3.2 NSCB Disciplinary Authority, Residential Disclosures & Warranties
Key Takeaways
NRS 624.300 generally authorizes an administrative fine of up to $10,000 and provides different fine rules for specified violations. The Board can order corrective work, restrict a license, or suspend or revoke it.
Under NRS 624.750(4)–(5), willfully failing to use earmarked money for its purpose and wrongfully diverting it is generally a gross misdemeanor at $1,000 or less and a Category E felony above $1,000.
NRS 624.600 requires a general building contractor to identify its subcontractors and suppliers furnishing at least $500 in materials to the covered project, and provide a lien warning and Board-prescribed informational form.
NRS 624.602 requires a new single-family home’s purchaser to receive a separate one-page rights disclosure and a written, transferable warranty valid at least one year from completion of a written punch list.
Board Discipline, Residential Disclosures and Builder’s Warranties
A job can generate more than one legal issue. The Nevada State Contractors Board (NSCB) can investigate and discipline a licensee, a criminal court can consider a fund-diversion offense, and the owner may have separate rights under the residential disclosure and warranty rules. Start with the facts and identify which statute fits each issue.
Board Powers and Reasons for Discipline
Under Nevada Revised Statutes (NRS) 624.300, the Board can refuse renewal, limit the scope or dollar amount of work, suspend or revoke a license, issue a public reprimand and increase license security. It can order a licensee to correct a condition at the licensee’s expense, hire another licensee to do the corrective work, or pay the owner a specified sum for correction. It can also order repayment to the Residential Recovery Fund of amounts paid because of the licensee’s act or omission. Expiration or voluntary surrender of the license does not end the Board’s jurisdiction over an investigation or proceeding.
The ordinary administrative fine ceiling under subsection 1 is $10,000. For specifically listed violations under subsection 3(a), including over-limit bidding under NRS 624.3015(2) and license misuse under NRS 624.3014, the ceiling is $50,000 per violation. Subsection 3(b) has separate mandatory fine ranges for knowingly entering into a contract with an unlicensed contractor. Identify the actual offense and subsection before selecting a fine range.
| Facts | Discipline provision |
|---|---|
| Abandonment or refusal without legal excuse to prosecute work with reasonable diligence or comply with a written warranty | NRS 624.301 |
| Willful material departure from plans without the required consent, or willful disregard and violation of applicable state or local building laws | NRS 624.3011 |
| Diversion of money or property from the project or purpose for which it was received | NRS 624.3012(1) |
| Deliberate failure to pay for materials or services when due and the licensee can pay or has received sufficient payment for the work | NRS 624.3012(2) |
| Substandard workmanship or construction advertising without the required name and license number | NRS 624.3017 |
Apply the Criminal Diversion Threshold to the Money Diverted
NRS 624.750(4) applies when a person receives money to obtain or pay for services, labor, materials or equipment, willfully fails to use it for that purpose by failing to complete the work or pay those project costs, and wrongfully diverts the money to another use. Unless another statute provides a greater penalty, subsection 5 makes diversion of $1,000 or less a gross misdemeanor and diversion of more than $1,000 a Category E felony. Count the amount diverted. For a $6,500 draw where $3,500 was knowingly diverted to a personal loan instead of paying the subcontractor and supplier, the relevant amount is $3,500.
Give the Owner the Project Disclosures
Under NRS 624.600, a general building contractor gives written information to the owner with whom it contracts for a single-family residence. The statute also covers specified residential photovoltaic work on qualified multifamily affordable housing property. The information includes:
- The name, license number, business address and telephone number for all subcontractors the general building contractor has contracted with on the project and all persons furnishing $500 or more in material for use on the project.
- A warning that those parties may record a notice of lien under NRS 108.226.
- The Board-prescribed informational form regarding contractors and mechanics’ and materialmen’s liens.
On a covered Reno remodel, a supplier furnishing $450 in materials falls below the statutory threshold. A $620 trim supplier is included. The general building contractor also includes the electrical subcontractor it hired for $400 because the material threshold applies to suppliers. This disclosure is one duty of the general building contractor. A lien claimant still follows the claimant’s own notices and recording requirements under NRS Chapter 108.
Hand Over the New-Home Rights Notice and Warranty
NRS 624.602 requires a licensee completing a new single-family residence to provide the purchaser with a separate, single-page notice of the purchaser’s Chapter 624 rights, including the right to file a complaint under NRS 624.480 seeking Recovery Fund payment. The licensee also provides a written builder’s warranty. It must last at least one year from completion of the written punch list and must transfer to a subsequent purchaser. It covers home systems, workmanship, materials, contractor-installed appliances, fixtures, equipment and structural components, subject to separate warranties provided by manufacturers or installers for particular items. The written warranty leaves other contractual and legal warranties available.
For a house whose written punch list is completed on June 15, use June 15 to measure the minimum one-year warranty period. Keep the completion date and the purchaser’s disclosure with the warranty records.
Nevada contractor statutes, including NRS 624.300–.3017, 624.600, 624.602 and 624.750 · Board form rule, NAC 624.693
A contractor receives a $6,500 draw earmarked to pay a framing subcontractor and supplier. The contractor willfully leaves their bills unpaid and wrongfully uses $3,500 of the draw for a personal vehicle loan. Under NRS 624.750(4)–(5), how is the diversion classified, assuming no statute supplies a greater penalty?
A Category E felony, because the diverted amount exceeds $1,000
A gross misdemeanor, because it is the contractor's first offense
A civil breach of contract only, unless the project is abandoned
A misdemeanor, because the total project draw was under $10,000
When completing a new single-family residence for a purchaser, what must the builder provide under NRS 624.602?
Only a verbal walkthrough agreement and a copy of the city certificate of occupancy
A 6-month workmanship warranty attached to the closing escrow instructions
A list of subcontractors and a 90-day punch list waiver signed by the buyer
A separate single-page Chapter 624 rights disclosure (referencing NRS 624.480) and a written builder's warranty valid for at least 1 year from punch list completion
Match each Nevada Revised Statutes section to its primary regulatory requirement or penalty.
Match each item on the left with the correct item on the right
NRS 624.300
NRS 624.600
NRS 624.602
NRS 624.750
Under NRS 624.600, what minimum dollar value of materials furnished to the project requires the general building contractor to identify that supplier to the owner of a covered single-family residence? Enter the number only.
Type your answer below