4.4 Bid Bonds, Bid Shopping Ethics & Monetary Limit Bid Compliance

Key Takeaways

  • Bid security addresses a bidder’s failure to follow through. For covered Nevada public works above the statutory threshold, performance and payment bonds are furnished before award and become binding on award.

  • A $680,000 bid requiring 5% security has a $34,000 penal sum. The bond form determines what costs are covered and how the cap applies.

  • Bid shopping is a prime contractor’s use of competing quotes to press prices down. NRS 338.141 separately governs first-tier subcontractor listing and substitution in covered bids.

  • An over-limit bid or contract is void under NAC 624.640(1). The license number and any monetary limit belong on every Nevada construction bid and contract.

  • Request a single-project limit increase at least five working days before the intended bid and receive Board approval before bidding.

Last updated: November 2026

Bid Bonds and Surety Guarantees

Bid security protects an owner if a bidder fails to follow through on commitments made in the bid. A bid bond involves a bidder, an owner or public body, and a surety. Check the invitation for the required form, amount, and bid period.

Separate bid security from the bonds required for award

A bid bond can respond when an awarded bidder fails to execute the contract or furnish the required performance and payment bonds. The bid bond form governs the surety’s obligation. Under Nevada Revised Statutes (NRS) 339.025(1), the contractor furnishes a performance bond and a payment bond before award of a covered public-works contract exceeding $100,000, except a contract subject to NRS Chapter 408. The contracting body sets each bond at no less than 50% of the contract amount. The bonds become binding upon award.

Worked Example: Calculating Bid Bond Penal Sum

Suppose a Nevada general contractor submits a $680,000 public bid requiring a 5% bid bond:

Bid Bond Penal Sum=$680,000×0.05=$34,000\text{Bid Bond Penal Sum} = \text{\textdollar}680,000 \times 0.05 = \text{\textdollar}34,000

The penal sum is the stated limit on the bond. Suppose the bid form states that if the bidder refuses to sign and the public body must contract with another party, the bidder and surety cover the increased cost up to the bond limit. If the replacement agreement costs $24,000 more, that difference is within the $34,000 limit. If the difference is $40,000, the bond recovery for that difference cannot exceed $34,000. Read the bond for the treatment of other covered costs.

Bond TypeTimingWho Is ProtectedWhat It Guarantees
Bid BondSubmitted with the bidProject OwnerBidder will sign the contract and supply performance/payment bonds if awarded
Performance BondFurnished before award under NRS 339.025(1)Project OwnerContractor will complete the work per plans, specs, and contract terms
Payment BondFurnished before award under NRS 339.025(1)Subcontractors & SuppliersProvides security to eligible claimants that supply labor or materials to the contractor or its subcontractors

Bid Shopping vs. Bid Peddling

Bid shopping occurs when a prime contractor uses a subcontractor’s quote to pressure another subcontractor into lowering its price. In bid peddling, a subcontractor offers a lower price to displace another subcontractor’s bid after prices are known. Industry organizations oppose both practices. Nevada’s statutory question is whether the bid lists required subcontractors and whether a substitution complies with the law.

On a covered public bid under NRS 338.141, follow the applicable listing route. If the public body identifies portions estimated to exceed 3% of its estimated cost, name the first-tier subcontractor for each listed portion you will subcontract. If the public body does not provide that list, name each first-tier subcontractor whose payment exceeds 5% of the prime’s total bid. Under that latter route, the three lowest bidders also have supplemental listing duties within two hours after bid opening is completed. Check the statute and solicitation for those details and the prime’s self-performed work.

A replacement for a named subcontractor must satisfy subsection 5. For example, the public body may request a change in writing and pay its increased cost, or the public body can approve a substitution under the rule. A cheaper offer alone is no authority to make a switch. An unauthorized substitution for a named subcontractor can cost the prime 1% of the total contract amount under subsection 6.

Nevada Monetary Limit Bid Compliance (NRS 624 & NAC 624)

Under NRS 624.220, the Board sets the license monetary limit using the applicable financial and qualification factors. That limit is the maximum dollar amount—combining labor, materials, overhead, and profit—that the contractor may bid or contract for on one construction site or subdivision site for a single client.

