4.3 Bid Types, Additive/Deductive Alternates, Allowances & Contingencies

Key Takeaways

  • Lump-sum contracts fix the price for a defined scope and place cost-overrun risk on the contractor, whereas unit-price contracts base final payment on actual measured quantities multiplied by bid unit rates.

  • A cost-plus agreement pays allowable costs plus the stated fee. A Guaranteed Maximum Price can cap the price for the agreed scope, subject to the contract terms.

  • Additive alternates price optional scope additions above the base bid, while deductive alternates price optional credits subtracted from the base bid to meet owner budgets.

  • A specified allowance carries an estimated cost for a defined item. Reconcile actual costs using the contract’s allowance and change-order terms.

  • Unused internal contingency leaves a fixed price unchanged if the agreement has no clause returning or sharing the savings.

Last updated: November 2026

Comparing Construction Bid and Contract Types

Different project owners and scope conditions require different pricing structures. On the Nevada CMS exam, you must recognize how each contract pricing model allocates financial risk, documentation burden, and profit opportunity.

Bid / Contract TypeHow Price Is DeterminedBest Project FitPrimary Risk Allocation
Lump-Sum (Fixed-Price)Single fixed total price for a complete, defined scope of workComplete drawings and detailed specs (standard commercial and residential builds)Contractor bears cost-overrun risk and keeps efficiency savings
Unit-PriceFixed bid price per unit (SY, CY, LF) multiplied by actual field-measured quantitiesHeavy civil, excavation, utility trenching, and paving where exact quantities are uncertainShared: contractor owns unit-rate productivity; owner owns quantity variance
Cost-Plus Fixed FeeOwner pays actual allowable job costs plus a predetermined dollar feeFast-track builds or complex renovations where scope is still evolvingOwner bears the risk of covered costs within the agreement. The fee stays fixed for the agreed scope.
Cost-Plus Percentage FeeOwner pays actual allowable job costs plus an agreed % of those costsA private contract where this method is permittedOwner bears high risk because higher allowable costs increase the contractor's fee
Cost-Plus with GMPCost-plus structure capped by a Guaranteed Maximum Price ceilingLarge commercial projects using Construction Manager at Risk (CMAR) deliveryContractor bears costs above the cap for unchanged scope, subject to the contract. Savings may be shared.
Time & Materials (T&M)Agreed hourly labor rates (including burden/markup) plus materials under the agreed cost and markup termsEmergency repairs, small troubleshooting tasks, or extra change-order workOwner bears duration/quantity risk unless protected by a Not-to-Exceed (NTE) cap

Unit-Price Watchout: Unbalanced Bidding

In a unit-price bid, owners estimate approximate quantities on the bid schedule so bidders can compete on an equal basis. For example, if a municipal bid schedule estimates 500 cubic yards of rock trench excavation and a contractor bids $42.00/cu yd, the bid-day line item equals $21,000. If field survey cross-sections later confirm 580 cubic yards were actually excavated within trench pay-lines, final payment adjusts to 580×$42.00=$24,360580 \times \text{\textdollar}42.00 = \text{\textdollar}24,360. Some contractors attempt unbalanced bidding—artificially inflating unit prices on early items (such as mobilization or clearing) to generate early cash flow, or inflating items they believe the owner underestimated while lowering items they think were overestimated. Nevada Department of Transportation (NDOT) highway solicitations are one setting in which the agency checks for unbalanced pricing. NDOT’s construction manual distinguishes inflated or understated line prices from a material imbalance that calls the actual cost ranking into question. Use the project’s bid instructions to determine how the bid will be evaluated.

Additive vs. Deductive Alternates

Owners facing budget uncertainty often ask bidders to submit a base bid along with separate alternates so the owner can tailor the final award after prices are opened. Read the award method in the solicitation. For example, the Nevada State Public Works Division’s published bidder instructions provide for selection in the order alternates appear on its bid proposal form when the approved budget permits. The contract should identify which options were accepted.

  • Additive Alternate — An optional scope upgrade or extra feature priced separately to be added to the base bid if funding allows (for example, Alternate #1: add a shaded steel patio structure for +$28,500).
  • Deductive Alternate — An optional scope reduction or lower-cost material substitution priced as a credit to be subtracted from the base bid if the base bid exceeds the owner's budget (for example, Deductive Alternate #2: substitute asphalt shingles for standing-seam metal roofing for -$19,200).

