8.1 Time, Variations, EOT, LAD & Defects Liability Administration
Key Takeaways
Check the authority to instruct, the scope of the variation and the contract’s valuation method. A consultant must also check the limits in the separate appointment.
An extension of time depends on the applicable event, notice and evidence of delay to completion. Review costs under their own entitlement rules.
Use the operative completion date and the actual certification requirements to calculate delay damages. Section 75 limits reasonable compensation to the stipulated amount.
Practical completion, defects rectification, retention and final settlement each have separate contractual milestones.
Establish the change and the authority to instruct
A variation changes work under a power in the works contract. Before issuing or acting on an instruction, identify the affected documents, confirm that the change is within the power, and check who can sign and whether a financial approval is required. Record the original requirement, the instruction, any effect on programme, and the quantities and rates. A discussion at a site meeting may leave the authority and valuation unresolved.
Under PAM 2018 With Quantities, clauses 2 and 11 address the Architect's instructions and variations. Use the prescribed written instruction or confirmation procedure. Clause 11.6 gives the following bases:
| Work to value | Basis used under this form |
|---|---|
| Similar character and conditions, with no significant change in quantity | Rates and prices in the contract documents |
| Similar character with changed conditions or materially changed quantity | Contract rates and prices with a fair adjustment |
| Work of different character | Fair market rates and prices determined by the Quantity Surveyor |
| Work that cannot properly be measured and valued under those routes | The daywork route, with the supporting records specified by the clause |
The consultant's appointment can also limit what the consultant may instruct. Under BEM Form 1999, Conditions of Engagement clause 5.9 requires prior client approval for an instruction the engineer considers likely to increase the cost of the works by more than the amount in memorandum clause 7, unless obtaining approval is impracticable in the circumstances. An urgent variation where delay risks injury, property damage or a claim against the client illustrates that exception. In those circumstances inform the client as soon as possible. Verify the actual amount and any contractual amendments.
Assess time and costs separately
Under PAM 2018 With Quantities clause 23.1, start from the earlier date of the Architect's Instruction, its confirmation or the start of the relevant event, where applicable. The initial written notice and supporting information are due within 28 contract Days of that trigger. Check the defined meaning of Day. Clause 23.1(b) addresses the final claim within 28 Days of the end of the cause of delay and allows longer time for particulars if the Architect agrees in writing. Clause 24 sets its own conditions for loss or expense. Under PWD Form 203 clause 43, check the notice of the cause of delay, supporting information and extension certificate. Clause 44 addresses separate loss-and-expense events and a separate notice period. Contract addenda can change these rules.
An assessment needs a timeline and a reasoned link between the event and the completion of the work. Check access, procurement, predecessors and available float before assigning an effect. If two delays overlap, trace each event's impact and apply the contract and applicable law to the time claim and any cost claim. An employer-caused delay can raise questions about the employer's ability to enforce the date. Check the available extension mechanism and whether it addresses the actual prevention event before concluding that the date has lost effect.
Apply the certification and completion rules
For PAM 2018 With Quantities clause 22.1, confirm that the Architect issued the Certificate of Non-Completion (CNC) and that the contract's rate and period apply. Under clause 22.3 a later extension fixing completion later than the date stated on an earlier CNC revokes that certificate. This requires reconsideration of damages, repayment of any surplus within the specified period, and a further CNC if the works are still late against the extended date. For public works, read PWD 203 or 203A clause 40 and the actual addenda. The PWD 203 tender example below illustrates an addendum changing the start and end points for the calculation. Apply Contracts Act section 75 to reasonable compensation, within the amount stated for the operative delay.
For example, assume a single completion date under an unamended PAM 2018 With Quantities contract. It is extended from 1 March to 26 March. Practical completion occurs on 5 April and the form's count yields ten chargeable Days. If the earlier CNC stated the superseded date, reassess any prior withholding and secure the required further certificate. At RM8,000 per chargeable Day the stipulated amount for ten Days is RM80,000, subject to the statutory and contractual conditions.
Practical completion is a contractual milestone. Verify the works, tests and required documents under the form. Check the start of the defects liability period, instructions for making good and any resulting certificate. Under PAM clause 30.6(c) and (d), the Architect issues a certificate for release of half of the retention fund after the applicable practical completion certificate and for the residue after the making good defects certificate. Check partial possession, sectional completion, deductions, the final account and final payment separately. BEM Form 1999 clause 2.7 ties the ordinary end of the consulting appointment to the certificate authorising final payment, which it defines by the release of retention upon completion of the defects or maintenance period.
PAM 2018 With Quantities · PWD 203 tender and addenda · BEM Form 1999 · Contracts Act 1950
A consulting engineer acting under unamended BEM Form 1999 considers an instruction likely to increase the cost by more than the amount in memorandum clause 7. When may clause 5.9 permit an instruction before approval?
Whenever the engineer believes it will help progress.
Whenever bills of quantities rates can be used.
Where obtaining approval is impracticable in the circumstances, such as urgent action where delay puts life or property at risk. Inform the client as soon as possible.
Whenever the change is under 10% of the contract sum.
Order the checks in the unamended PAM 2018 With Quantities clause 11.6 valuation sequence.
Arrange the items in the correct order
Use fair market rates for work of different character.
Use the daywork provision if the work cannot properly be measured and valued under the preceding routes.
Adjust contract rates fairly for similar work with materially changed conditions or quantity.
Use applicable contract rates for similar work under similar conditions with no significant quantity change.
On an unamended PAM 2018 With Quantities contract, the Architect issues a CNC for the original date. A subsequent certificate of extension fixes completion after the date stated in that CNC. The work still finishes late against the new date. What does clause 22.3 require?
The earlier CNC is revoked. Reassess damages, repay any surplus under the clause and issue a further CNC for remaining delay.
The earlier CNC carries forward without reconsideration.
Section 75 allows the employer to ignore the certification clause.
Any extension permanently prevents enforcement of delay damages.