12.2 Bidding Phase: RFIs, Addenda, Substitutions, and Value Engineering

Key Takeaways

  • Route bid questions through the authorized procurement process.

  • In a federal FAR sealed bid, material information goes to affected bidders in an amendment.

  • Compare proposed equals against salient requirements and evidence for the actual installation.

  • Evaluate effects on cost, schedule, performance and owner requirements before recommending a change.

Last updated: November 2026

Handle questions during bidding

Read the solicitation for the permitted contact, deadline, format and amendment process. A bid RFI identifies the affected sheet, specification paragraph or schedule entry and states what needs clarification. The designer can help prepare the technical answer. The issuing authority controls how it reaches bidders.

For a federal sealed bid governed by FAR 14.208, amend a defective or ambiguous invitation or change its quantity, specification or schedule through the authorized amendment. If information given to one bidder is necessary to prepare bids or withholding it would prejudice others, furnish it to the others in the amendment. The contracting officer considers whether bidders need extra time. A pre-bid conference does not replace a required amendment. Other contracts may call this document an addendum and use a different transmission process.

For example, a cove detail conflicts with the luminaire schedule on remote versus integral drivers. Identify the effect on the price and access needs, confirm the intended system with those responsible, and send a proposed written clarification through the procurement contact. Do not assume informal guidance will amend the solicitation. After award use the construction contract’s interpretation and change process.

Review a proposed equal

Where the solicitation includes FAR 52.211-6, a proposed equal must satisfy the stated salient characteristics. The offeror identifies the product and supplies descriptive evidence and proposed modifications. The contracting officer evaluates on the solicitation basis. In other settings, use the contract’s specified substitution process and authority. A reviewer’s technical opinion and the authorized acceptance are distinct actions.

Review areaEvidence to request
Installed performanceExact delivered lumens and photometry, mounted distribution, glare and uniformity on the same geometry.
Color and controlsRequired color metrics and tolerances, exact driver and protocol, tested low-end behavior and any specified waveform or camera performance.
Equipment and fitRequired listing and environment, physical mounting, clearances and electrical ratings.
Project effectsInstalled watts, life-cycle costs, warranty and service, supply availability, schedule and affected trades.

Two products with equal initial flux and nominal CCT can differ in beam shape, color rendition and control response. Compare curves, planes and reported test conditions. If a difference affects a required criterion, describe the actual test or documentation; distinguish a failure from evidence that remains missing. Ask for a representative mock-up when the documents require it or when a critical behavior needs verification.

Worked proposal comparison

An 80-unit project requires a driver that reliably reaches 1% output in a documented presentation scene. The specified unit uses 30 W at full output. The alternate uses 36 W, provides the same delivered lumens and has a documented 10% minimum. The alternate misses the stipulated scene criterion. Even if another driver addressed that, verify actual compatibility and photometry before recommending acceptance.

At 3,500 full-load equivalent hours and the same rate, the 6 W difference per luminaire adds 80(6)/1,000=0.48 kW80(6)/1{,}000=0.48\text{ kW} and 1,680 kWh per year. At 0.15 USD/kWh the difference is 252 USD per year. Use the actual expected operating loads in a proposal. This example assumes neither different schedules nor HVAC or demand-charge effects. Send the objective findings to the authorized decision maker.

Evaluate value and scope together

A value-engineering proposal should explain the change, affected requirements, cost and schedule, and how it preserves required function. For example, standardizing trims can reduce purchase and stock costs. First verify aperture, finish, aiming and optical performance in existing ceiling conditions. Ask what happens to spare stock and replacement compatibility. Record costs across the useful period, document any required design revision and confirm who authorizes it. A proposed saving achieved by deleting required control behavior or an emergency function needs review against the governing requirements before any approval.

Record the disposition and any procurement impact

Keep the bidder inquiry, drawings, technical response and issued amendment together. If the response changes product availability or quantity, ask the issuing authority to review whether the bid schedule still works. If a supplier proposes a substitution with a different delivery date, assess which affected trades and tests must move, including rough-in and controls integration. Record the proposal’s date, the assumptions used and the person authorized to decide it. The record should let a later reviewer distinguish a product that met the requirements from one for which the bidding documents were changed through the authorized process.

Compare proposals on the same scope. For example, a lower equipment price may omit compatible trim or commissioning. Include those activities in the comparison and send unresolved allowances or exclusions to the procurement lead.

References: FAR 14.208 and 14.211, FAR 52.211-6, FAR value engineering, and IES commissioning practice.

Loading diagram...
Bid and Substitution Decisions
Test Your Knowledge

In a federal FAR sealed bid, a bidder identifies a fixture-voltage ambiguity that affects proposals. How should the technical response be handled?

A

Leave the answer with that bidder only.

B

Advise bidders to pick whichever voltage costs less.

C

Issue a construction change after the call.

D

Route the clarification to the contracting officer for a solicitation amendment giving affected bidders the information.

Test Your Knowledge

A specified installed scene requires stable 1% output. The proposed equal has the same lumens and CCT, but the documented minimum with the specified controls is 10%. What should the reviewer report?

A

The proposed configuration misses the documented low-output requirement.

B

Matching flux and CCT establishes equivalence.

C

A 10% input-power rating always yields 1% light output.

D

The life-safety lighting test will establish normal dimming equivalence.

Test Your Knowledge

What makes a proposal to consolidate corridor trim types technically credible?

A

It reduces cost without needing a check of installed performance.

B

The supplier offers a larger nominal warranty regardless of fit.

C

The team verifies fit, appearance, output and controls against the requirements and documents cost and service impacts.

D

It transfers all approval authority to the supplier.