2.4 Building Drains, Building Sewers & Private Interceptor Main Sewers

Key Takeaways

  • Table 382.30-3 lets a 4-inch building drain or sewer carry 180 dfu at 1/8 inch per foot, 216 at 1/4 inch and 250 at 1/2 inch; 1/16-inch pitch is permitted only at 8 inches and larger.

  • A gravity-flow sanitary building sewer must be at least 4 inches in diameter; pressurized sewers must be at least 2 inches for ejectors and sewage pumps and 1-1/4 inches for grinder pumps.

  • The top of a building sewer must be at least 42 inches below finished grade, or 18 inches where it discharges to a septic tank, holding tank or grease interceptor.

  • Frost protection is required where the sewer top is less than 60 inches below a snow-cleared surface or less than 42 inches below a surface not cleared of snow.

  • Buried nonmetallic sewers draining to municipal mains need locating means, such as 18-gauge insulated copper tracer wire with green insulation within 6 inches above the pipe.

Last updated: October 2026

Definitions that drive the answer

  • Building drain: horizontal piping within or under the fully enclosed part of a building, below the lowest fixture, that drains by gravity to the building sewer (SPS 381.01 (39)).
  • Building subdrain: the horizontal portion that does not flow by gravity to the sewer, so it discharges to a sump (SPS 381.01 (47)).
  • Building sewer: the part of the drain system outside the fully enclosed building that conveys discharge to a public sewer, private interceptor main sewer, POWTS or other discharge point (SPS 381.01 (44)).
  • Private interceptor main sewer: a sewer serving 2 or more buildings that is not part of the municipal system (SPS 381.01 (193)).

Table 382.30-3: building drains, subdrains, sewers and private interceptor main sewers

Diameter (in.)1/16 in./ft1/8 in./ft1/4 in./ft1/2 in./ft
1-1/4NPNP11
1-1/2NPNP33
2NPNP69
3NP364250
4NP180216250
5NP390480575
6NP7008401,000
81,4001,6001,9202,300
102,5002,9003,5004,200

NP means not permitted. Pipes 3 to 6 inches cannot be laid at 1/16 inch per foot, and pipes 2 inches and smaller need at least 1/4 inch per foot. Building sewers 12 inches and larger, and private interceptor main sewers 8 inches and larger, follow the municipal criteria in NR 110.13.

Worked example. A commercial building drain carries 200 dfu. At 1/8 inch per foot a 4-inch drain is limited to 180, so it needs 5 inches; at 1/4 inch per foot a 4-inch drain (216) works. Pitch can save a pipe size.

Minimum sizes (SPS 382.30 (4) (b) and (c))

PipeMinimum
Gravity sanitary building sewer4 inches (a municipality may require more between the lot line and the public sewer)
Pressurized sewer, ejector or sewage pump2 inches and 2 ft/s velocity
Pressurized sewer, grinder pump1-1/4 inches and 2 ft/s velocity
Gravity private interceptor main sewer4 inches

Building drain elevation and backwater (SPS 382.30 (11) (b))

  • Building drains go below the lowest floor on which fixtures may be installed, if the sewer elevation permits.
  • Where an above-ground building drain discharges to a vertical pipe, it must connect to the building sewer at least 30 inches above the basement floor.
  • A building drain subject to backflow must be protected by a backwater valve or a sump with pumping equipment. The valve must have full-pipe capacity when open and be readily accessible for cleaning.
  • A floor that is entirely below grade and has a plumbing fixture or appliance must have a floor drain.

Depth and frost protection (SPS 382.30 (11) (c))

ConditionRequirement
Minimum depth to top of building sewer42 inches below finished grade
Sewer discharging to septic tank, holding tank or grease interceptor18 inches minimum
Top less than 60 inches below a surface cleared of snowFrost protection required
Top less than 42 inches below a surface not cleared of snowFrost protection required

Frost protection is not required: within 30 feet of the building drain where the sewer feeds a holding tank, POWTS tank or grease interceptor under an uncleared surface; where the predicted frost depth (Figure 382.30-1 and Table 382.30-6) doesn't reach the pipe; or for public facilities closed from November 15 to March 15 that are not places of employment.

The approved insulation methods are:

  1. Flat extruded polystyrene: at least 18 inches below grade and at least 6 inches above the pipe. Thickness and width come from Tables 382.30-5 and 382.30-7, and any height above 6 inches is added to the width.
  2. Box method: a 3-sided polystyrene box at least 12 inches below grade, 6 inches above and 6 inches to each side of the pipe.
  3. Lightweight insulating concrete: placed to the spring line, extending 6 inches each side, with the top at least 12 inches below grade.

Trenching, bedding and backfill (SPS 382.30 (11) (e))

  • Use open-trench work unless a local ordinance or inspector allows otherwise.
  • Where stone over 1 inch or bedrock is found, excavate 3 inches below grade and bed with material that passes a 3/4-inch sieve, compacted to 90 percent standard Proctor.
  • Initial backfill extends 12 inches over the pipe, uses material passing a 1-inch sieve, and is placed in lifts of 6 inches or less, well tamped.
  • Provide at least 36 inches of cover before wheel-loading the trench.
  • Unstable bottoms: drive sheathing 48 inches below the trench bottom, remove 24 inches of soft material and replace it, or pour a reinforced concrete cradle or slab at least 3 inches thick.

Connections and location rules

  • A building sewer may not pass under one building to serve another, except for farm buildings on one property or buildings on the same property with a piping document recorded with the register of deeds within 90 days.
  • If no public sewer connection exists within 3 feet of the designated point, use an approved saddle, a cut-in tee or wye, or for concrete or clay mains a connection encased in at least 3 inches of concrete.
  • A forced sewer connecting to a pressurized public sewer needs a curb stop, a check valve and an accessible quick disconnect upstream of the check valve.
  • Separation from wells follows NR 811 and NR 812.
  • Tracer wire for nonmetallic sewers: at least 18-gauge insulated single-conductor copper, within 6 inches above the pipe, green insulation, accessible at 400-foot intervals, and conductivity-tested. Warning tape is not a substitute. Recording GPS data with the municipality is an alternative.
  • Storm and clear water may not discharge to a sanitary building drain connected to a publicly owned treatment works, except as SPS 382.36 (3) allows.
Loading diagram...
Building sewer installation checks
Test Your Knowledge

A building drain will carry 200 dfu. Which choice satisfies Table 382.30-3?

A

4-inch drain at 1/8 inch per foot

B

3-inch drain at 1/2 inch per foot

C

4-inch drain at 1/4 inch per foot

D

4-inch drain at 1/16 inch per foot

Test Your Knowledge

Under SPS 382.30 (11) (c), what minimum depth below finished grade is required for the top of a building sewer that discharges to a public sewer?

A

18 inches

B

30 inches

C

36 inches

D

42 inches

Test Your Knowledge

A building sewer's top will be 50 inches below a driveway that is plowed all winter. What does SPS 382.30 (11) (c) 2. require?

A

Frost protection, because the sewer is less than 60 inches below a snow-cleared surface

B

No frost protection, because the sewer is deeper than 42 inches

C

Frost protection only if the sewer is plastic

D

A larger pipe size instead of insulation