3.4 Standards, Codes & Welding Procedure Specs
Key Takeaways
Module 08303 covers codes, standards, specifications, WPSs and material identification. Verify the applicable edition and approved project requirements.
ASME B31.1 covers power piping in its defined scope, including specified boiler-external piping. B31.3 covers process piping with its own inclusions and exclusions. Confirm the code of record for the line.
Material specifications (for example ASTM A106, A53) define product chemistry, manufacture, and testing; pipefitters identify and install to the specified grade.
The WPS states approved production variables. Confirm its qualification basis and the welder’s separate performance qualification as applicable.
Install only to approved drawings and procedures; when field conditions conflict with documents, stop and obtain authorized change rather than improvising.
Standards, Codes & Welding Procedure Specs
Quick Answer: Module 08303 builds literacy in codes, standards, and specifications—especially ASME B31.1 (power piping) and B31.3 (process piping)—plus material specs, WPS purpose, and identification of pipe and components. Pipefitters do not write the code, but they must follow approved drawings and procedures and recognize when something is outside what those documents allow.
Construction uses the rules and edition adopted for the line and the approved project documents. Fundamentals items ask which documents define the design, material, dimensions and production work.
Specs vs codes vs standards (working definitions)
Training language varies slightly by instructor, but the useful field distinctions are:
| Term | Meaning for the pipefitter |
|---|---|
| Code | A body of rules for design, construction or other work. The applicable adoption, law or contract determines its obligations for the job. |
| Standard | A published consensus document (dimensional, material, or practice) often referenced by codes and specs (ASME, ASTM, API, AWWA, etc.) |
| Specification (spec) | Project-, owner-, or manufacturer-specific requirements that may equal or exceed code minimums—materials, testing, documentation, welding, coating, cleanliness |
| Drawing / isometric | The approved geometric and BOM instructions for this spool or line |
| Procedure (WPS, hydro procedure, torque procedure) | Step-by-step approved method to perform a controlled activity |
Key Point: Follow a stricter approved project requirement when it is consistent with the governing code. Refer actual conflicts for authorized resolution. Verify the edition, code boundary and approved drawing revision.
ASME B31 piping code family
The B31 Code for Pressure Piping has sections with defined scopes. Verify the section and edition invoked for the specific line and its interfaces. One facility can have piping under different rules.
| Code section | What its scope includes |
|---|---|
| ASME B31.1, Power Piping | Power piping typically found at generating stations, industrial and institutional plants, geothermal systems and central or district heating and cooling. This includes specified boiler-external piping for power boilers under its scope. |
| ASME B31.3, Process Piping | Design, materials, fabrication, erection, examination, inspection and testing for process piping typically found in refineries, chemical plants and related facilities. It can include utilities such as steam and water where within scope. |
Boundary example. A refinery may have both a process steam header and piping required to comply with B31.1 at power boilers. B31.3-2024 §300.1.3(b) excludes power boilers covered by BPVC Section I and boiler-external piping required to conform to B31.1. Trace the code break from the engineering line list and drawings. The fact that the commodity is steam does not establish the code for both runs.
Apply the chosen code’s own pressure, temperature and examination provisions. For existing systems, identify the adopted in-service inspection and repair rules. For example, ASME PCC-2 covers repair methods after equipment and piping are placed in service where that standard applies.
Material specifications at awareness level
ASTM (and similar) material specifications define how pipe and fittings are made and tested. Pipefitters encounter them on drawings, stencils, and material test reports (MTRs).
Examples frequently cited in industrial carbon steel work:
| Spec (examples) | Awareness-level idea |
|---|---|
| ASTM A106 | Seamless carbon steel pipe for high-temperature service (grades such as B common in industry) |
| ASTM A53 | Black or hot-dipped zinc-coated welded and seamless steel pipe, ordered by type and grade |
| ASTM A333 | Low-temperature carbon/alloy steel pipe (when specified for cold service) |
| ASTM A312 | Seamless, welded and heavily cold-worked welded austenitic stainless steel pipe within the specification |
| ASTM A105, A234, A182 | Respectively, carbon steel forgings for piping, specified wrought carbon/alloy steel fittings, and specified forged or rolled alloy/stainless flanges and forged fittings |
The ASTM product specification provides material and manufacturing requirements. A dimensional standard such as ASME B36.10 provides size and wall designations. Verify them together on the order and drawings.
