13.3 EPA Lead RRP (Pre-1978), Asbestos NESHAP & Stormwater (NPDES)
Key Takeaways
EPA Lead RRP applies to covered paid renovations of pre-1978 target housing and child-occupied facilities. The minor repair exception has painted-area limits of 6 square feet per interior room or 20 square feet exterior and excludes window replacement and demolition of painted surfaces.
Asbestos NESHAP requires a thorough inspection of the affected area before demolition or renovation of a covered facility, regardless of its age.
For routine covered renovations, the federal asbestos notice thresholds are 260 linear feet on pipes, 160 square feet on other components, or 35 cubic feet where length or area could not be measured. Covered facility demolition normally requires notice even with no asbestos.
The air authority normally requires asbestos notice 10 working days in advance. Nevada OSHA has separate licensing, work-practice, and 10-calendar-day project notice requirements under NAC 618.
Under Nevada’s construction stormwater general permit, a project that can discharge to waters of the United States generally needs coverage at 1 acre of disturbance, including a smaller site in a qualifying common plan. Prepare the SWPPP and obtain authorization before disturbing soil.
EPA Lead RRP, Asbestos NESHAP, and Stormwater NPDES Compliance
Before mobilization, identify the affected building materials and painted surfaces, the total land disturbance under the common plan, and the agency with jurisdiction. A single project may need to satisfy more than one program.
EPA Lead Renovation, Repair, and Painting (RRP) Rule (40 CFR Part 745)
The EPA RRP Rule governs covered renovation, repair, and painting work performed for compensation that disturbs painted surfaces in:
- Target housing: Residential dwellings built before 1978 (for example, remodeling a 1968 single-family home or apartment), subject to the statutory exclusions for certain elderly or disability housing and zero-bedroom dwellings. Check the exception to those exclusions if a child under 6 resides or is expected to reside there.
- Child-occupied facilities: Pre-1978 buildings or portions such as daycares, including in public or commercial buildings. The same child under 6 must visit at least two different days in a week, for at least 3 hours each visit, 6 hours per week, and 60 hours per year.
Minor Repair Exemption vs. Mandatory RRP Compliance
Minor repair can qualify at 6 square feet or less per interior room or 20 square feet or less exterior. Count nonemergency jobs in the same room within 30 days together. The exception excludes work involving window replacement, demolition of painted surface areas, or prohibited or restricted practices under 40 CFR 745.85(a)(3).
Caution
Window replacement: In a 1968 home, replacing a painted window is outside the minor-repair exception even if only 3 square feet of trim are disturbed. Check for a documented lead-free determination of affected components under 40 CFR 745.82 before deciding whether the renovation rule applies.
Core RRP Contractor Duties
- Firm & Renovator Certification: The contracting business must be an EPA-certified RRP firm, and a Certified Renovator must be assigned to the project to oversee setup, containment, worker training, and cleaning verification.
- Pre-Renovation Education: For a housing unit, give the owner and, when different, an adult occupant the EPA Renovate Right pamphlet no more than 60 days before work. Follow the applicable acknowledgment, mailing, or delivery documentation requirements. Common areas and child-occupied facilities have additional notification procedures under 40 CFR 745.84.
- Lead-Safe Containment & Cleanup: Contain dust and debris, protect openings and ducts as required, and use the rule’s interior HEPA vacuuming and damp-cleaning procedures. The certified renovator verifies cleaning after the required visual inspection.
- Prohibited Practices: Prohibited methods include open-flame burning or torching and operating a heat gun at 1,100°F or above. High-speed power sanding or grinding requires compliant shrouding or containment and a HEPA vacuum attachment.
- Recordkeeping: Retain RRP compliance records (test-kit results, Renovate Right receipts, training records, and cleaning verification) for at least 3 years after completion. For worker exposure to lead in construction, separately check 29 CFR 1926.62.
Asbestos NESHAP (40 CFR Part 61 Subpart M) & Nevada Licensing
Asbestos NESHAP applies to covered commercial, institutional, industrial, public, and residential facilities. An isolated residential building with up to four dwelling units is generally excluded, but structures in a larger covered installation or redevelopment can fall within the rule.
Inspection, Notice and Licensing
- Inspect first: Before demolition or renovation of a covered facility, the owner or operator must arrange a thorough asbestos inspection of the affected area, including relevant friable and nonfriable materials. Use an appropriately accredited inspector. Age alone cannot rule out asbestos.
- Check the amount and work type: For routine renovation, the federal thresholds for regulated asbestos-containing material (RACM) are 260 linear feet on pipes, 160 square feet on other components, or 35 cubic feet off components when length or area could not previously be measured. RACM includes friable material and certain nonfriable material that is or will be disturbed in ways specified in 40 CFR 61.141. Normal demolition of a covered facility also requires notice when the inspection finds no asbestos. Federal demolition means taking out a load-supporting structural member or intentionally burning the facility.
- Notify the air authority: For ordinary covered demolition and renovations at or above the applicable RACM threshold, submit notice at least 10 working days ahead under 40 CFR 61.145. Orders for an imminent collapse and emergency renovations have special rules. Confirm the recipient for the site, such as the Clark County Division of Air Quality in Clark County or Northern Nevada Public Health in Washoe County.