Tip

Price the scope that changes and the costs that stay. For a $240,000 base, accepting only the $28,500 additive alternate raises the bid to $268,500. Accepting only a $19,200 deductive alternate lowers the same base to $220,800. Keep supervision or mobilization costs that the remaining scope still requires.

Allowances vs. Contractor Contingencies

An allowance prices a defined item with an unresolved cost. A contingency budgets for uncertainty. Read the contract to see whether and how either affects the agreed price.

Specified Allowances

A specified allowance is an amount carried in the contract price for an item whose exact design, finish, or brand has not been chosen at bid time (such as custom light fixtures, cabinetry hardware, or lobby stone tile).

  • How it works: A solicitation may direct every bidder to carry the same allowance so bids can be compared on a consistent basis.
  • How to reconcile it: If the contract adjusts the price dollar for dollar for actual covered cost, add the overage or subtract the underrun. If the owner selects tile costing $14,500 against a $12,000 material allowance, the contract price increases by $2,500 before any contract-specified adjustment for overhead or profit via formal change order. Conversely, if the owner selects $9,800 in tile, the contract price is credited (reduced) by $2,200.
  • Check what the allowance covers: Verify whether the specification defines the allowance as material delivery only (installation labor stays in the base bid) or furnish-and-install.

Contractor-Owned Contingencies

An internal contingency is an amount the contractor includes in a fixed price to cover risks such as quantity uncertainty or minor cost increases. If the fixed-price agreement contains no reconciliation or savings clause, using less of the internal estimate leaves the price unchanged. Under an open-book agreement with a Guaranteed Maximum Price (GMP), the contract determines who may use the contingency and how any savings are divided. Nevada Revised Statutes (NRS) 338.1696 and 338.1697 provide an example on covered public works: a contract with a construction manager at risk can use a GMP and can allocate some or all savings below the cap to the construction manager.

Worked Example: Reconciling an Allowance on a Lump-Sum Job

A homeowner signs a $240,000 lump-sum remodel contract that includes a $10,000 material-only appliance allowance and a $6,000 internal contractor contingency. The contract says the price adjusts dollar for dollar for actual appliance costs and contains no contingency refund or shared-savings clause. At project finish, the homeowner selects appliances costing $12,800, while the contractor avoids all unforeseen framing problems and spends none of the $6,000 contingency.

  • Appliance allowance adjustment: $12,800−$10,000=+$2,800\text{\textdollar}12,800 - \text{\textdollar}10,000 = +\text{\textdollar}2,800 upward change order.
  • Internal contingency adjustment: $0 refund (the price is unchanged under these terms).
  • Final adjusted contract price: $240,000+$2,800=$242,800\text{\textdollar}240,000 + \text{\textdollar}2,800 = \text{\textdollar}242,800.

Federal contract pricing models, FAR Part 16 · Nevada State Public Works Division bidder instructions · NDOT contract administration manual · Nevada public works contracting, NRS 338

Test Your Knowledge

A contractor signs a $315,000 lump-sum contract that includes an $18,000 owner-specified flooring material allowance and an internal $7,500 contractor contingency. The owner selects flooring materials costing $15,400, and the contractor finishes the project without using any of the $7,500 contingency. The contract adjusts actual flooring material costs dollar for dollar and has no contingency refund or shared-savings clause. Under these terms, what is the final adjusted contract price?

A

$304,900

B

$307,500

C

$312,400

D

$315,000

Test Your Knowledge

Under which pricing model is the contractor’s uncapped fee calculated as a percentage that raises the dollar fee as allowable costs rise?

A

Lump-sum fixed-price contract

B

Cost-plus percentage-of-cost contract

C

Cost-plus with Guaranteed Maximum Price (GMP)

D

Unit-price contract with fixed quantities

Test Your Knowledge
Ordering

An agreement requires a dollar-for-dollar change order for the difference between a material-only allowance and the actual approved material cost. Put the reconciliation steps in order.

Arrange the items in the correct order

1

Verify the approved invoice for the covered materials

2

Subtract the included allowance from the approved covered cost

3

Identify the included material allowance and confirm the items it covers

4

Issue the written change order showing the resulting credit or charge

Sections you finish are checked off in the contents.