obligation, disregard of professional advice, or circumstances outside the engineer’s control that delay services more than 12 months, prevent them or unreasonably impede them. The alternative is immediate suspension for 60 days, promptly informing the client in writing with reasons, followed by resumption or written termination if a reason remains. |
| Impossibility outside the engineer's control | Clause 2.9 requires prompt written notice. Written client confirmation or no response within 30 days results in the relief from liability specified in the clause. |
| Unpaid sums or a disputed item | Clause 11.6 provides 42 days from submission of accounts for sums due. Overdue sums then bear interest accruing daily at two percentage points per annum above the current prime rate. If delay continues for a further three months, the clause provides written termination in lieu of imposing that interest. Clause 11.7 protects payment of the remainder and the part the client agrees to pay. |
| Close-out | Apply clause 2.6 where triggered and preserve accrued rights under clause 2.8. Under clause 2.7, the ordinary end is the certificate authorising final payment, defined by release of retention at the end of the defects or maintenance period. |
| Dispute under clause 4.1 | Give written notice and seek agreement on the arbitrator. The form names the IEM President as the appointing authority if agreement fails within two months from notice. Its reference to the 1952 Act extends to statutory modification or re-enactment. The clause addresses continued work after consultation and payment of amounts outside the dispute. |
If a Shah Alam client directs a suspension and makes no request to resume postponed work for 14 months, document the direction and elapsed time under clauses 2.3–2.4. Identify accrued fees and the close-out steps. For outstanding accounts, analyse clause 11.6's alternatives and clause 11.7's undisputed balance. Clause 11.8 addresses service tax as prescribed by law. Review the chosen dispute procedure and any CIPAA eligibility separately.
BEM Form 1999 · BEM Form 2009 · Arbitration Act · Federal Court on section 10 · Act A1737 · Mediation Act text
Under the unamended BEM Form 1999, a client requires in writing that the engineer suspend services on postponed work. The client makes no request to resume them for 14 months. What follows under clauses 2.3–2.4?
The postponed work is treated as abandoned and the agreement terminates.
The consultancy agreement becomes void ab initio and all previously paid fees must be refunded to the Client
The Engineer must wait a full 24 months before any abandonment entitlement or close-out fee arises
The Engineer's accrued fee claims are extinguished under Clause 2.8 unless arbitration is filed within 14 days
Which THREE statements accurately describe payment and termination rules under the BEM Model Form of Memorandum of Agreement (1999 Edition)? (Select three)
Select all that apply
Under clause 11.6 sums due are payable within 42 days from submission of accounts. Unpaid sums then bear the specified daily accrual at an annual rate two percentage points above the current prime rate.
Under Clause 11.7, if a Client disputes a single line item on a fee invoice, the Client may lawfully withhold 100% of the entire invoice until arbitration concludes
For a qualifying client failure, clause 2.5 permits at least 60 days’ written notice of termination or an alternative immediate 60-day suspension with written notification of reasons as soon as practicable.
If delay continues for a further three months after the clause 11.6 payment period, the clause provides for written termination in lieu of imposing the stated interest.
Under Clause 2.7, the consultancy agreement automatically ends immediately upon issuance of the Tender Award Letter
A 2026 Malaysian works contract contains an operative written arbitration agreement covering a wrongful termination claim. The claimant sues in the High Court. The respondent applies to stay before taking any other step. What must the court do under section 10?
Strike out the arbitration clause because High Court jurisdiction always overrides private contracts
Refuse the stay unless the Contractor first completes CIPAA 2012 adjudication
Order both parties to sign a fresh Mediation Act 2012 Settlement Agreement before proceeding
Grant a mandatory stay of the court proceedings under Section 10 and refer the parties to arbitration