1.2 Open-Book Mastery & Paper 2 Essay Technique
Key Takeaways
The 2026 applicant booklet allows an average of 2 minutes 37.5 seconds per objective question and 40 writing minutes per essay. Use the separate 15 minutes to read the essay paper.
Practise locating a rule by issue, instrument and section. Check the instructions for your sitting before bringing any materials or making notes during reading time.
Act 138 gives 21 days from notification for specified professional appeals. The 2026 booklet gives two weeks from receipt of results for a written PCE appeal through MyBEM.
An issue, rule, application and conclusion structure gives each essay a place to connect the facts to the next professional step.
Trace a change of consultant through the appointment terms, Regulation 31 and any authority procedure. For unpaid consultancy accounts, read clauses 2.5 and 11.6 of the BEM model form separately.
1.2 Open-Book Mastery & Paper 2 Essay Technique
Time budgets for both papers
BEM describes Part A as an open-book examination. Check your sitting instructions for the materials you may bring, what you may mark, and how you may use the reading period. Practise with your indexed references beforehand so you can find an applicable provision under exam time limits.
Consider the exact clock constraints:
- Paper 1 (Objective): 40 questions in 105 minutes equals 2.625 minutes per question. Four minutes on one item uses an extra 1 minute 22.5 seconds compared with an even allocation. Flag it for a second pass when your remaining time permits.
- Paper 2 (Essay): 15 minutes reading time followed by 120 minutes for 3 essays equals 40 minutes per essay. Budget time to state the rule, connect it to the stated facts and identify an action the named project participant can take.
Tip
Practise a two-pass lookup. Recall the main duty first, then check the source for a condition that could change the answer, such as when a notice period starts or which party must give it.
How to Tab and Index Primary Malaysian Instruments
Organise your reference set into three colour-coded binders (or tabbed volumes) and place a one-page Master Section Index at the front of each volume to reduce lookup time during timed practice.
| Volume / Tab Colour | Primary Instrument | High-Yield Provisions to Tab |
|---|---|---|
| Blue: Governance & Ethics | Registration of Engineers Act 1967 [Act 138] (REA 1967, Revised 2015) | s.4(1)(ed)(ii) & (f); s.7, s.7A, s.7B (ECP); s.10(2) vs. s.10D; s.15 (Discipline); s.19 & s.22 (21-day Appeal Board) |
| Blue: Governance & Ethics | Registration of Engineers Regulations 1990 (RER 1990, with 2021 & 2025 Amendments) | Part IV Code of Conduct; Reg 31 (substituted by 2025 Amendment, effective 5 Nov 2025, on supplanting/takeover); Reg 34A (2021 Amendment); updated 2025 fee/reinstatement schedules |
| Blue: Governance & Ethics | BEM Circular No. 001 (Code of Conduct of Registered Persons) | Issued under s.4(1)(f) REA 1967; public safety primacy, personal performance, conflict of interest, endorsement rules |
| Amber: Building, Safety & Environment | Street, Drainage and Building Act 1974 [Act 133] (SDBA 1974) & Uniform Building By-Laws 1984 (UBBL 1984) | s.70 & s.70A (plans, earthworks, CCC); Submitting Person duties; UBBL G-Forms (G1–G21) |
| Amber: Building, Safety & Environment | Occupational Safety and Health Act 1994 [Act 514] (OSHA 1994, 2022 Amendment effective 1 June 2024) & CDM Regulations 2024 | Repeal of FMA 1967 [Act 139]; expanded workplace scope; Occupational Safety and Health (Construction Work) (Design and Management) Regulations 2024 (CDM 2024) duties of Client, Principal Construction Work Designer, Construction Work Designer, Contractor, pre-construction information, construction phase plan, safety and health file |
| Amber: Building, Safety & Environment | Environmental Quality Act 1974 [Act 127] (EQA 1974, 2024 Amendment) | Section 34A and the prescribed activities order for Environmental Impact Assessment (EIA) |
| Green: Contracts & Consultancy | Contracts Act 1950 [Act 136] | Offer/acceptance, consideration, s.10–s.24 (void/voidable), s.74 (damages), s.75 (liquidated damages / reasonable compensation) |
| Green: Contracts & Consultancy | Construction Industry Payment and Adjudication Act 2012 [Act 746] (CIPAA 2012) | Payment claim (s.5), payment response (s.6), 10-working-day response window, adjudication notice, s.29 suspension right, s.30 direct payment |
| Green: Contracts & Consultancy | BEM Model Form of Memorandum of Agreement (1999 Edition) (BEM Form 1999) & Notification of Scale of Fees 1998 (SOF 1998) | Clause 2.5 (60-day written notice or 60-day suspension for client breach), Clause 2.6 (orderly conclusion), Clause 2.8 (accrued rights), Clause 11.6 (42-day payment, 2% above prime interest, termination after further 3 months); SOF 1998 stage fee percentages & reimbursables |
Rules to distinguish in Paper 1
Practise distinguishing rules that use similar labels or deadlines.