- Check Nevada OSHA and contractor credentials separately: Under NAC 618, an ordinary asbestos abatement project above the state spot-repair limits requires a properly licensed abatement contractor and notice to the Nevada OSHA Enforcement Section at least 10 calendar days before on-site work. NAC 624.585 limits a contractor without the A-23 asbestos removal classification to at most 25 linear feet or 10 square feet, subject to exposure limits and all other requirements. Spot repairs still must follow 29 CFR 1926.1101.
Stormwater Permitting: Clean Water Act NPDES & NDEP CGP
Stormwater runoff from graded construction sites carries sediment, concrete washout, fuel, and debris into storm drains and waterways. Under the federal Clean Water Act National Pollutant Discharge Elimination System (NPDES), the Nevada Division of Environmental Protection (NDEP) issues coverage under NVR100000 in its jurisdiction. EPA Region 9 is the permitting authority in Nevada Indian country.
The 1-Acre and Common-Plan Thresholds
When construction stormwater can discharge to waters of the United States, coverage generally applies to sites with:
- 1 acre or more of total land disturbance, OR
- Less than 1 acre of disturbance if the site is part of a larger common plan of development or sale that will cumulatively disturb 1 acre or more (for example, building on a 0.4-acre pad inside a commercial development that will disturb 5 acres). The permitting authority can also designate a smaller site based on its potential effect on receiving waters.
Required Steps Before Soil Disturbance
- Develop a SWPPP: Prepare a site-specific Stormwater Pollution Prevention Plan (SWPPP) identifying pollutant sources, drainage patterns, inspection schedules, and Best Management Practices (BMPs)—such as silt fences, wattles/fiber rolls, storm drain inlet protection, stabilized construction entrances (crushed rock pads to prevent mud tracking onto streets), and concrete washout pits.
- File an NOI & Receive Authorization: Submit a Notice of Intent (NOI) electronically through NDEP, mail the signed certification and fee, and wait for NDEP's written approval/authorization before clearing or grading begins.
- Inspect, Maintain, and Terminate: Keep the SWPPP on site, conduct routine and post-storm BMP inspections, repair damaged silt fencing promptly, and file a Notice of Termination (NOT) once the permit’s termination conditions are met, such as final stabilization for a completed site.
Summary Comparison of the Three Environmental Regimes
| Environmental Program | Core Trigger | Key Pre-Work Requirement | Mandatory Credential / Filing |
|---|---|---|---|
| EPA Lead RRP (40 CFR 745) | Paid work disturbing paint in covered pre-1978 housing or a child-occupied facility | Check covered work and exclusions, provide required education and plan lead-safe work | Certified firm and renovator, 3-year records |
| Asbestos NESHAP (40 CFR 61 Subpart M) | Demolition or renovation of a covered facility | Thorough inspection of affected area | Air authority notice for ordinary covered demolition or qualifying renovation, separate Nevada asbestos requirements |
| Stormwater NPDES (NDEP CGP) | Qualifying discharge with at least 1 acre of disturbance or qualifying common plan | Prepare SWPPP and select site controls | File NOI and receive NDEP approval before grading |
A contractor is paid to replace four painted wood windows in a 1968 Reno single-family home. Each window replacement disturbs 4 square feet of painted trim. There is no lead-free determination for the affected components. What does EPA Lead RRP require?
No RRP compliance is required because each window disturbs less than 6 square feet of interior paint
Only the homeowner needs to sign a waiver because the home is a single-family residence
Full compliance only applies to the exterior side of the windows if the disturbed area exceeds 20 square feet
Full EPA RRP compliance is required—including an EPA-certified firm, Certified Renovator, lead-safe containment, and the Renovate Right pamphlet—because window replacement is never exempt as a minor repair
A contractor plans to take out load-bearing walls in a 1972 commercial building with suspect ceiling fireproofing. Which asbestos step must precede the work and inform the notice and abatement decisions?
Arrange a thorough inspection of the affected area by an appropriately accredited asbestos inspector.
Wet down the ceiling fireproofing with a garden hose and haul it to a construction landfill
Have the general contractor's crew remove a small section with respirators to check if dust forms
Submit an NPDES Notice of Intent (NOI) to NDEP at least 10 working days before interior work
In NDEP jurisdiction, an operator plans to grade a 0.6-acre pad in a retail development that will disturb 5 acres in total. Construction stormwater can reach waters of the United States. Which actions apply under NDEP’s Construction General Permit? (Select all that apply.)
Select all that apply
Obtain NDEP CGP coverage because the pad is part of a common plan of development disturbing 1 acre or more
Develop a site-specific Stormwater Pollution Prevention Plan (SWPPP) with BMPs such as silt fences and inlet protection
File a Notice of Intent (NOI) and wait for NDEP authorization before disturbing soil
Skip permitting because the individual pad is under 1 acre
Install and maintain the stabilized entrance and washout controls specified in the project SWPPP.