10.3 BEM Scale of Fees and Reimbursables

Key Takeaways

  • Use the amended general or housing notification according to the defined development, the buildings’ storeys and the location.

  • Start with the applicable cost of works and interpolate between adjacent rates on the same fee boundary. The selected percentage is agreed within the resulting range.

  • Multiply salary cost by the agreed multiplier for time-basis work. Calculate separate additional services, reimbursables and supervision as applicable.

  • For a qualifying client suspension or termination beyond preliminary services, calculate one sixth of the difference under Part C and deduct amounts already paid from what remains due.

Last updated: November 2026

Choose the applicable notification

BEM sets scales with ministerial approval under section 4(1)(d) of the Registration of Engineers Act. The current texts to read together are the general P.U. (B) 548/1998 as amended by P.U. (B) 343/2003, and the housing P.U. (B) 288/1997 as amended by P.U. (B) 344/2003. Under the 2003 amendment, housing development buildings up to and including four storeys use the housing notification. Housing development buildings above four storeys and other buildings use the general notification. The definition includes houses, shop houses, flats, condominiums and apartments in a single location, meaning the same housing development area developed or to be developed by the same developer. A three-storey standalone office outside the housing definition therefore uses the general notification.

Establish the cost of works and fee rate

Under paragraph 3 of the general notification, start with the cost to the client. Before deducting contractor liquidated damages or penalties, include covered payments including claim settlements, bonuses and incentives. Consider the fair value of client-provided inputs, the new market value of incorporated second-hand items, geotechnical investigations and the prescribed fair share of eligible utility provision or diversion. Exclude client administration, cost under the consultant’s professional services appointment, financing costs, land and wayleaves, and contract price variation arising from escalation.

Under Part B paragraph 1(1), apply the fee to the cost of the components in the respective type. Interpolate each relevant rate boundary using its own adjacent percentages. Agree the actual percentage between the two interpolated values before engagement, considering complexity. This extract shows the adjacent bands used below.

CostMinimumMaximum
RM5 million5.20%5.50%
RM10 million4.75%5.00%

Under paragraph 1(1)(c), add 0.75% of the relevant reinforced concrete cost when bar bending schedules are prepared and furnished. For repeat work under paragraphs 1(1)(e) and (f), check that the same client reuses the documents under the same consultancy agreement and apply the schedule’s unit and adjustment rules. For the second Type A unit Table A distinguishes design copyright only (30%), up to tender (35%) and up to construction (65%), each as a percentage of the full first-unit fee. Table B uses 75% of the first-unit fee for each second through fifth Type B or C unit under its respective headings.

Distinguish salary cost, supervision and reimbursables

Salary cost is annual salary divided by 1,800 and multiplied by the eligible working hours spent. Multiply that result by the applicable multiplier for time-basis services under Part B paragraph 1(2). Do not bill routine secretarial, accounting or general office administration time under this provision. Under paragraph 2, additional services can use agreed hourly rates for partners and consultants or salary cost times the multiplier. The 5% coordination fee applies to specialist advice obtained under the specified Part A provisions, based on the specialist fee the client pays, and is excluded where the parties agree on the paragraph 1(2) method for the professional services.

Part C paragraph 2 reimburses listed disbursements actually incurred, such as printing, courier charges, travel and statutory approval charges paid by the engineer. It includes service tax on the professional fee as required by law. Paragraph 4 separately addresses salary cost times a multiplier for seconded site staff, actual salary or wages times a multiplier for specially recruited staff plus their actual employment-related costs, and eligible office and running costs unless the client provides them.

Calculate a client termination after Design II

Assume a Type A appointment on the minimum percentage under the general notification, an accepted RM6 million cost basis, completion through Design II, no previous fee payments and a qualifying client termination unrelated to engineer default or negligence. The RM6 million falls one fifth of the way from RM5 million to RM10 million.

Pmin⁡=5.20%−6−510−5(5.20%−4.75%)=5.11%P_{\min}=5.20\%-\frac{6-5}{10-5}\left(5.20\%-4.75\%\right)=5.11\%

The full fee is RM6,000,000 × 5.11% = RM306,600. Preliminary, Design I and Design II account for 20% + 35% + 20% = 75% under Part B paragraph 3, so RM229,950 is earned and RM76,650 is unearned. Part C paragraph 6(1)(b) gives one sixth of the difference when services advanced beyond preliminary, or RM12,775. The resulting fee and disruption charge total RM242,725 before other amounts and applicable tax. Credit prior payments when determining the balance. If suspended work restarts, paragraph 6(2) treats the relevant earlier payments as payments on account and allows the engineer to retain the disruption charge.

BEM general and housing notifications and 2003 amendments · General notification · Works Ministry register

Test Your Knowledge

A Client engages an ECP at P(min) for a Type A infrastructure project with a contractor final account of RM10,000,000 (after deducting RM300,000 in LAD, meaning pre-LAD contractor payments were RM10,300,000), excluding RM1,500,000 in land acquisition costs. What is the correct Cost of Works under SOF 1998 para.3, and which rule governs disbursements under Part C para.2?

A

RM11,800,000 including land acquisition; disbursements charged at a mandatory 5% fixed surcharge on the Basic Fee

B

RM10,000,000 net after LAD deduction; disbursements absorbed inside the Basic Fee percentage

C

RM10,300,000 before LAD and excluding land. Reimburse the listed disbursements actually incurred.

D

RM8,800,000; disbursements billed using the 1,800-hour Salary Cost formula

Test Your Knowledge
Ordering

Arrange the five fee-bearing consultancy project stages under BEM Scale of Fees (Revised 1998) [P.U.(B) 548] Part B para.3 in correct chronological order from first to last.

Arrange the items in the correct order

1

Tender Stage (5%)

2

Preliminary Stage (20%)

3

Construction Stage (20%)

4

Design Stage (ii) (20%)

5

Design Stage (i) (35%)