- PE vs. PEPC Authority Trap: For a question on submitting structural or building-services plans, identify the engineer’s registration and the particular work. Start with the ordinary route through a PEPC or ECP under section 8. Check branch, purpose and authority requirements, and distinguish the narrow equipment, plant and specialised-product exception in section 8A.
- 21-Day Statutory Appeal vs. 2-Week Exam Appeal Trap: Under Section 19 of REA 1967, a person aggrieved by BEM's refusal of registration, imposed conditions, removal from the Register, or a Disciplinary Committee order has 21 days to file a written Notice of Appeal to the Appeal Board (under Section 20/22). By contrast, appealing a PCE examination result via MyBEM (with the RM400 fee) has a 2-week deadline from receipt of results.
- Repealed FMA 1967 vs. Current OSHA 1994 (2024) & CDM 2024 Trap: The Factories and Machinery (Repeal) Act 2022 [Act 835] repealed the FMA from 1 June 2024. Use the amended OSHA and applicable subsidiary rules for current duties. For older notices, applications or proceedings, check the savings provisions in sections 4–6 of Act 835.
- Pre-2025 Regulation 31 Wording Trap: Always rely on the substituted Regulation 31 introduced by the Registration of Engineers (Amendment) Regulations 2025 (effective 5 November 2025) alongside BEM's stakeholder/takeover procedures, rather than outdated notes.
Paper 2 Structured Essay Technique: The IRAC Method
Use the 15-minute reading time to read all five Paper 2 questions, select the three questions where you can cite exact statutes or contract clauses with confidence, and sketch brief IRAC bullet outlines on the question paper (if permitted by room rules) before the 120-minute writing period starts. Use Issue, Rule, Application and Conclusion (IRAC) to organise the answer.
- I — Issue: Frame the precise legal, contractual, and ethical questions raised (usually 2–4 sub-issues per scenario).
- R — Statutory / Contractual Rule: Cite the exact Act, Section, Regulation, BEM Circular, or Contract Clause, plus the governing legal doctrine. Keep rule statements crisp—never transcribe entire statutory pages.
- A — Fact Application: Apply every condition and timeline of the rule directly to the facts in the prompt. Address both parties' positions, conditions precedent, and notice defects.
- C — Conclusion and professional action. State the exact, practical steps the PEPC, Submitting Engineer, or Contract Administrator (CA) must take next (written notices, determinations, authority notifications, stakeholder deposits, and documentation).
Worked scenario 1 — A late instruction while an extension claim is open
Facts. An employer delivers access to a drainage workfront late. The signed contract in this example allows a time extension for late access and instructed variations. It requires the contract administrator to evaluate the causal effect on completion before certifying delay damages. The contractor serves notice and submits a programme update showing which activity lost access. The original date passes with the request undecided. The administrator then instructs an additional drainage connection.
- Issue. Which delays affect completion, and which steps must precede certification?
- Rule. Use the signed contract’s extension and certification provisions. Check whether they permit a decision after the original date and which notices each event requires.
- Application. The outstanding access request and the new instruction are separate events. Compare the programme immediately before each event against the update and look for overlap. A delayed activity can have float, the time it can slip before affecting completion. The record needs to show how much of either event actually shifts the contractual completion date.
- Conclusion. Record the instruction and the time implications separately. Assess each extension within the authority conferred by the contract and defer the damages decision until its stated prerequisites are met. If the form leaves a gap, identify the clause or legal issue requiring resolution before giving a definite answer about the employer’s entitlement.
