10.3 Lighting Economics: Energy Cost, Simple Payback, and Life-Cycle Cost Analysis
Key Takeaways
Energy savings in kWh and bill savings in dollars are different quantities.
Demand charges need a tariff and evidence of coincidence with the billing peak.
Choose and state the study period, discount basis, timing, maintenance and residual assumptions.
Use simple payback for screening. Compare discounted cash flows on a consistent basis.
Separate the quantities on the utility bill
Estimate energy by multiplying input kW by hours in the same operating state, then summing states. Multiply kWh by the applicable energy prices to find cost. Use measurements or logged schedules when hours differ across alternatives. A dimming command is not the system’s measured input power.
Demand charges depend on the utility’s tariff and the interval or other method used for billing demand. A 30 kW connected lighting reduction gives 30 kW of billing-demand savings only when the revised peak calculation supports the full reduction. The new peak can occur at another time. Check coincidence, season, rate and any minimum-charge or ratchet rules.
HVAC interaction depends on where heat is released and the building’s heating and cooling response. Lower lighting input may reduce cooling load when the lights and cooling operate together. It can also increase demand for heat at other times. An estimate of the change in lighting heat is not a direct measurement of HVAC electricity saved. Model or measure the specific interaction if it matters to the investment.
Compare the options over the same horizon
| Metric | Application |
|---|---|
| Simple payback | For constant annual savings, divide net initial cost by annual net savings. It gives a quick estimate of recovery time and ignores discounting and post-payback costs. |
| Simple annual return | Annual net savings divided by net initial cost. State the convention because an ROI report can use a different period or denominator. |
| Net present value (NPV) | Discount future net cash flows to the base date and subtract the initial net investment. A positive NPV means the transaction exceeds the assumed discount benchmark under the modeled cash flows. |
| Internal rate of return (IRR) | Solve for the discount rate at which project NPV is zero. Report its cash-flow basis. A change in cash-flow sign more than once can give multiple roots or no useful rate. |
| Life-cycle cost (LCC) | Add present values of costs on a common study horizon, including initial, operation, maintenance, replacements and net end-of-period amounts where applicable. Compare alternatives delivering the required performance. |
For a constant end-of-year saving , with discount rate and years, compute . At the multiplier is . Match a real rate to constant-dollar cash flows or a nominal rate to nominal flows. Use separately timed flows if replacements, incentives, utilities or disposal occur on a different schedule. Discounted cost comparisons assume a consistent base year and study period.
When preparing a proposal, keep a record of what was measured and what was estimated. Existing equipment input, combined occupancy and daylight schedules, and the owner’s rate sheet provide different evidence. Compare alternatives delivering the same required illumination and distribution. If a proposed product changes access or cleaning costs, include that difference explicitly. A contractor’s installed price belongs in the base-year cash flow unless the payment is scheduled later.
Worked warehouse comparison
A warehouse has 100 fixtures drawing 458 W each for 4,000 hours a year. Its proposed LED system has 100 fixtures drawing 158 W each and logs an estimated 3,200 equivalent full-load hours. Assume a flat energy price of $0.12/kWh. Both systems are modeled at full lighting input at the monthly facility billing peak, at $10 per kW per month. These are hypothetical operating and tariff inputs.
| Annual input | Existing | Proposed |
|---|---|---|
| Connected load | 45.8 kW | 15.8 kW |
| Energy | 183,200 kWh | 50,560 kWh |
| Energy cost | $21,984.00 | $6,067.20 |
| Demand cost | $5,496.00 | $1,896.00 |
| Maintenance | $2,500.00 | $400.00 |
| Total | $29,980.00 | $8,363.20 |
The retrofit costs $36,000 installed and receives a $12,000 initial rebate. Net initial cost is $24,000 and annual projected savings are $21,616.80. Simple payback is about 1.11 years, and simple annual return is 90.07% on this basis.
At a real discount rate of 6% and ten equal year-end flows, the present-worth multiplier is 7.360087. For this exercise assume no additional HVAC effect, replacements or end-of-period cost difference. Existing LCC is about $220,655.41. Proposed LCC is about $85,553.88, including the initial cost. The difference is a retrofit NPV of about $135,101.53. Under the same cash-flow assumptions solving for zero NPV gives an IRR of about 89.92%. These are numerical outputs for the modeled case. Test changes in hours, demand coincidence, incentive and component replacement before using the proposal to make a decision.
For a sensitivity check, suppose the LED savings at the billing peak vanish because the facility peak moves. Removing the $3,600 annual demand savings leaves $18,016.80 per year in the comparison. Applying the same factor to the lower net savings reduces the modeled NPV to about $108,605.22. If a future replacement is also needed, enter it in the year it is expected. For example, a $5,000 replacement at the end of year 7 has a present cost of about $3,325 at 6%. A decision maker can compare these documented scenarios and ask for better evidence where uncertain assumptions matter most.
References: NIST Handbook 135, 2025 edition, DOE energy and utility cost savings guidance, and NREL measurement and verification guidance.
A lighting retrofit reduces connected power by 20 kW. What should an analyst do before crediting coincident demand and cooling savings?
Credit 20 kW across every bill and treat all lighting watts as annual HVAC electricity savings.
Check the utility billing peak and determine the building-specific HVAC interaction.
Infer demand savings from fixture efficacy without operating data.
Ignore coincident billing demand and enter the reduction as 20 kWh/year.
Two upgrades have equal simple payback. One needs a major overhaul after payback. Which comparison accounts for this difference?
Choose solely by initial price.
Count only savings before the payback date.
Discount all relevant cash flows across the same study horizon, including the overhaul.
Treat the two options as economically equivalent.
An upgrade costs $40,000 net and saves $10,000 at each year end. The applicable study-period present-worth factor is 5.7466. What is its NPV?
$17,466.
$40,000.
$57,466.
$80,000.