- Confirm the specified material appears on the stencil/MTR
- Do not substitute "equivalent looking" material without engineering approval
- Understand that grade (A, B, C, etc.) and type (seamless vs ERW, etc.) matter
- Keep MTRs and heat numbers when the QA program requires traceability to the installed location
Welding Procedure Specification (WPS)
Read the WPS for the approved production process, base metal and thickness range, filler, position, joint preparation, preheat, interpass limits and PWHT as applicable. Check the engineering joint detail as well. Under B31.3-2024 §328.4.3, the WPS controls root opening and the WPS and engineering design control alignment of inside surfaces at girth and miter groove welds. Section 328.5.1(c) requires qualified personnel for tack welds.
| Document | Role |
|---|---|
| WPS | Approved production welding instructions and parameter ranges |
| PQR | Certified record of the actual applicable test-coupon variables and qualification results supporting a WPS |
| WPQ | Separate record of the welder’s performance qualification and applicable limits |
Qualification routes. For B31.3-2024 work, §328.2 invokes the applicable ASME BPVC Section IX with stated modifications. Under Section IX QW-200, a qualified procedure can draw on one or more supporting PQRs. B31.3 §328.2.1 permits listed AWS Standard WPSs when adopted under Section IX Article V limitations. Section 328.2.2 permits use of a procedure qualified by others if the owner approves and the paragraph’s conditions are met. Check the actual procedure basis and the employer’s available qualification records. The approval of a procedure does not qualify an individual welder.
Use the issued WPS and drawing for the joint. If fit-up, material or an essential variable falls outside the approved ranges, stop and have the issue resolved before welding. Use the selected code’s procedure-qualification provisions on B31.1 work as well.
Pipe and component identification
Check the identity of components using the markings, purchase documents and quality records required for the job:
- Pipe: spec, grade, NPS, schedule/wall, heat number
- Fittings: size, rating/class, material, heat when required
- Flanges: size, facing, class, material, bore matching pipe schedule when specified
- Valves: figure number, rating, end type, trim as specified
- Gaskets and fasteners: material and grade per bolt-up procedure
Mismatched class (for example a Class 150 flange on a Class 300 system) is a classic construction error with severe pressure-boundary consequences. Read the drawing BOM and the component stamping—do not assemble by "bolt hole count looks right."
Following approved drawings and procedures
Professional pipefitting is document-driven:
- Latest revision of the isometric or orthographic—check the revision cloud and title block
- Line class / pipe class on the drawing points to materials, valves, and gaskets allowed on that commodity
- Notes may require PMI, special cleaning, oxygen service, NDE hold points, or soft-gasket rules
- Field changes follow the authorized disposition process. Record approved design changes in the controlled drawing set
- Hold points in the approved plan identify activities awaiting a required check or release. Keep joints accessible for the specified examinations and test
When drawings conflict with field conditions (interference, wrong nozzle projection, missing support steel):
- Stop before cutting permanent work that locks in the error
- Document the conflict
- Obtain authorized disposition
- Update as-built/red-line records per site procedure
Scenario: B31.3 process line vs "we always do it this way"
The approved B31.3 process-line WPS allows a root opening of 1/8 in ± 1/32 in and requires a minimum preheat. The field fit has a 1/4 in opening, above the allowed maximum of 5/32 in. Correct the fit or obtain an approved disposition consistent with the governing procedure. Verify the required preheat before tack welding and maintain it as specified during production.
Putting Module 08303 together
- Know code vs spec vs drawing vs WPS—each has a role.
- Remember B31.1 power and B31.3 process at awareness level.
- Treat ASTM/material specs as identity requirements, not suggestions.
- Use the WPS and joint detail for fit-up and production variables.
- Install only to approved documents; escalate conflicts instead of improvising.
Combined with hand tools, power threading, and materials/NPS literacy, this standards awareness completes the Pipefitting Fundamentals domain (modules 08102, 08103, 08303—15 assessment items). Work document-smart as well as tool-smart, and both the exam and the plant stay on the right side of the code.
Which ASME code section covers process piping within its scope in a refinery or chemical plant?
ASME B31.1
ASME B31.3
ASME Section IX only, with no B31 section
ASTM A106, which is itself a piping design code
What is the primary purpose of a Welding Procedure Specification (WPS)?
To list payroll hours for the welding crew
To specify the approved production welding variables and ranges for the joint
To replace the engineering joint design and spool drawing
To grant a welder any performance qualification needed for the work
An approved project specification is stricter than, and consistent with, the invoked code minimum. Which requirement should the pipefitter follow?
Follow the stricter project specification requirements
Ignore the project spec and use only the code minimums
Average the two requirements and split the difference on wall thickness
Substitute any material as long as the outside diameter matches
The drawing identifies a run as boiler-external piping for a 150 psig power boiler built to ASME BPVC Section I. Which B31 section covers that run?
ASME B31.9 Building Services Piping
ASME B31.3 Process Piping
ASTM A106/A106M
ASME B31.1 Power Piping