9.1 Feasibility/Preliminary Stage & Design Stage I
Key Takeaways
Use the services incorporated into the adopted BEM appointment. Part A describes the services and Part B paragraph 3 apportions the fee.
In both the Type A and Type B preliminary service lists, where necessary, the engineer advises on geotechnical investigation, arranges it, certifies the amount due for directed investigation and advises on the results.
Move from identifying principal site and authority constraints to developing a coordinated engineering scheme. The published stage shares are 20% for Preliminary and 35% for Design Stage I.
Start with the appointment and discipline
The BEM Form 1999 is a model agreement between a client and a consulting engineer. The adopted memorandum identifies services by reference to Part A of the Notification of Scale of Fees 1998, P.U. (B) 548/1998. Read the appointment, service category and supplements first. Part A describes basic and additional services. Part B paragraph 3 provides the stage apportionment. For an exercise using the original stage schedule, Preliminary is 20% and Design Stage I is 35% of the apportioned fee. The separate housing notification and any applicable revision or agreed adjustment need their own check.
| Works as defined in the 1998 general notification | Example |
|---|---|
| Type A, civil and structural engineering other than building structures, and mechanical or electrical engineering other than building engineering systems | Bridge or a standalone pumping installation |
| Type B, structural works in a building of more than four storeys | Foundations and structure of a ten-storey office |
| Type C, engineering systems in a building of more than four storeys | Electrical distribution, ventilation or building services in that office |
The same tower can have a Type B structural appointment and a Type C services appointment. Assess the particular work and engagement. A separate access road or external drainage package may raise different scope questions.
Feasibility and preliminary work
For Type A or Type B under Part A 1(1)(a) and 1(2)(a), review the available reports and data and advise on additional topographic survey where necessary. Where geotechnical information needs supplementation, advise the client, arrange the investigation, certify the amount of payments to the people or firms carrying out the work under the engineer's direction and advise on the results. Certification addresses amounts payable by the client. Where special investigations, surveys or model tests are needed, check the provisions on arrangements and additional services. Consultation on matters of principle and preliminary reports help the client assess options and seek approval in principle.
For Type B, share enough structural information for the architect's sketch plans. For Type C, Part A 1(3)(a) identifies consultation on principle, review of data and reports, coordination with the architect and others, preliminary information and approximate estimates to support sketch plans and budgets, and proposals or alternatives. An adequate information basis remains important for both appointments.
Suppose a building is proposed on reclaimed land. The structural engineer compares available fill and groundwater records with the load assumptions and arranges supplementary investigation where needed. The client can use the report to choose between feasible foundation concepts. The building services engineer checks service entry, plant space and the likely cost of competing systems. Keep an assumptions register, identify who is obtaining each item of information, and record which choices depend on an authority response. An approval in principle is a different milestone from approval of a design or a statutory submission.
Design Stage I develops the scheme
For Type B, Part A 1(2)(b)(i) identifies collaborating with the architect and others, preparing calculations, drawings and specifications so others can prepare a bill of quantities, consulting approving authorities in connection with the design, and preparing typical details and calculations. For a Type A appointment, the single Design Stage list in 1(1)(b) covers design, tender drawings and the documents needed to price the work. Coordinate the timing of those deliverables with the client's design sign-off.
For Type C, Part A 1(3)(b) lists plant-room and main-duct information and approximate weights of heavy plant, along with design and tender drawings. The building team can use that information early to coordinate loading, access, openings and clearances. For example, record the approximate operating load and service clearance for a pump set before the structural team fixes the slab and plinth. The notification groups those Type C deliverables under Design Stage. Check the adopted appointment for the milestones that assign them to Design I or Design II. A sketch of an agreed plant zone still needs coordination against the detailed scheme.
Under the stated apportionment, an assumed total basic fee of RM200,000 yields RM40,000 for Preliminary and RM70,000 for Design I. That is RM110,000 across those stages before a separate adjustment. It is a fee allocation example rather than a calculation of an applicable project fee rate.
BEM Form 1999 · General fee notification, Part A and Part B paragraph 3
Which preliminary service lists expressly include, where necessary, arranging the geotechnical investigation and certifying the amount of payments for investigation carried out under the engineer’s direction?
Type A only
Type C only
Both Type A and Type B
Type B and Type C
For Type B structural works under the 1998 notification, which three tasks are in the Preliminary Stage list?
Select all that apply
Consulting local and approving authorities on matters of principle
Preparing formal authority-submission calculations for SDBA/UBBL building plan approval
Consulting the Architect on architectural treatment and supplying structural/services space information for sketch plans
Issuing the Letter of Acceptance to the successful contractor on behalf of the Client
Advising the Client on special surveys and model tests where required and preparing preliminary proposals/alternatives
A ten-storey building has a Type B structural appointment using the 1998 schedule. Which Design Stage I share and activity are supported by Part B paragraph 3 and Part A 1(2)(b)(i)?
35% and preparing typical structural details and calculations with the coordinated scheme.
20% and checking the contractor’s shop details.
35% and issuing the certificate releasing final retention.
25% and advising on competing tenderers.