Mandatory Rules Tested on the Nevada CMS Exam

  1. Bidding Over Your Limit Renders the Bid Void (NAC 624.640(1)) — If a contractor with a $250,000 monetary limit submits a $310,000 bid for a single project, the bid and any resulting contract are legally void under NAC 624.640(1).
  2. Disciplinary Action (NRS 624.3015) — Under NRS 624.3015(2), bidding to contract or contracting for a sum exceeding the license's monetary limit is cause for Nevada State Contractors Board (NSCB) discipline. Under NRS 624.3015(3), a prime contractor can also be disciplined for knowingly contracting with a subcontractor whose subcontract exceeds that subcontractor's monetary limit or license classification!
  3. No Contract Splitting — A contractor cannot legally evade a $250,000 limit by breaking a $310,000 remodel into two $155,000 contracts on the same site for the same client.
  4. Mandatory License & Limit Disclosure (NAC 624.640(5)) — Every licensee must include the license number and any monetary limit on all bids submitted and all contracts entered into for construction work in Nevada.
  5. Single-Project Limit Increase Option (NRS 624.220(3) & NAC 624.670) — If a contractor with a $250,000 limit wants to bid a $310,000 job without permanently upgrading the license, the contractor may apply in writing to the NSCB for a single-project monetary limit increase.
    • Advance deadline: Under NRS 624.220(3), the written application must be filed at least 5 working days before the date of submitting the bid, and Board approval must be obtained prior to bidding (retroactive approvals after bid submission are not allowed).
    • Supporting proof: Under NAC 624.670, the licensee must provide financial statements meeting NAC 624.593 standards and agree to procure any required performance/payment bonds.
    • Annual cap: A licensee may submit no more than five (5) single-project increase applications in any 12-month period.

Bid Mistakes and Subcontractor License Verification

Distinguish a clerical error, such as transposed digits, from an estimating judgment that proves wrong. For example, under the Nevada State Public Works Division’s published Instructions to Bidders, section 8.2 considers withdrawal after opening begins only for a bona fide clerical error. The owner must receive written notice within 24 hours after opening, the notice must explain the error, and the owner determines whether withdrawal is justified. When studying a bid error, first identify the solicitation and its deadline. Keep the bid worksheets and quotes that show how the price was assembled.

Verify each prospective subcontractor’s active license, scope and monetary limit before considering its bid. NAC 624.640(6) requires the bidder’s licensing to be checked, and NRS 624.3015(3) addresses knowingly contracting with a contractor beyond that contractor’s limit or scope.

Nevada public works bond requirements · Nevada public works subcontractor listings and substitutions · Nevada contractor statutes · Nevada contractor regulations · State Public Works Division bidder instructions · AGC and partner organizations’ statement on bid shopping

Test Your Knowledge

A Nevada B-2 residential and small commercial contractor holds a $250,000 monetary limit and wants to submit a $310,000 bid on a single-story tenant improvement within its B-2 scope. What does the single-project increase procedure require before it bids?

A

Split the $310,000 project into two separate $155,000 contracts on the same site for the client

B

Submit the $310,000 bid now and request a retroactive limit increase within 5 days after award

C

Have the project owner sign a written addendum waiving the NSCB license monetary limit

D

Obtain NSCB approval for a single-project limit increase requested at least 5 working days before bidding

Test Your Knowledge

A prime has named a subcontractor in a Nevada public bid governed by NRS 338.141. After opening, a different subcontractor offers a lower price. What should the prime check before making a change?

A

Whether the substitution satisfies NRS 338.141(5), including any required public-body approval

B

Whether the price difference is at least 1% of the original subcontract

C

Whether the replacement bid came from the same town as the named subcontractor

D

Whether the supplier agrees to let the lower price replace the named subcontractor without notifying the public body

Test Your Knowledge
Fill in the Blank

A bid schedule sets security at 5% of the total bid, including the alternates listed in the schedule. The base is $710,000 and the security calculation includes a $50,000 additive alternate. What is the required penal sum? Enter the amount in dollars.

Type your answer below