4.4 Existing Energy Baselines, Code Audits, and Retrofit Options

Key Takeaways

  • Calculate connected power from the actual system input watts and count. Divide by the applicable area to calculate lighting power density.

  • Estimate annual energy from power in each operating state and hours in that state. Evaluate demand savings under the actual tariff.

  • Use documentation and site observations to distinguish inadequate light, excess light, and depreciation. Verify the proposed system against the task and applicable code.

  • Type A lamps use a compatible existing ballast, Type B substitutes a line-voltage connection, and Type C uses a separate driver. Check the product listing and instructions.

  • Determine whether lamps qualify for U.S. universal waste management and address suspected PCB ballasts separately.

Last updated: November 2026

Establishing Energy Baselines and Code Audits

Once physical inventories and electrical measurements are complete, the auditor translates field data into an energy and code baseline. Start by calculating total connected lighting load in kilowatts (kW\text{kW}) by summing measured or documented luminaire input watts (lamp plus ballast/driver wattage, not nominal lamp wattage alone) across every fixture type:

Connected Load (kW)=∑(Fixture Counti×Input Wattsi)1,000\text{Connected Load (kW)} = \frac{\sum (\text{Fixture Count}_i \times \text{Input Watts}_i)}{1,000}

For a fully on system at one power level, multiply kilowatts by annual hours to obtain kilowatt-hours. For dimming or reduced output, total each state’s measured power times its hours. Use representative logging and facility schedules for weekdays, weekends, seasonal patterns, and controls. Record which occupancy sensors, schedules and bi-level commands changed the load.

Lighting power density (LPD) is connected lighting watts divided by area. For a preliminary baseline, state the surveyed floor area. For compliance, use the area definition, included or exempt loads, and calculation method in the applicable adopted edition.

LPD=Connected lighting power (W)Area (ft2)LPD = \frac{\text{Connected lighting power (W)}}{\text{Area (ft}^2\text{)}}

Separate utility energy charges from demand charges. An energy rate may change with time of use. Demand may depend on a peak measured over a defined interval or during a defined period. Check the actual tariff and coincident building peak before assigning savings to load shedding or a lower connected load.

Also establish a maintenance cost baseline. If records show 20 replacements per year at $15 per replacement lamp and $25 labor per replacement, the documented replacement cost is $800 per year, before cleaning and disposal. Record access costs in high spaces and verify whether failed-driver replacements are handled differently from spot relamping.

Where measured light is low, inspect cleaning and source history before assuming that the installed design was inadequate. In a suspected overlit room, compare the task area, visibility, and project criteria before eliminating equipment. Dimming may allow the design target to be met with lower input power, but confirm the actual performance.

Worked Baseline LPD and Energy Savings Example

A 10,000 ft210,000\text{ ft}^2 commercial office operates 3,000 hours/year3,000\text{ hours/year} at a blended electricity rate of $0.14/kWh. Currently, it has 125125 four-lamp 32 W32\text{ W} T8 troffers drawing 112 W112\text{ W} each (ballast included) and measures 68 fc68\text{ fc} on the documented task grid. A monitored trial of a 32 W32\text{ W} LED kit measures 38 fc38\text{ fc} at the same grid under comparable conditions. The project target is 35 fc35\text{ fc} average, with separate uniformity and glare checks:

Baseline Connected Load=125×112 W1,000=14.00 kW,LPDbase=14,000 W10,000 ft2=1.40 W/ft2\text{Baseline Connected Load} = \frac{125 \times 112\text{ W}}{1,000} = 14.00\text{ kW}, \qquad LPD_{\text{base}} = \frac{14,000\text{ W}}{10,000\text{ ft}^2} = 1.40\text{ W/ft}^2 Retrofit Connected Load=125×32 W1,000=4.00 kW,LPDnew=4,000 W10,000 ft2=0.40 W/ft2\text{Retrofit Connected Load} = \frac{125 \times 32\text{ W}}{1,000} = 4.00\text{ kW}, \qquad LPD_{\text{new}} = \frac{4,000\text{ W}}{10,000\text{ ft}^2} = 0.40\text{ W/ft}^2 Annual Savings=(14.00−4.00) kW×3,000 hr/yr=30,000 kWh/yr\text{Annual Savings} = (14.00 - 4.00)\text{ kW} \times 3,000\text{ hr/yr} = 30,000\text{ kWh/yr} Annual Cost Savings=30,000 kWh/yr×$0.14/kWh=$4,200/yr\text{Annual Cost Savings} = 30,000\text{ kWh/yr} \times \text{\textdollar}0.14/\text{kWh} = \text{\textdollar}4,200/\text{yr}

The connected reduction is 10.00 kW10.00\text{ kW}. Demand charges fall only if it reduces demand as defined by the tariff. Heating and cooling interactions require a separate assessment.

