5.2 Coordinating Planning, Technical Plans and Construction Through OSC

Key Takeaways

  • The OSC 3.0 Plus manual distinguishes optional technical information gathering in Process 1 from development-plan consideration in Process 2.

  • Group filings according to the authorised local route. Track separate decisions for planning permission, technical plans, start notices and completion.

  • In the Selangor example, Act 133 sections 70 and 70A supply the separate building and earthworks controls. Form B is the commencement or resumption notice in the applicable by-laws.

Last updated: November 2026

Use the portal to coordinate separate decisions

The local authority's One Stop Centre (OSC) routes development files for internal and external technical review. Identify the participating local authority, the application category and the documents it needs. The OSC 3.0 Plus manual, section 5.1, identifies six main processes. In this framework a single channel for applications can carry several legal decisions. For each package record who has to issue the approval, which drawing version it covers and which conditions still control work.

Process in the KPKT manualWhat the engineer checks
1. Collection of technical information, optionalDecide whether early technical information would help. Seek relevant input about road access, drainage outlets, utility reserves or affected land before fixing the layout.
2. Consideration of development plansUse the appropriate local route and category for the planning and technical submissions. The manual supports different routes and combinations. Identify the approval and conditions for each package even when files are reviewed in parallel.
3. Notification of start of constructionConfirm the approvals and any outstanding conditions that bear on commencement. In the Selangor building example, use Form B for the applicable notice and satisfy the timing under Act 133 and the Selangor by-laws.
4. Site monitoring and interim inspection notificationsMatch required inspections to programme milestones. Collect the records that the signatories will need before concealed work is covered.
5. Final inspection notifications, Stages I and IICheck the authorities' applicable final inspection and supporting documentation requirements before the relevant completion certification.
6. Deposit of CCC/CFOFollow the current approval regime. For the Selangor CCC example, the PSP issues Form F only after the relevant conditions are met, then deposits the prescribed packet.

Worked example: access and drainage at an industrial development

A Selangor council is handling a light-industrial development. The project team's proposed access crosses a route with drainage constraints. The team obtains technical information from the road and drainage authorities to decide what access corridor and runoff controls to show in the layout. That consultation belongs to Process 1 where the team uses it. The eventual development proposal and plans belong to Process 2. When the council states that the planning and technical plans can be lodged together for that application category, the team can use the concurrent route. Keep a separate row for each decision and its status.

Record for this projectRelease decision
Act 172 planning permission and access conditionCheck that the proposed industrial use is approved and the technical designs reflect the stipulated access position.
Act 133 section 70A earthworks approvalCompare its scope, slope and drainage drawings and required controls to the actual package before the contractor starts the earthworks. Section 70A(2) calls for the related plans required under the Act or its by-laws to be submitted at the same time as the earthworks plans when the earthworks serve that construction or work.
Act 133 section 70 building approval and structural packageThe building cannot be erected without prior written permission. Verify the detailed structural plans and calculations before erection under subsection (9A).
Selangor Form B and commencement datesAct 133 section 70(9) requires four days' written notice. Selangor by-law 22 uses Form B for building operations and requires a further notice if work does not start or resume on the given date. Record the authority's receipt as well as the intended start.

Suppose the team has planning permission and approved building plans, but the earthworks revision is awaiting approval. Keep that earthworks package off the site release programme. Check the drawings against the permission before the revised earthworks are issued for use. At completion, reconcile inspection records and any updated approvals against the built work before the PSP considers Form F.

For an essay, set out the open decision and the work it controls. Then give the next action and who records it. This avoids treating a technical comment, an OSC receipt and a legal approval as interchangeable.

KPKT OSC 3.0 Plus manual, sections 5–6 · Act 133, sections 70 and 70A · Selangor Uniform Building By-Laws, by-laws 22 and 25

Loading diagram...
Selangor example using the six OSC processes
Test Your Knowledge

A Selangor consultant has an optional early drainage discussion and later files planning and technical drawings in the category accepted by the council. Which OSC 3.0 Plus mapping fits?

A

Early technical information in Process 1 and development-plan consideration in Process 2

B

Both are approval decisions in Process 1

C

Early information is Process 3 and plan submission is Process 4

D

Both milestones occur when the CCC is deposited in Process 6

Test Your Knowledge
Ordering

For the approved Selangor building scope with no exceptional procedure, order these milestones from plan review through occupation certification.

Arrange the items in the correct order

1

Obtain the applicable planning and technical decisions and check pre-start conditions

2

Complete notified interim and final inspections with the stage records

3

PSP issues Form F after verification and deposits the prescribed packet

4

Give the required building commencement notice before commencing