9.1 POWTS Regulation, Sanitary Permits, Plan Review & Inspection
Key Takeaways
No POWTS may be installed, or have a holding, treatment or dispersal component added or replaced, unless the property owner holds a valid sanitary permit and plan approval (SPS 383.21).
A sanitary permit expires 2 years after issuance unless renewed, and may transfer to a new owner; the governmental unit decides an application within 30 days of receiving all information.
Plans go to the department for state-owned systems, mixed industrial waste and unrecognized technologies; to the governmental unit for up to two one- or 2-family dwellings using gravity in-ground designs and holding tanks under 3,000 gpd.
If the governmental unit does not inspect by the end of the next workday after the requested inspection day, the master plumber may proceed with backfilling.
SPS 383 is uniform: a local unit may not adopt POWTS design, installation, inspection or management ordinances that are more or less stringent, except where the rule allows.
What a POWTS is
Wis. Stat. s. 145.01 (12) defines a private onsite wastewater treatment system as a sewage treatment and disposal system serving a single structure with a septic tank and soil absorption field on the same parcel. The term also covers alternative systems the department approves: a substitute for the septic tank or soil absorption field, a holding tank, a system serving more than one structure, or one on a different parcel. Special purpose districts as well as property owners may own them.
A POWTS has three kinds of components:
| Component | Examples |
|---|---|
| Holding | Holding tank, RV transfer tank |
| Treatment | Septic (anaerobic) tank, aerobic treatment unit, sand or peat filter, disinfection unit |
| Dispersal (often also treatment) | In-ground trench or bed, mound, at-grade, drip |
Who works on POWTS
- Installation and modification are plumbing. SPS 305.90 (1) (b) lets restricted-service licensees install POWTS. A master plumber or master plumber-restricted service is responsible for each installation (SPS 305.91 (6) (d) and 305.92 (6) (d): no installation before a sanitary permit is issued).
- Soil evaluations are performed by a certified soil tester (SPS 385.10), covered in section 9.2.
- Inspections by a governmental unit are made by a certified POWTS inspector (SPS 305.66).
- Maintenance after installation is done by a registered POWTS maintainer, and pumping by a licensed septage servicing operator (section 9.5).
How the code applies (SPS 383.03)
| Situation | Rule |
|---|---|
| New POWTS | Must meet ch. SPS 383 |
| Modification (replacement, alteration or addition of components) | The modification must meet ch. SPS 383 |
| Building addition that pushes flow or load beyond the existing system's capability | The POWTS must be modified to comply |
| Existing POWTS installed or permitted before July 1, 2000 | Not retroactive; it follows the rules in effect when permitted, except the listed prohibitions and the maintenance rules |
| Pre-December 1, 1969 system with infiltrative surface 2 ft or more above groundwater or bedrock | Presumed to discharge final effluent that is not sewage |
The permit is reviewed under the rules in effect on the date of permit approval (s. 145.19 (3m) (b)).
Uniform statewide code (SPS 383.03 (5)). A governmental unit may not enact a POWTS ordinance that is more or less stringent than ch. SPS 383 unless a rule specifically allows it. Proposed POWTS ordinances must reach the department at least 30 days before the first public hearing. Permitted local options (SPS 383.32 (2)) include prohibiting or limiting holding tanks, constructed wetlands and evapotranspiration beds; stricter rules for systems existing before December 1, 1972; and requiring government ownership of systems serving 2 or more structures on more than one property. Department interpretations override lower jurisdictions.
Sanitary permits (SPS 383.21)
- Before installation, the property owner must hold a valid sanitary permit, and plan approval must be obtained.
- Modifications that add or replace a holding, treatment or dispersal component also need a permit and plan approval.
- The application goes to the governmental unit (usually the county), or to the department for state-owned property. It includes plans, the department's conditional approval when required, supporting information, local items and the fee.
- If the system uses a restricted technology (Table 383.04-1: pressure distribution with orifices under 1/8 inch, including drip; mechanical treatment such as aerobic units; disinfection units; and sand, gravel or peat filters other than mounds), the responsible master plumber must document approved training.
- If the management plan calls for evaluation, monitoring or maintenance at intervals of 12 months or less, the requirements must be recorded with the deed.
- The governmental unit must decide within 30 days after receiving everything. A denial must state the reasons and appeal rights; appeals of a department denial are due within 30 days.
- A permit expires 2 years after issuance unless renewed, and it transfers with ownership.
Plan review (SPS 383.22)
| Reviewer | Types of POWTS |
|---|---|
| Department only (Table 383.22-1) | State-owned POWTS or state facilities; systems not fully using approved or recognized technologies; domestic waste combined with industrial waste; experiments |
| Department or designated agent (Table 383.22-2) | Systems fully using approved or recognized methods; holding systems designed for more than 3,000 gpd |
| Governmental unit (Table 383.22-3) | Up to two one- or 2-family dwellings with accessory buildings using recognized methods and gravity distribution to an in-ground cell; holding systems under 3,000 gpd |
Inspection (SPS 383.26)
- No component may be covered or put into service until the governmental unit or department has had the opportunity to inspect.
- The responsible master plumber notifies the governmental unit and keeps records of each notice (date, time and person contacted). They also supply equipment and properly licensed personnel for the inspection.
- If the inspection isn't made by the end of the next workday (excluding weekends and holidays) after the requested inspection day, the plumber may proceed, including backfilling.
- Components must be tested per the manufacturer or the conditions of approval before being put into service.
- A local ordinance may require additional inspections.
Prohibitions to know (SPS 383.32)
- No cesspools, including ones existing before 2000.
- No final discharge of wastewater or effluent to open water or the ground surface.
- No wastes that cause NR 140 groundwater standards to be exceeded.
- Deleterious substances must be treated under SPS 382.34 first.
- No industrial wastes without DNR approval.
- No part of a POWTS in a floodway.
- RV transfer tanks are limited to ATCP 79 campgrounds or sites allowed by local ordinance.
How long is a Wisconsin POWTS sanitary permit valid unless renewed?
6 months
1 year
2 years
5 years
A master plumber requests a POWTS inspection for Tuesday. The county does not inspect by the end of Wednesday, the next workday. What may the plumber do under SPS 383.26 (2) (e)?
Proceed with the installation, including backfilling and covering
Wait 30 days for the inspector
Ask the owner to inspect it
Cover only the tank and leave the dispersal cell open indefinitely
Which local POWTS ordinance does SPS 383.32 (2) expressly allow a municipality to adopt?
A rule requiring 48 inches of separation to groundwater for all new systems
A ban on mound systems
A prohibition or limit on holding tanks
A rule shortening sanitary permits to 6 months