12.3 Construction Phase: Submittals, Field Observations, and Change Orders

Key Takeaways

  • Check the submitted configuration and explicit deviations against the contract.

  • Record field conditions, required corrections, responsibilities and retest criteria.

  • Under the AIA example, distinguish minor instructions, directives and agreed change orders.

  • A review stamp, field discussion or RFI response is not itself approval of an unpriced scope change.

Last updated: November 2026

Review submittals against the stated design

For project systems requiring submittal, request the documents specified by the contract. These may include product data, exact photometric files, wiring and control details, emergency equipment evaluation, shop drawings, dimensions and installation instructions. Review the approved versions together. A custom pendant submittal may need the finish and optics as well as coordination with the structure and wiring. Verify which party supplies each support or driver and what access is required.

AIA A201–2017 provides one example. The contractor reviews and coordinates the information, including field criteria. The architect reviews for the limited purpose stated in the contract. The contractor must call out deviations and follow the approval provisions for them. Review terms and status labels vary. If a submission lacks the required control and mounting data, return it for correction using the applicable resubmittal status. Do not assume a status label authorizes work outside the project’s specific process.

Observe work and record deficiencies

Schedule field observations where they inform a decision. Before a ceiling closes, compare routing, support, fixture placement, access and the installed equipment with drawings and approved information. Check emergency wiring under the adopted edition, including permitted exceptions. If normal and emergency conductors appear to share a box, identify the circuits and enclosure function and route the observation to the responsible electrical professional. Do not declare compliance or a violation from wire color or enclosure presence alone.

For cove or facade lighting, test an early portion with actual finishes and viewing positions before repeating it across a site. After installation, observe the distribution, shielding and reflections in the relevant scenes. For an outdoor area, include nighttime views and property boundaries. Coordinate focusing and aiming through the project team, confirm installed orientation and compare actual performance with the approved criteria.

A field observation report records what was observed and where. A punch list tracks items requiring correction or completion. Use specific locations, references and measurable outcomes. For example, identify the device and zone that fails to dim, the command and measured response, the criteria, who will address it and how the team will retest. Follow the contract for closure and payment decisions. The observation does not transfer contractor responsibilities.

Select the applicable post-award instrument

In the AIA A201–2017 example, the architect can issue a written minor change consistent with the intent of the contract when no adjustment of contract sum or time is involved. AIA G710 is an example of the architect's supplemental instruction used for this purpose. If the contractor believes the adjustment affects time or price, follow the notice and change procedure. An RFI response communicates a clarification. It does not by itself resolve a price or time change.

AIA exampleWhen the project uses it
Supplemental instructionClarification or authorized minor change consistent with the contract and without a sum or time change.
Construction change directiveOwner and architect direct a change before agreement with the contractor on the affected sum or time. The contract governs valuation and any unresolved claims.
Change orderThe authorized parties record an agreed change in work and any corresponding adjustment to sum and time.

For a clarification during construction, distinguish the observed condition, the requested interpretation and the contractor’s proposed solution. Attach the marked detail, note the date the response is needed, and identify affected electrical and architectural sheets. If a mounting conflict moves light away from its target, compare the revised distribution before accepting the location. Give the field team the current detail and note the updated revision in the project record. Confirm the fix on the next visit.

Worked scope and cost check

The owner requests 18 added gallery track heads at 420 USD material and 110 USD labor each, and 120 ft of track at 35 USD per foot installed. Assume the stated contract permits a 15% markup on both cost items. Direct cost is 18(420+110)+120(35)=13,74018(420+110)+120(35)=13{,}740 USD. The proposed price is 13,740(1.15)=15,80113{,}740(1.15)=15{,}801 USD. Check electrical support, procurement time, circuit and dimmer capacities, circuit changes and the specification. Cost calculations do not authorize work.

If the owner, contractor and architect agree on the changed work and any sum and time adjustment under the example contract, use its change-order process. If direction is needed before agreement, use the contract’s authorized directive if available. A price change does not fit the no-cost, no-time adjustment premise for the minor-change instrument.

References: AIA A201–2017 summary, AIA supplemental conditions guidance, AIA G710, AIA G714, and AIA G701 instructions and authorization scope.

Loading diagram...
Field Decision and Change Documentation
Test Your Knowledge

A custom pendant submittal has the wrong specified CCT, omits required driver data and shows an incompatible mounting detail. What response fits a project with a revise-and-resubmit status?

A

Approve for fabrication and discuss the issues after delivery.

B

Return it with the specific issues and request a coordinated resubmission before work relying on approval proceeds.

C

Issue an unrelated bid addendum.

D

Assume that the omission is equivalent to compliance.

Test Your Knowledge

A site observation finds a shared junction box with identified normal and emergency conductors. What is the appropriate review step?

A

Approve solely because the conductor colors differ.

B

Treat it only as an energy-code daylight issue.

C

Assume it complies because there is generator power.

D

Document the condition and verify the applicable emergency wiring separation requirements and any permitted exception.

Test Your Knowledge

Under the stated AIA A201–2017 arrangement, a minor luminaire relocation is consistent with design intent and has no effect on contract sum or time. Which is an appropriate architect-issued instrument?

A

A supplemental instruction such as G710.

B

A new federal invitation for bids.

C

A construction change directive solely to obtain an unneeded price adjustment.

D

A purchase order to the luminaire vendor.