6.3 Cash Flow Timing, Retainage & NSCB Financial Statement Tiers (NAC 624.593)
Key Takeaways
A job can earn a profit and still need cash before a draw arrives. Forecast the dates of payroll, deposits, supplier bills, progress receipts, and release of retention.
For private progress payments governed by NRS 624.609 or NRS 624.624, contractually authorized retention may not exceed 5% of the payment. Check statutory scope and separate grounds for withholding.
Under NAC 624.593, NSCB financial statement requirements escalate across four tiers: $25,000 or less; more than $25,000 to less than $500,000; $500,000 to less than $1,000,000; and $1,000,000 or more (where compilations are not accepted)
Under NAC 624.675, an applicant whose own financial statement cannot support a requested monetary limit may submit a personal or corporate indemnification agreement with qualifying financials
Cash Flow Timing, Retainage & NSCB Financial Statement Tiers (NAC 624.593)
Cash flow measures what actually comes in and goes out. Estimate the timing of both so a profitable job has enough cash to reach the next progress payment. On a new job, mobilization, material deposits and weekly payroll can fall due before the first draw arrives. A change-order dispute can push back part of an expected payment, and retainage can defer another part.
Suppose the company has $50,000 in cash earmarked for a job and must pay $70,000 for materials and payroll before the first approved draw is paid. It needs another $20,000 to bridge the gap even if the invoiced work is expected to earn a profit. Keep an estimate of remaining job cash needs and a calendar of when collections and bills are due. The Board’s financial statement requirements and contractual collection deadlines answer different questions.
Retainage in a Cash Flow Forecast
In construction accounting, retainage (retention) is an amount held back from payment under the applicable agreement or law. Here is the cash calculation when retainage is the only deduction:
Check the Governing Rule Before Applying the Percentage
For covered Nevada private agreements, NRS 624.609(2)(a)(1) and NRS 624.624(2)(a)(1) cap contractually authorized retention at 5% of the stated payment amount. NRS 624.609 covers payments from owner to prime, and NRS 624.624 covers higher-tier to lower-tier payments. Under NRS 624.622(4), NRS 624.609–.622 exclude agreements between a prime and a natural person who owns a single-family residence for qualified services on the residence, and agreements between a public body and a prime for public work.
On a covered private commercial job with $200,000 due before retention, 5% is $10,000. If no other amounts are properly withheld, the current payment is $190,000. The $10,000 is a deferred collection, not automatically a reduction in earned contract revenue. The statute separately authorizes other kinds of withholding with conditions and notice. For public-body payments under NRS 338.515, generally start with 5% withheld until half the work is performed. Then consult the satisfactory-progress and withholding provisions before forecasting release or reduced retention.
NSCB Financial Statement Tiers (NAC 624.593)
Under NRS 624.220, the monetary limit governs one or more construction contracts at one construction or subdivision site for one client. The requested limit determines the statement required. NAC 624.593 dictates the exact level of financial statement assurance and recency required for each requested monetary limit:
| Requested Monetary Limit | Minimum Financial Statement Requirement (NAC 624.593) | Maximum Age at Filing |
|---|---|---|
| $25,000 or less | Independent certified public accountant (CPA) statement; OR NSCB-prescribed form with affidavit; OR GAAP accounting-software printout with affidavit | Current. Board instructions specify six months for self-prepared or compiled statements. |
| More than $25,000 to less than $500,000 | Independent CPA compiled statement; OR Independent CPA reviewed or audited statement | 6 months (compiled) / 1 year (reviewed or audited) |
| $500,000 to less than $1,000,000 | Independent CPA compiled statement with full disclosures; OR Independent CPA reviewed or audited statement | 6 months (compiled w/ full disclosures) / 1 year (reviewed or audited) |
| $1,000,000 or more (including Unlimited) | Independent CPA reviewed or audited statement (compiled statements are NOT accepted) | 1 year (reviewed or audited) |
Apply the Cutoffs and File the Supporting Records
- The 6-Month vs. 1-Year Split: CPA compiled statements (whether standard or with full disclosures) must be dated within 6 months of filing, whereas CPA reviewed or audited statements are valid for 1 year.
- Full Disclosures at $500,000: A compilation of the kind in subsection 2 applies above $25,000 and below $500,000. At $500,000 or more and below $1,000,000, a compilation under subsection 3 needs full disclosures.
- No Compilations at $1,000,000+: Once a requested monetary limit reaches $1,000,000 or more, compiled financial statements are prohibited—an independent CPA review or audit is mandatory.
For an application, the Board also requires a bank verification form. Its instructions call for a classified balance sheet for business statements and a working-capital and net-worth schedule for a personal statement prepared by a CPA.
NSCB Indemnification Option (NAC 624.675)
What if a newly formed Nevada LLC or growing contractor does not yet have sufficient working capital or net worth on its own Balance Sheet to qualify for its desired monetary limit? Under NAC 624.675, the Board may consider a written indemnification agreement from a financially qualified indemnitor—such as a corporate parent, an officer/director, or a third party—to bridge the financial gap.
- Applicant Must Still File: Indemnification does not waive NAC 624.593; the applicant must still submit its own required financial statement tier alongside the indemnitor's qualifying financial statements.
- Personal vs. Corporate Indemnitors: Individual indemnitors (officers, directors, or other natural persons) sign the Board's indemnification form—along with their spouse, if applicable. A corporate indemnitor must submit a formal resolution of its board of directors, its qualifying financial statement, and the Board’s indemnification form signed by an authorized officer. The Board’s application guidance also calls for the indemnitor’s bank verification form.
- Withdrawal Restrictions: If an indemnification agreement was required as a precondition for a single-project limit increase under NAC 624.670, the indemnitor cannot withdraw it. For a withdrawal that is permitted, send written notice to the Board. Withdrawal takes effect 90 days after the Board receives it.
Nevada owner and subcontractor progress payments, NRS 624.609 and 624.624 · Nevada public works, NRS 338.515 · Nevada financial statements and indemnification, NAC 624.593 and 624.675 · NSCB application and financial instructions
A Las Vegas general contractor is applying for a $750,000 monetary limit on its Nevada license. Under NAC 624.593, which financial statement satisfies the Board's minimum requirement?
A self-prepared QuickBooks balance sheet accompanied by a notarized affidavit
An independent CPA compiled statement omitting disclosures, dated 4 months ago
An independent CPA compiled statement with full disclosures, dated 4 months ago (or a CPA review/audit within 1 year)
An independent CPA compiled statement with full disclosures, dated 11 months ago
Match each Nevada financial rule or NAC 624.593 tier to its exact requirement.
Match each item on the left with the correct item on the right
Monetary limit of $25,000 or less
Monetary limit of $1,000,000 or more
Contractually authorized retention under NRS 624.609 or 624.624
NAC 624.675 indemnification withdrawal (when allowed)
On a private Nevada commercial remodel governed by NRS 624.609, an owner and prime contractor agree to withhold the maximum legally permitted retainage. If the contractor submits an approved progress billing of $200,000 that is otherwise payable with no other amounts withheld, what is the maximum retainage the owner may withhold and the minimum net progress payment due?
$20,000 retainage withheld; $180,000 net payable
$10,000 retainage withheld; $190,000 net payable
$5,000 retainage withheld; $195,000 net payable
$40,000 retainage withheld; $160,000 net payable
Sections you finish are checked off in the contents.