10.2 Schedule of Values, Progress Billing & Closeout Punch Lists

Key Takeaways

  • Allocate the contract sum across measurable work items. Separate prior and current earned amounts, approved stored materials, retainage and prior payments.

  • Five percent retainage on an otherwise approved $32,000 draw is $1,600 when that rate is allowed and authorized. The net current draw is $30,400.

  • Use submittals for technical review and requests for information to clarify a requirement. Follow the contract’s authorization and notice process if a response affects scope, price or time.

  • For owner-prime agreements covered by NRS 624.620, actual occupancy or use, or documented availability, starts the 30-day final-payment rule, subject to statutory exceptions and withholding.

  • A new single-family residence builder’s warranty under NRS 624.602 lasts at least one year from completion of the written punch list and must be transferable.

Last updated: November 2026

Schedule of Values and Progress Billing

A schedule of values (SOV) allocates a stipulated contract sum across work items the parties can measure and verify. Depending on the contract, items can follow specifications divisions, physical areas, trades or another useful breakdown. A reviewer checks that the values add to the contract sum and that early items are reasonably valued. Inflating mobilization or early earthwork to collect disproportionate cash before performing later work is called front-loading.

The American Institute of Architects’ G702 payment application summarizes the contract sum, changes, work completed and stored, retainage, prior certificates for payment and current request. The G703 continuation sheet provides the item detail. A contract may use different forms or reporting intervals. Confirm whether stored materials may be included and how approved changes are handled. Use the contract’s required support for each payment request.

Worked Example: Current Draw and Cumulative Amount

A Nevada commercial owner and prime contractor have a $320,000 covered agreement authorizing 5% retention. Assume no other withholding, stored materials or changes, and assume the prior certificate was fully paid.

SOV ItemScheduled ValuePrior EarnedCurrent EarnedCumulative Earned
Sitework and concrete$48,000$48,000$0$48,000
Framing$64,000$0$32,000$32,000
Mechanical, electrical and plumbing$96,000$0$0$0
Exterior and interior finishes$112,000$0$0$0
Total$320,000$48,000$32,000$80,000

Framing has reached 50% × $64,000 = $32,000. At the authorized 5%, current retention is $1,600 and the net current draw is $30,400. The cumulative check gives the same result: $80,000 earned less $4,000 cumulative retention equals $76,000 earned less retention. Subtract the $45,600 previously certified and paid, leaving $30,400.

NRS 624.609 caps retention on a covered owner-to-prime progress payment at 5% when retention is authorized by the agreement. The separate lower-tier rule is NRS 624.624. NRS 624.622(4) excludes public-body prime contracts and agreements with natural persons for qualified services on their single-family residences from NRS 624.609–.622. Identify the contracting parties and job type before applying these rules.

Submittals, Requests for Information, and Changes

DocumentPurposeAction
SubmittalShop drawings, samples or product data show how an item will meet the contract requirements.Coordinate and review before sending it to the contract’s designated reviewer. Obtain the required review before the applicable fabrication or installation.
Request for information (RFI)Asks for clarification, such as how to route a duct where two drawings conflict.Record the question and response, and follow the notice and authorization procedures if the response may change the work.
Change authorizationThe contract’s process for approved changes to scope, price or time.Obtain authorization from the party empowered by the contract. Use an agreed change order or another authorized mechanism where applicable.

In AIA A201-style administration, design-team review of a submittal is limited to the stated contract purpose. Contractor coordination and disclosure of departures still matter. A response to an RFI is not by itself a determination of price or time. If a response affects scope, preserve notice and follow the change procedure, including any contract provision for a directed change before final pricing.

Substantial Completion and Final Payment

Substantial completion generally means the work or an agreed portion can be used for its intended purpose under the contract. A substantial completion certificate can record the date, remaining items, completion deadlines and who is responsible for insurance, maintenance or utilities. The contract determines those responsibilities and how liquidated damages apply. A certificate of occupancy comes from the relevant building authority and serves a different function.

For an owner-prime agreement covered by NRS 624.620, the ordinary final-payment period is 30 days from actual occupancy or use by the owner or an authorized person, or from availability for intended use supported by the prime’s timely written notice or a certificate or temporary certificate of occupancy. For example, actual full use starts September 1, 2026. With no statutory withholding or other exception, the 30-day point is October 1, 2026. Partial occupancy or availability requires proportionate payment based on value; separate buildings are evaluated separately.

An authorized and timely written withholding notice must identify the amount and specific reasons permitted by statute. Authorized lien releases can be a condition of payment. Under NRS 108.2457, distinguish the conditional statutory release used with payment from an unconditional release for funds actually received. Check the applicable lower-tier payment terms and NRS 624.624 separately. The date of upstream payment may be one of two deadlines, and the earlier applicable deadline controls.

Closeout and the New-Home Warranty

The contract may require record drawings, operations and maintenance manuals, equipment training, inspection and occupancy records, warranty documents, statutory lien waivers or other evidence. A punch list records incomplete work, incorrect installation and items to correct. It may be prepared around the substantial completion review and completed after that milestone. Tie closing documents and final inspection to the agreed process without assuming that a punch-list date controls every payment deadline.

Under NRS 624.602, a licensee completing a new single-family residence must give the purchaser a separate single-page disclosure of rights, including access to the Residential Recovery Fund process, and a written builder’s warranty. The warranty lasts at least one year after completion of the written punch list. It must be transferable to a later purchaser, preserve other available warranties, and cover the specified workmanship, materials, systems and components unless separately warranted by the manufacturer or installer.

Loading diagram...
Project Administration and Closeout Milestones
Test Your Knowledge

A commercial owner-prime agreement covered by NRS 624.609 has a $400,000 contract sum. The approved mechanical, electrical and plumbing line is $100,000 and advances from 20% to 60% complete in the current period. The agreement authorizes 5% retention. What is payable for this line on this draw if prior billing was paid and no other withholding or stored materials apply?

A

$40,000

B

$36,000

C

$57,000

D

$38,000

Test Your Knowledge
Ordering

A commercial contract uses the stated closeout sequence: the contractor completes correction items after substantial completion, then requests final payment with the completed records. No separate payment due date is being calculated. Put these actions in order.

Arrange the items in the correct order

1

Resolve a design conflict and obtain the required shop-drawing review before fabricating the affected work

2

Complete the corrective work left on the punch list

3

Submit the final application with the required completed closeout records

4

Document substantial completion when the contracted work can be used for its intended purpose

Test Your Knowledge
Matching

Match each project management document or milestone to its primary contractual or Nevada statutory role.

Match each item on the left with the correct item on the right

1

Schedule of Values (SOV)

2

Request for Information (RFI)

3

Submittal (Shop Drawing)

4

NRS 624.602 Written Punch List