7.3 Pre-Contract Instruments & Breach Remedies (s.74 & s.75)

Key Takeaways

  • Read the words, surrounding dealings and agreed milestones to determine which obligations a memorandum, letter of intent or award creates.

  • Section 74 requires loss caused by the breach and addresses what follows naturally or what the parties knew at formation was likely. Consider available steps to limit the loss.

  • For a current dispute under section 75, establish the breach and the stipulated damages provision. Assess reasonable compensation within the agreed sum, including any evidence that the sum is unreasonable.

  • For early work, first check any enforceable agreement and its payment terms. Section 71 can apply where the recipient enjoyed the benefit of a lawful, non-gratuitous act.

Last updated: November 2026

Read the commitments in the document

DocumentWhat to look forProject decision
Memorandum of understanding (MOU)Wording that records the plan and any separate obligations intended to bind, such as confidentiality or cost sharing.Identify the parties, definite promises and whether approvals or later execution are required.
Letter of intent (LOI)Authority to start any early activity, agreed terms, cap, expiry and instructions to stop.Confirm who may order work and what is payable, including how the work will be treated if the main contract is concluded.
Letter of acceptance (LOA)Unqualified assent and compliance with the proposal's terms on method and timing.Check whether acknowledgement or formal execution is a condition of commitment. A response that changes price or scope may be a new proposal.

In Ayer Hitam Tin Dredging v YC Chin Enterprises, the Supreme Court read the letter and dealings to decide whether the proposed project contract had been concluded. It found no main contract and allowed a separate claim for reasonable remuneration for preliminary work, subject to the limit it found in that letter. Where signing is explicitly a condition of the main commitment, look for compliance with that condition. Where the essential terms and a present commitment are established, a planned formal document can serve to record the bargain.

For example, an authorised letter and acceptance create an interim contract for bored piling up to RM800,000. The agreed measurement and rates produce RM650,000 earned, with no adjustment or deduction in the example. If the owner shelves the proposed main contract, assess the RM650,000 under the interim terms. If there was neither an interim contract nor a main contract, section 71 of the Contracts Act 1950 may instead require compensation where the contractor lawfully acted for the owner, did not intend the work to be gratuitous and the owner enjoyed the benefit. The statutory test and proof of value matter in that scenario. The original price or budget does not fix the amount.

Analyse breach before choosing compensation

Under section 40, if a party refuses or disables itself from performing the whole of its promise, the promisee may end the contract unless its words or conduct show acquiescence in its continuance. Read any applicable contractual notices and the facts before acting. Section 76 permits compensation for damage sustained through non-fulfilment by a person who rightfully rescinds.

Section 74 compensates for breach-caused loss that arises naturally in the usual course or that both parties knew at formation was likely to result from the breach. It excludes remote and indirect loss. A supported additional cost of replacing defective work may fall in the first category. An unusual liability to a financier needs evidence about what the parties knew and the connection between breach and loss. Learning of a special liability after award does not establish that knowledge at formation. The explanation to section 74 requires taking available means of remedying the inconvenience into account. For example, record the cost of reasonable temporary covers and the damage those covers would avoid.

Apply section 75 to an agreed sum

Under section 75, a breach with a named sum or other stipulation by way of penalty may give rise to reasonable compensation up to the stipulated amount. In Cubic Electronics v Mars Telecommunications, the Federal Court explained that the claimant initially establishes the breach and the applicable clause. Actual loss need not be proved as a prerequisite in every case. Once the initial requirements are established, the defaulting party bears the burden of showing unreasonableness. Legitimate interest and proportionality are relevant, and actual loss can be evidence in assessing reasonableness.

For a late-performance claim, read section 56 and the agreed completion and extension clauses. Where the contract is voidable for late performance and the promisee accepts that performance, section 56(3) ordinarily requires notice of an intention to claim delay loss at the time of acceptance.

For a current project with delay damages of RM12,000 per day, an operative completion date allowing for extensions, and 20 days of proven delay after that date, the stipulated amount is 20 × RM12,000 = RM240,000. Assume any applicable notice and certification requirements have been satisfied. RM240,000 is the ceiling under the provision and the reasonable sum remains open to challenge. Keep the extension decisions, contractual notices, dates and any evidence addressing the commercial interest in timely completion.

Check whether specific relief fits

Under the Specific Relief Act 1950, section 11 identifies when specific performance may be available and section 21 makes the relief discretionary. Section 20 excludes contracts where money is adequate or whose details or dependence on personal qualifications make enforcement of material performance impracticable. This is relevant to an order compelling a named engineer to complete a personal and technically detailed appointment. Sections 50–55 govern preventive relief, including temporary and perpetual injunctions and the circumstances for a mandatory injunction. For example, check the statutory requirements and any adequate alternative remedy before seeking to restrain a threatened disclosure in breach of a confidentiality clause.

Contracts Act 1950 · Ayer Hitam Tin Dredging judgment · Cubic Electronics judgment · Specific Relief Act 1950

Test Your Knowledge

A 2026 building contract provides for delay damages of RM10,000 per day. The contractor completes 30 days after the extended completion date, and the contract’s requirements for notices and certification have been met. The contractor says the developer cannot show lost rent. Which statement applies under section 75 and Cubic Electronics?

A

The developer recovers zero LAD because Section 75 requires strict proof of actual financial loss whenever tenant leases are not yet executed

B

The developer can recover more than RM300,000 if it proves actual financing interest exceeded RM10,000 per day

C

The LAD clause is automatically void as a penalty unless the developer submits pre-tender cost-of-delay spreadsheets

D

If the developer proves the breach and the relevant clause, it may recover reasonable compensation up to RM300,000. The contractor can challenge the reasonableness of the stipulated amount.

Test Your Knowledge

A Selangor developer claims RM2 million from a contractor for one week of drainage delay. The amount is an unusual liability to a financier, does not arise in the ordinary course of a week’s delay, and was unknown to the contractor when the parties agreed. Why is that item outside section 74 on these facts?

A

It neither arises in the usual course nor was known by the parties at formation as a likely consequence of breach.

B

Under Section 74, damages are restricted exclusively to physical rectification cost and never include financial penalties

C

Under the Specific Relief Act 1950, undisclosed financier penalties can only be enforced by injunction

D

The contractor is shielded by Section 64 because late completion constitutes partial remission of performance

Test Your Knowledge
Fill in the Blank

No interim or main contract was concluded. A contractor lawfully executes preliminary piling for the employer at its request, intending to be paid. The employer enjoys the benefit. What section of the Contracts Act 1950 addresses compensation for this benefit? Enter the section number.