Worked scenario 2 — A client moves a design assignment in-house
Facts. The external consultant has completed the initial design and filed selected plans. The client informs its newly hired Professional Engineer with Practising Certificate (PEPC) that it intends to transfer detailing and statutory follow-up to the in-house team. The external firm disputes its final invoice and the client has yet to establish who may reuse the design files.
- Issue. Can the incoming engineer take over and use the drawings now?
- Rule. The consultancy agreement governs termination and the permission to use project material. From 5 November 2025, Regulation 31(c) permits takeover for the same client with the outgoing engineer’s consent, with the client’s formal notice of termination and the outgoing engineer’s confirmation of fee payment, or with the Board’s approval. The client can ask BEM to act as stakeholder when fees are disputed. Check both the applicable regulation and the local authority’s substitution process.
- Application. The client’s informal direction does not establish consent, confirmed fee payment or Board approval. A proposed transfer also leaves unresolved which designs are current, who holds the rights to use them, and what the incoming engineer can substantiate through review.
- Conclusion. Establish the outgoing scope and current filing status. Check the contract and document permissions, follow an available takeover route, and record the outstanding safety, design and authority issues for the handover.
Worked scenario 3 — An unpaid consulting account
Facts. The parties adopted unamended BEM Model Form 1999 payment terms. The consultant submitted an account for sums due on 1 February in a non-leap year, and payment is still outstanding on 1 June. For this exercise the parties count 2 February as day one and calendar months from the end of the 42-day period.
- Issue. Has the specific termination option in clause 11.6 arisen?
- Rule. Clause 11.6 gives 42 days to pay from submission of the account. Interest then accrues daily at an annual rate two percentage points above the current prime rate. After three additional months of delay the consultant may give written termination notice in lieu of the interest specified by the clause. Clause 2.5 separately addresses a general client breach and other specified circumstances, with its own notice and suspension provisions.
- Application. There are 27 days from 2 to 28 February and 15 more through 15 March. The 42-day payment window ends 15 March and the further three calendar months run to 15 June under the stated convention. As of 1 June the specific clause 11.6 termination option is premature. Check clause 11.7 if just part of an account is disputed.
- Conclusion. Keep proof of submission, separate disputed and undisputed sums, maintain the service and notice record, and check the actual agreed dates and notice terms before choosing a remedy. Clause 2.6 expressly deals with close-out under clauses 2.3 and 2.5. For a separate clause 11.6 termination, plan an orderly handover and identify any applicable legal and authority duties.
Official references
- 2026 BEM applicant booklet, sections 10 and 15, and Act 138, sections 8, 8A, 19 and 22.
- Regulation 31 replacement, P.U. (A) 403/2025 and BEM Model Form 1999, clauses 2.3–2.8 and 11.6–11.7.
- Factories and Machinery (Repeal) Act 2022 and commencement notification.
A registered PE receives a Disciplinary Committee suspension order from BEM and also fails a PCE sitting in the same year. Which option states the correct appeal deadlines for each matter?
Both appeals must be filed within 14 days via the MyBEM portal with a RM400 fee
The Section 19 disciplinary appeal has a 2-week deadline, while the PCE exam appeal has a 21-day deadline
Both appeals have a 3-month deadline matching the PCE results release window
The Section 19 disciplinary appeal to the Appeal Board must be filed in writing within 21 days of notification, whereas the PCE exam appeal via MyBEM must be lodged within 2 weeks of receiving results
An undisputed account under unamended BEM Model Form 1999 remains unpaid after the 42-day payment period and a further three months. Which option is available under clause 11.6?
Suspend services automatically without contacting the client
Give the client written notice of termination in lieu of imposing the interest specified by clause 11.6
Revoke the client’s development approval under section 10D of Act 138
Transfer the appointment to a different consultancy without the client’s consent
Which of the following practices reflect sound open-book and Paper 2 IRAC examination technique for PCE Part A? (Select all that apply)
Select all that apply
Use the 15-minute reading period to select the three strongest essay questions and outline answers if the sitting instructions permit notes
Citing the Factories and Machinery Act 1967 (FMA 1967) as the active Malaysian statute governing construction site safety and designer duties
Index the instruments so you can locate an applicable provision quickly during timed practice
Give a conclusion that identifies the available professional action for the facts
Copying entire statutory sections verbatim into Paper 2 essays to maximise page count