LED Retrofit Pathways for Existing Luminaires

First choose whether to keep the existing housing and whether compatible, listed equipment is available. Confirm the project’s optical requirements, controls and technology, maintenance access, and emergency function.

Retrofit pathHow it operatesWhat to verify
Type A lampOperates on an existing fluorescent ballast.Exact ballast compatibility, measured system watts, dimming behavior, and the future ballast replacement plan.
Type B lampUses line voltage without the original ballast.The intended single-ended or double-ended arrangement, socket compatibility, markings, and product certification and conversion instructions.
Type C lampOperates with a specified separate driver.Driver and lamp pairing, output and input ratings, available space, and any promised dimming performance.
Retrofit kitConverts the existing luminaire using the kit components and instructions.The host fixture requirements, certification and markings, optical performance, and applicable environmental conditions.
Full replacementRemoves the old luminaire and installs a complete replacement.Mounting, ratings, light distribution, emergency operation, controls, labor, and repair access.

For a Type B conversion, the certification and installation instructions apply to the particular system. A shunted holder connects its pin contacts. It is incompatible where the specified lamp requires those contacts to be separate. Double-ended products also have product-specific wiring and socket rules. Do not assume a design will avoid shock during insertion. Have qualified personnel evaluate the conversion and check that any emergency operation remains suitable.

Waste streams in a U.S. retrofit

  • Lamps: If spent lamps are hazardous waste and managed as universal waste, consult 40 CFR Part 273 and the authorized state program. The federal handler provisions address closed, compatible, structurally sound containers for lamps, labeling and tracking accumulation time. One year is the general federal limit, with a limited exception when needed to facilitate proper recovery, treatment, or disposal under the rule. A low-mercury marketing label alone does not make a waste determination.
  • Ballasts: Suspect older PCB-containing fluorescent ballasts are a separate stream under the Toxic Substances Control Act (TSCA) rules in 40 CFR Part 761. Disposal depends on the PCB-containing component, whether it is intact or leaking, and the associated contamination. Use EPA guidance and the approved disposal process for those facts. Ensure that lamps potentially contaminated by a ballast leak are evaluated separately before routing them as ordinary universal waste lamps.
  • Backup batteries: Record chemistry and condition. Follow the applicable battery waste program, including any state requirements. The path for a battery may differ from that of the lamp or luminaire it powered.

References: DOE utility tariffs and interval data, DOE troffer retrofit guidance, UL conversion kit certification, 40 CFR Part 273, and EPA PCB ballast disposal guidance.

Loading diagram...
LED Retrofit Pathway Selection Logic
Test Your Knowledge

A 20,000 ft220,000\text{ ft}^2 warehouse currently has 8080 metal halide high-bay luminaires, each drawing 458 W458\text{ W} (lamp plus constant-wattage autotransformer ballast). Assuming this is the full lighting load in that area, what is the baseline Lighting Power Density (LPDLPD)?

A

1.45 W/ft21.45\text{ W/ft}^2

B

1.60 W/ft21.60\text{ W/ft}^2

C

1.83 W/ft21.83\text{ W/ft}^2

D

2.29 W/ft22.29\text{ W/ft}^2

Test Your Knowledge

A listed single-ended Type B lamp conversion requires separate contacts in the powered lampholder. Inspection shows that the existing lampholders are shunted. What must the reviewer verify before approving the substitution?

A

Keep the existing ballast connected to limit line voltage.

B

Approve the conversion because all Type B kits fit the same wiring.

C

Replace the remote controls instead of checking the lampholder.

D

Confirm that the listed conversion uses the required non-shunted lampholders and approved arrangement.

Test Your Knowledge

A U.S. school project removes mercury-containing lamps already classified as universal waste and original, unmarked 1974 fluorescent ballasts. The lamps have no PCB contamination. Which approach properly addresses both streams?

A

Treat them all as clean scrap and crush the lamps.

B

Manage the lamps under the applicable universal waste rules and evaluate the ballasts under the PCB rules for the documented legacy equipment.

C

Classify both streams as ordinary trash if the lamp glass is intact.

D

Store both streams indefinitely in unmarked containers.