10.1 Energy Codes: ASHRAE/IES 90.1, IECC, and Title 24 Compliance
Key Takeaways
Verify the adopted edition and amendments before applying an allowance or threshold.
Building Area and Space-by-Space calculate the general interior allowance from different classifications.
Special-function allowances and exemptions have eligibility, installation and control conditions.
Review installed power, control sequences and applicable acceptance procedures separately.
Establish the governing rules
A lighting energy review starts with the jurisdiction, building classification, permit scope and adopted edition. ASHRAE/IES Standard 90.1 addresses buildings and sites within its scope, except low-rise residential buildings. ASHRAE’s 2025 edition revises items such as decorative lighting allowances. A jurisdiction may use an earlier edition. The International Energy Conservation Code (IECC) has commercial and residential provisions. Read the adopted path before borrowing a table or control limit from another code. In California, the Energy Code is Title 24, Part 6. Different occupancy and building categories have different provisions.
Lighting energy review addresses both installed power and control functions. A design can fall within the allowed watts while failing required control tests. Estimate annual use and visual performance separately. Connected power density is a code input, while hourly electric lighting consumption also depends on operation.
Calculate the interior allowance
Lighting power density (LPD) is lighting power per unit area. Determine what input watts count as installed power, including applicable driver or ballast input and specific treatment of track, limited or adjustable equipment, and exempt functions. Use the applicable area definition.
| Prescriptive method | Calculation and scope |
|---|---|
| Building Area | Classify the building areas by permitted use. Multiply each applicable area by its table rate and use the compliant sum. |
| Space-by-Space | Classify individual spaces, multiply area by the corresponding rates, and sum eligible general allowances under the governing rules. A mixed-use floor can have separate types for open office, enclosed office, meeting and circulation. |
Check the edition’s provisions for tall or unusual rooms and the evidence required to claim an adjustment. Track separately controlled special-function lighting. For example, the 2024 IECC C405.3.2.2.1 limits additional lighting power to the specified function. A qualifying decorative or display allowance cannot offset general lighting. Exemptions likewise depend on the adopted list and conditions.
Worked general allowance
The following rates are hypothetical exercise inputs, expressed in W/ft². Use the rates from the adopted tables on an actual project.
| Space | Area (ft²) | Stipulated rate | Allowed W | Proposed W |
|---|---|---|---|---|
| Open office | 6,000 | 0.61 | 3,660 | 3,200 |
| Enclosed offices | 1,500 | 0.74 | 1,110 | 1,050 |
| Meeting rooms | 1,000 | 0.97 | 970 | 1,120 |
| Corridors | 1,000 | 0.41 | 410 | 380 |
| Lobby | 500 | 0.84 | 420 | 480 |
| Total | 10,000 | 6,570 | 6,230 |
Assume this example permits pooling the general allowances. The general installed power is 340 W under the general allowance. The individual meeting-room and lobby line items being above their rates does not invalidate the pooled calculation. Verify that proposed watts are complete. A separate allowance for decorative lighting would require the qualifying luminaires and controls to be documented.
Exterior budget and required controls
Determine the lighting zone using the adopted code and site designation. Verify applicable base, tradable and restricted allowances, including how the code measures the areas or lengths. For a store, draw the parking bays, entrances and facade features. Track a feature-only allowance against its eligible equipment. A site meeting a wattage limit still needs a check of location, controls and any outdoor light ordinance.
For controls, check local operation, automatic shutoff or reduction, daylight response, interior and exterior schedules and applicable exceptions. Use the actual room types, affected power and prescribed sequences. For the 90.1-2022 daylight example in Chapter 8, review the primary and toplighted thresholds, combined primary/secondary threshold, and overlap rules. A project governed by a different edition needs its own control check.
For a retail renovation, start with the scope of new and retained equipment and determine how the alterations provisions apply. Show display luminaires, general lighting and any claimed exemptions in distinct schedule columns. Use installed input watts and the applicable track calculation. Mark each required local switch, daylight control area and special-function control on the drawings. A reviewer can then trace a line item to the luminaire schedule and confirm which installed units the controls actually operate.
California example
The 2025 California Energy Code took effect January 1, 2026. For nonresidential work, use the applicable §130.1 indoor provisions and required compliance documentation. The California Energy Commission describes manual controls, multilevel control and automatic shutoff with space-specific conditions. Review the actual occupant-sensing requirements and accepted sequence for each space. Where required, document nonresidential lighting control acceptance through the applicable CEC forms and technician requirements. For example, §130.1(b) is a separate multilevel control check for applicable enclosed spaces of 100 ft² or larger with a general lighting load above 0.5 W/ft². A 160 ft² office with 96 W of general lighting has . If no exception applies, the required multilevel control must provide continuous dimming from full power to 10% or less. This check does not substitute for the separate shutoff review. For dwelling unit lighting, check the relevant sections and whether Joint Appendix JA8 applies to each source or luminaire, including stated exceptions.
References: ASHRAE 90.1 editions, DOE 90.1-2022 reference manual, ICC 2024 IECC index, 2024 IECC code development record, CEC effective date, CEC 2025 Energy Code, CEC nonresidential indoor lighting guidance, and CEC dwelling unit lighting FAQs.
In a 2024 IECC Space-by-Space calculation, general lighting is 250 W above its total allowance. There is unused allowance for luminaires specifically highlighting merchandise. How should the reviewer treat it?
Move those unused watts into the general lighting allowance.
Keep the additional allowance with its eligible function and resolve the general lighting overrun separately.
Relabel general lighting as display lighting without changing how it is used.
Exclude all connected luminaires in the sales area from the calculation.
Using the hypothetical Space-by-Space table, what is the margin for general installed power if pooling is permitted?
210 W over.
340 W over.
460 W below.
340 W below.
A California nonresidential tenant project is under the 2025 Energy Code. Its power worksheet passes. What scope still requires review before claiming lighting energy compliance?
Verify the applicable §130.1 control sequences and required acceptance documentation.
Assume high-efficacy luminaires waive the lighting controls.
Use dwelling-unit JA8 certification as the only lighting control evidence.
Use a separate fixture only if it draws more than 100 W.