9.3 Construction Stage & Post-Construction Stage

Key Takeaways

  • Apply the construction service list for the actual discipline. Check contractual authority before issuing instructions or certificates.

  • Under BEM Form 1999, periodic engineer visits and resident supervision have separate scope and staffing rules.

  • Clause 5.10 requires immediate reporting. Following the client’s written direction, proceed within 14 days to cause remedial works to be carried out.

  • Distinguish the contractual handover, statutory occupation procedure and ordinary end of the consulting appointment.

Last updated: November 2026

Administer the construction appointment

Part A of the 1998 general fee notification gives construction-stage basic service lists for each type of work. Review the appointment and actual works contract before giving instructions. Type A includes preparing formal contract documents, including the letter of acceptance, and issuing certificates required under the contract. Form 1999 clause 5.7 governs authority to accept the tender. Type B includes advising on contract documents and payment certificates and checking shop details for general dimensions and adequacy of members and connections. Type C includes providing information for installation drawings, checking shop and installation details, commissioning procedures, performance tests and payment or final-account advice as applicable. Do not infer a power to certify from a duty to advise.

Record the applicable inspection and test procedures and the evidence to be reviewed. A contractor's equipment test can support acceptance under the works contract. Check separately whether the statutory process requires a different qualified person, certificate or authority response. Preserve the approved drawing revision, outstanding defects and any technical reservations.

Manage site staff and decisions under Form 1999

Clauses 5.8 and 8.7 distinguish the engineer's site visits under the notification from continuous or detailed supervision by site staff. Under clauses 8.1–8.4 the engineer considers the need for site staff, the client cannot unreasonably object to their appointment, and direct employment by the client requires agreement and the engineer's selection or approval. Where the client employs them, the appointment must require instructions to come from the engineer. Clause 8.5 excludes client-employed supervision staff where the client wholly or partly owns the contractor, or a partner or director of the client has a direct or indirect financial interest in the contractor. Check clause 8.8 and the works contract before issuing instructions. For cost-increasing instructions, apply the separate clause 5.9 test of whether prior approval is practicable in the circumstances, and inform the client as soon as possible when the exception applies.

Under clause 5.10(a), report the failure, accident or event immediately to the client. Unless directed otherwise, investigate and submit the report and remedial proposal. Under clause 5.10(b), wait for written client direction before causing remedial works to be carried out. Once directed, proceed within 14 days from the direction to cause the work to be carried out. That clock concerns taking action, including arranging the work, rather than promising completion within two weeks. Give the required assistance to a separate client investigation under clause 5.10(c). Under clause 5.10(d) the services are additional and payable if the event was not due to the engineer's negligence. The contractual direction rule does not discharge statutory safety or reporting duties.

Prepare handover and close-out

The syllabus identifies a post-construction stage. The 1998 notification places various handover tasks in its construction-stage service lists and gives Construction the final 20% share in Part B paragraph 3. It supplies no sixth percentage row. At completion, confirm the appropriate structural or services records, instructions, manuals and where applicable the test documents and spare items. Identify the deliverables and authorisation needed for the particular discipline. Under an applicable CCC regime, the responsible professionals complete or endorse the stage documentation as required and the principal submitting person issues the applicable completion form. The building-control decision should be recorded separately from a contractual certificate of practical completion.

Track the defects and any contractual inspections, verification and certificates for the end of the defects or maintenance period. Under unamended Form 1999 clause 2.7 the ordinary end of the appointment is the certificate authorising final payment, defined as the certificate to release retention at completion of that period. Check the adopted terms and retain a separate record of accrued claims and final-account advice.

Additional professional services in Part A paragraph 2 may include services required by legal changes after engagement, some alternative work, and work arising from a contractor’s abandonment or failure to perform the contract properly. Check the specific type and trigger. Basic determination of a referred employer-contractor dispute does not extend to the later advice specified in the exclusions after steps toward arbitration or litigation have begun. Obtain prior client agreement to arrangements as required under Form 1999 clause 7.1. For qualifying specialist advice, Part B paragraph 2(e) specifies a coordinating fee of 5% of the specialist fee paid by the client, subject to the stated exception for the time-based method.

BEM Form 1999 · General fee notification · BEM CCC practice documents

Loading diagram...
Six project stages and the consulting appointment
Test Your Knowledge

A property developer owns a 60% controlling equity stake in the Main Contractor awarded a 20-storey residential project. The developer insists on directly employing the Resident Engineer and Clerk of Works on its own payroll to reduce consultancy costs. Under BEM Form 1999 Clauses 8.1-8.5, what is the legal position?

A

Permitted, provided the Consulting Engineer retains the right to sign the Interim Payment Certificates

B

Clause 8.5 excludes client-employed supervision staff because the client partly owns the contractor.

C

Permitted, provided the Resident Engineer signs a non-disclosure agreement with the Architect

D

Prohibited only during the Defects Liability Period, but permitted during active superstructure construction

Test Your Knowledge
Matching

Match each BEM Form 1999 clause to its governing contractual rule during the Construction and Post-Construction Stages.

Match each item on the left with the correct item on the right

1

Clause 8.7

2

Clause 5.9 with memorandum clause 7

3

Clause 5.10(b)

4

Clause 5.10(d)

5

Clause 2.7

Test Your Knowledge
Multi-Select

Which three services may be additional under the applicable Type A, Type B or Type C provisions of the 1998 general notification?

Select all that apply

Redesign caused by statutory or regulatory code changes enacted after the Consulting Engineer's engagement

Checking Contractor shop details for general dimensions and adequacy of members and connections

Advising and acting for the Client in arbitration or litigation proceedings arising from contractor disputes

Reviewing and delivering Record Drawings, O&M manuals, and test certificates during Post-Construction

Additional engineering work resulting from the Main Contractor abandoning the project midway through construction